| 11/6/2017 | 1 | 1 1843-PMUTL-DA1 Notice Name & Address of the Engineer.pdf |
| 11/8/2017 | 2 | 2 SMC4-1 Proposal for approval of Project Manager.pdf |
| 11/8/2017 | 3 | 3 SMC4-2 Schedule of some documents to prepare for the execution of the Project.PDF |
| 11/8/2017 | 4 | 4 SMC4-4 Fix the date of Ground Breaking Ceremony PK1.pdf |
| 10/31/2017 | 5 | 5 1579-PMUTL-DA1 Appointment of the Engineer.pdf |
| 11/16/2017 | 6 | 6 SMC4- 5 Notice on the Contractor s address.pdf |
| 11/17/2017 | 7 | 7 SMC4-6 Proposal for approval of Key Personnel.pdf |
| 11/17/2017 | 7 | 7- SMC4-6 Proposal for approval of Key Personnel.pdf |
| 11/20/2017 | 8 | 8 SMC4-7 Submission of Performance Security.pdf |
| 11/20/2017 | 8 | 8- SMC4-7 Submission of Performance Security.pdf |
| 11/22/2017 | 9 | 9 SMC4-9 Submission of Contract's License.PDF |
| 11/22/2017 | 9 | 9-SMC4-9 Submission of Contract's License.PDF |
| 11/23/2017 | 10 | 10 1436.2017-JICA-YL Review of Contract for PK1 & PK2.pdf |
| 11/23/2017 | 10 | 10-1436.2017-JICA-YL Review of Contract for PK1 & PK2.pdf |
| 11/29/2017 | 11 | 11 2251-PMUTL-DA1 Request for Review of Contract (2nd).pdf |
| 12/1/2017 | 12 | 12 SMC4- 12 Submission Quality Control Plan sửa.pdf |
| 11/25/2017 | 12 | 12 SMC4-12 Submission Quality Control Plan.pdf |
| 11/25/2017 | 13 | 13 SMC4- 11 Submission of SMCC-CIENCO4 JV's office and Accommodation for Staff Layout.pdf |
| 12/6/2017 | 14 | 14 SMC4-LT-02 Capacity Profile of Site Laboratary ( Las-XD668).pdf |
| 12/6/2017 | 14 | 14 SMC4-LT-2 Capacity Profile of Site Laboratary ( Las-XD668).pdf |
| 12/4/2017 | 15 | 15 SMC4- LC-13 Addtitional Geological Investtigation Plan.pdf |
| 12/4/2017 | 16 | 16 SMC4-LC-14 Submission of Project Health and Safety Plan.pdf |
| 12/4/2017 | 17 | 17 SMC4-LC-15 Tasks and Technical Options of Topographic Survey.pdf |
| 12/6/2017 | 18 | 18 1469.2017-JICA-YL Request Letters Ref 1706;2251PMUTL-DA1.pdf |
| 12/6/2017 | 18 | 18-1469.2017-JICA-YL Request Letters Ref 1706;2251PMUTL-DA1.pdf |
| 12/7/2017 | 19 | 19 SMC4- MS-01 Method statement of traffic Control for Additional Geological Investtigation.pdf |
| 12/7/2017 | 20 | 20 SMC4-WD-01 Working Drawing. General view and Girder arrangement of Main Bridge and off Ramp HQV-B 1st.pdf |
| 12/7/2017 | 20 | 20 SMC4-WD-1 Working Drawing. General view and Girder arrangement of Main Bridge and off Ramp HQV-B 1st.pdf |
| 12/7/2017 | 21 | 21 SMC4-MA-01 Capacity Profile of Batching Plant Asean.pdf |
| 12/7/2017 | 21 | 21 SMC4-MA-1 Capacity Profile of Batching Plant Asean.pdf |
| 12/7/2017 | 22 | 22 SMC4-MA-02 Capacity Profile of Bentonite Manufaturer-Truong Thinh.pdf |
| 12/7/2017 | 22 | 22 SMC4-MA-2 Capacity Profile of Bentonite Manufaturer-Truong Thinh.pdf |
| 12/8/2017 | 23 | 23 LC-0016-17 Replacement of Contractor's key Personnel.pdf |
| 12/8/2017 | 23 | 23 LC-16 Replacement of Contractor's key Personnel.pdf |
| 12/26/2017 | 23 | 23 SMC4-LC-16 Replacement of Contractor's key Personnel(new).pdf |
| 12/8/2017 | 24 | 24 SMC4-LT-03 Laboratory LAS-XD595 of Viet Delta Consultancy Joint Stock Company.pdf |
| 12/8/2017 | 24 | 24 SMC4-LT-3 Laboratory LAS-XD595 of Viet Delta Consultancy Joint Stock Company.pdf |
| 12/11/2017 | 25 | 25 SMC4-LC-17 Hand over GPS point and secondary tranverse benchmark for survey work.pdf |
| 12/11/2017 | 26 | 26 LT-0001-17 the list of apparatuses supplied for Site Laboratory ( LAS-XD 668).pdf |
| 12/11/2017 | 26 | 26 LT-01 The list of apparatuses supplied for Site Laboratory ( LAS-XD 668).pdf |
| 1/9/2018 | 26 | 26 SMC4-LT-01 Apparatuses supplied for Site Laboratory ( LAS-XD 668)(New).pdf |
| 1/9/2018 | 26 | 26 SMC4-LT-1 Apparatuses supplied for Site Laboratory ( LAS-XD 668)(New).pdf |
| 12/12/2017 | 27 | 27 SMC4-WD-02 Term of reference (TOR) for additional geological investigation.pdf |
| 12/12/2017 | 27 | 27 SMC4-WD-2 Term of reference (TOR) for additional geological investigation.pdf |
| 12/12/2017 | 28 | 28 SMC4-WD-03 Working drawing of Relocation of Existing Ultilities- Estimate quantity.pdf |
| 12/12/2017 | 28 | 28 SMC4-WD-3 Working drawing of Relocation of Existing Ultilities- Estimate quantity.pdf |
| 12/12/2017 | 29 | 29- MOT- Hand over of the GPS Points and the Secondary Control Points of the HRR3.pdf |
| 12/13/2017 | 30 | 30 SMC4-LO-02 Notice on Bank account for receiving Contract Payment of package 1.pdf |
| 12/13/2017 | 30 | 30 SMC4-LO-2 Notice on Bank account for receiving Contract Payment of package 1.pdf |
| 12/13/2017 | 31 | 31 SMC4-LP-01 Notice on the name of beneficiary of package 1.PDF |
| 12/13/2017 | 31 | 31 SMC4-LP-1 Notice on the name of beneficiary of package 1.PDF |
| 12/14/2017 | 32 | 32 2485-BQLDATL-DA1 Approval of Nominated Sub-Contractors for Execution of Provisional Sum Items PK1.pdf |
| 12/14/2017 | 32 | 32-2485-BQLDATL-DA1 Approval of Nominated Sub-Contractors for Execution of Provisional Sum Items PK1.pdf |
| 12/14/2017 | 33 | 33 SMC4-LP-03 Submission of Advance Payment Security.pdf |
| 12/14/2017 | 33 | 33 SMC4-LP-3 Submission of Advance Payment Security.pdf |
| 12/14/2017 | 34 | 34 SMC4-LP-02 Issuance of Power of Attorney of the Contractor's representative.pdf |
| 12/14/2017 | 34 | 34 SMC4-LP-2 Issuance of Power of Attorney of the Contractor's representative.pdf |
| 12/14/2017 | 35 | 35 SMC4-LP-04 Provide Evidence of Employer's Financial arrangement.pdf |
| 12/14/2017 | 35 | 35 SMC4-LP-4 Provide Evidence of Employer's Financial arrangement.pdf |
| 12/14/2017 | 36 | 36 SMC4-LC-18 Working drawing design Contractor.pdf |
| 1/9/2018 | 37 | 37 SMC4-LT-04 Capacity Profile of Site Laboratory (Las-XD668)(New).pdf |
| 12/14/2017 | 37 | 37 SMC4-LT-04 Capacity Profile of Site Laboratory (Las-XD668).pdf |
| 1/9/2018 | 37 | 37 SMC4-LT-4 Capacity Profile of Site Laboratory (Las-XD668)(New).pdf |
| 12/14/2017 | 37 | 37 SMC4-LT-4 Capacity Profile of Site Laboratory (Las-XD668).pdf |
| 12/20/2017 | 38 | 38 SMC4-LC-19 Interim payment Certificate for Advance payment(N).pdf |
| 12/18/2017 | 39 | 39 SMC4-LC-20 Tasks and Technical options of Topographic Survey (2nd ).pdf |
| 12/18/2017 | 40 | 40 SMC4-LC-21 Submission of Evidence of Insurance.pdf |
| 12/20/2017 | 41 | 41 SMC4-LC-22 Manpower and equipment mobilization of project center for geological and topographic investigations.pdf |
| 12/21/2017 | 42 | 42 SMC4-LC-23 Power of Attorney for Contractor's Superintendence (Principal Personnel).pdf |
| 12/21/2017 | 43 | 43 SMC4-LC-24 Capacity profile of Joint Venture of Technical and Natural Resource Co., Ltd and Hanoi Environment Investment JSC for environment monitoring work.pdf |
| 12/21/2017 | 44 | 44 SMC4-LC-26 Approval of Environmental Monitoring plan at pre-construction phase.pdf |
| 12/21/2017 | 45 | 45 SMC4-LP-05 Notice again on Bank Account for Receiving contract payment of package 1.pdf |
| 12/21/2017 | 45 | 45 SMC4-LP-5 Notice again on Bank Account for Receiving contract payment of package 1.pdf |
| 12/22/2017 | 46 | 46 SMC4-MA-03 Capacity profile of 190 steel pipes ,Sonic Tube and Tien Lam.pdf |
| 12/22/2017 | 46 | 46 SMC4-MA-3 Capacity profile of 190 steel pipes ,Sonic Tube and Tien Lam.pdf |
| 12/22/2017 | 47 | 47 SMC4-LC-25 Quality control plan(2nd Submission).pdf |
| 12/25/2017 | 48 | 48 SMC4-LT-05 Capacity profile of Laboratory LAS-XD595 of Viet Delta Consultancy JSC.pdf |
| 12/25/2017 | 48 | 48 SMC4-LT-5 Capacity profile of Laboratory LAS-XD595 of Viet Delta Consultancy JSC.pdf |
| 12/25/2017 | 49 | 49 SMC4-LT-06 Technical of Crushed stone quarry,yellow sand and water for ASEAN.pdf |
| 12/25/2017 | 49 | 49 SMC4-LT-6 Technical of Crushed stone quarry,yellow sand and water for ASEAN.pdf |
| 12/26/2017 | 50 | 50 SMC4-LC-27 Capacity profile of infrastructure JSC for Protection and Relocation of Existing Utilities (1).pdf |
| 12/26/2017 | 51 | 51 SMC4-LP-06 Submission of Evidence of insurance (2nd).pdf |
| 12/26/2017 | 51 | 51 SMC4-LP-6 Submission of Evidence of insurance (2nd).pdf |
| 12/26/2017 | 52 | 52 SMC4-LC-28 Withdraw the letter power of Attorney for contractor's Superintendence (principle personnel).pdf |
| 12/26/2017 | 53 | 53 SMC4-LC-29 Project Health and Safety plan (2nd).pdf |
| 12/26/2017 | 54 | 54 2718 BQLDATL-DA1 Approval for Replacement of Key personnel(Quality control manager and safety manager).pdf |
| 12/27/2017 | 55 | 55 SMC4-LC-30 Capacity profile of Thang Long Building and Experiment consulting JSC for test on concrete piles and rotation steel piles.pdf |
| 12/28/2017 | 56 | 56 SMC4-MA-4 Capacity profile of batching Plant Asean (2nd submission).pdf |
| 12/28/2017 | 57 | 57 SMC4-MA-5 Capacity profile of Nghi Son cement coporation, Cement manufacturer and Construction Material JSC of Center Region, Cement Supplier.pdf |
| 12/28/2017 | 58 | 58 SMC4-MA-06 Capacity profile of Truong Thinh Co., Ltd (2nd submission).pdf |
| 12/28/2017 | 58 | 58 SMC4-MA-6 Capacity profile of Truong Thinh Co., Ltd (2nd submission).pdf |
| 12/28/2017 | 59 | 59 SMC4-LC-31 Notice on New year 2018 holiday Schedule of the Contractor.pdf |
| 12/29/2017 | 60 | 60 2693-PMUTL-DA1 The Employer's Financial Arrangement.pdf |
| 12/29/2017 | 61 | 61 Minute of Handing over Benchmark for coordination and Elevation.pdf |
| 7/25/2018 | 62 | 62 SMC4-LC-32 Deputy Quality control manager and Deputy safety manager.pdf |
| 12/29/2017 | 63 | 63 SMC4-MA-7 Capacity profile of BASF Vietnam Ltd., Admixture manufacturer and Hiep An Trading & construction JSC,BASF's admixture Supplier.pdf |
| 12/29/2017 | 64 | 64 SMC4-LC-33-Capacity profile of Working drawing design contractor (2nd ).pdf |
| 12/30/2017 | 65 | 65 SMC4-LT-07 Capacity profile of laboratories of institute of Transport Science and Technology (ITST).pdf |
| 12/30/2017 | 65 | 65 SMC4-LT-7Capacity profile of laboratories of institute of Transport Science and Technology (ITST).pdf |
| 12/30/2017 | 66 | 66 SMC4-LT-08 Capacity profile of laboratories of Vietnam institute for Building science and technology (IBST).pdf |
| 12/30/2017 | 66 | 66 SMC4-LT-8 Capacity profile of laboratories of Vietnam institute for Building science and technology (IBST).pdf |
| 12/30/2017 | 67 | 67 SMC4-MS-03 Additional geological investigation plan (2 nd ).PDF |
| 12/30/2017 | 67 | 67 SMC4-MS-3 Additional geological investigation plan (2 nd ).PDF |
| 1/2/2018 | 68 | 68 Addendum No.1_PK1_full.pdf |
| 1/3/2018 | 69 | 69 SMC4-LP-07 Details of SMCC's Managing Executive officer.pdf |
| 1/3/2018 | 69 | 69 SMC4-LP-7 Details of SMCC's Managing Executive officer.pdf |
| 1/3/2018 | 70 | 70 SMC4-LC-34 Withdraw the letters SMC4-LC-0022 and SMC4-0011.pdf |
| 1/3/2018 | 71 | 71 SMC4-LP-08 Expedition of Additional Geological Investigation.pdf |
| 1/3/2018 | 71 | 71 SMC4-LP-8 Expedition of Additional Geological Investigation.pdf |
| 1/4/2018 | 72 | 72 SMC4-MA-8 Capacity profile of Batching plant Transmeco.pdf |
| 1/4/2018 | 73 | 73 SMC4-WD-04 Technical Clarification to the Employer's Drawing.pdf |
| 1/4/2018 | 73 | 73 SMC4-WD-4 Technical Clarification to the Employer's Drawing.pdf |
| 1/4/2018 | 74 | 74 SMC4-MS-04 Method statement of Bored pile Diameter D=1.2M.pdf |
| 1/4/2018 | 74 | 74 SMC4-MS-4 Method statement of Bored pile Diameter D=1.2M.pdf |
| 1/4/2018 | 75 | 75 SMC4-LC-35 Capacity profile of TSP service and trading construction JSC for Traffic control.pdf |
| 1/5/2018 | 76 | 76 SMC4-MA-10 Capacity of Vietnam-Japan Steel and Thien Ma JSC.pdf |
| 1/5/2018 | 77 | 77 SMC4-LC-36 Environment Management plan.pdf |
| 1/5/2018 | 78 | 78 SMC4-MA-09 Capacity of Vietnam Germany steel and VPA Group.pdf |
| 1/5/2018 | 78 | 78 SMC4-MA-9 Capacity of Vietnam Germany steel and VPA Group.pdf |
| 1/8/2018 | 79 | 79 SMC4-MS-02 General traffic control plan for Construction project.pdf |
| 1/8/2018 | 79 | 79 SMC4-MS-2 General traffic control plan for Construction project.pdf |
| 1/9/2018 | 80 | 80 SMC4-LP-09 Method of Traffic control and Girder Transportation(N.pdf |
| 1/9/2018 | 80 | 80 SMC4-LP-9 Method of Traffic control and Girder Transportation(N.pdf |
| 1/8/2018 | 81 | 81 104-BQLDATL Meeting to review the project implementation.pdf |
| 1/8/2018 | 82 | 82 SMC4-LC-0037 Clarification of Drainage system design drawings and Highway.pdf |
| 1/8/2018 | 82 | 82 SMC4-LC-37 Clarification of Drainage system design drawings and Highway.pdf |
| 1/9/2018 | 83 | 83 SMC4-38 manpower and equipment mobilization of the Team for geological and topographic.pdf |
| 1/9/2018 | 84 | 84 SMC4-39 Manpower and equipment mobilization of the team 1 for bored pile and Super T girder.pdf |
| 1/9/2018 | 85 | 85 SMC4-LC-040 Capacity profile of Subcontractor 479 JSC.pdf |
| 1/9/2018 | 85 | 85 SMC4-LC-40 Capacity profile of Subcontractor 479 JSC.pdf |
| 1/9/2018 | 86 | 86 SMC4-LT-09 Capacity profile of Laboratory LAS-XD71-VILAS-932.pdf |
| 1/10/2018 | 87 | 87 SMC4-MA-11 Capacity profile of Manufacturer and supplier of Sonic Tube (2nd Submission).pdf |
| 1/11/2018 | 88 | 88 SMC4-RP-01 GPS Benchmarks Survey Report.pdf |
| 1/11/2018 | 88 | 88 SMC4-RP-1 GPS Benchmarks Survey Report.pdf |
| 1/11/2018 | 89 | 89 SMC4-RP-02 Benchmark Analytic Grade 1 Report.pdf |
| 1/11/2018 | 89 | 89 SMC4-RP-2 Benchmark Analytic Grade 1 Report.pdf |
| 1/11/2018 | 90 | 90 SMC4-LC-41 Gradation for Coarse aggregate for Concrete Class A.pdf |
| 1/11/2018 | 91 | 91 149 GM-BQLDATL Meeting Invitation on 15 Jan.2018.pdf |
| 1/13/2018 | 92 | 92 SMC4-MS-05 Method statement of Arrangement of Temporary facilities on site.pdf |
| 1/13/2018 | 92 | 92 SMC4-MS-5 Method statement of Arrangement of Temporary facilities on site.pdf |
| 1/13/2018 | 93 | 93 SMC4-LC-42 Geological and topographic investigations(2nd).pdf |
| 1/15/2018 | 94 | 94 SMC4-LT-10 Capacity profile of Laboratories of ITST(2nd).pdf |
| 1/15/2018 | 95 | 95 SMC4-MA-12 Technical Proofile of crushed stone quarry,Yellow sand and water for Asean Batching(2nd).pdf |
| 1/15/2018 | 96 | 96-SMC4-LT-11 Capacity profile of Laboratories of IBST(2nd).pdf |
| 1/15/2018 | 97 | 97 SMC4-MS-06 General Traffic control plan for construction project(2nd).pdf |
| 1/15/2018 | 97 | 97 SMC4-MS-6 General Traffic control plan for construction project(2nd).pdf |
| 1/16/2018 | 98 | 98 SMC4-LP-10 Clarification on the removal of cable line of Widending Project at Pier P26 and P39.pdf |
| 1/16/2018 | 99 | 99 SMC4-MA-13 Capacity profile of cement Manufacturer and Supplier (2nd ).pdf |
| 1/16/2018 | 100 | 100 SMC4-SC-01 Capacity profile of the Subcontractor 482 JSC.pdf |
| 1/16/2018 | 100 | 100 SMC4-SC-1 Capacity profile of the Subcontractor 482 JSC.pdf |
| 1/16/2018 | 101 | 101 SMC4-SC-02 Capacity profile of the Subcontractor Construction and Trading JSC 423.pdf |
| 1/16/2018 | 101 | 101 SMC4-SC-2 Capacity profile of the Subcontractor Construction and Trading JSC 423.pdf |
| 1/17/2018 | 102 | 102 SMC4-MS-10 Proposal for approval of additional geological investigation plan (3rd ).pdf |
| 1/17/2018 | 103 | 103 SMC4-SC-03 Capacity profile of the Subcontractor 475 JSC.pdf |
| 1/17/2018 | 103 | 103 SMC4-SC-3 Capacity profile of the Subcontractor 475 JSC.pdf |
| 1/17/2018 | 104 | 104 SMC4-SC-04 Document of manpower and equipment mobilization of the sub-contractor 482 JSC for construction from P32 to P35.pdf |
| 1/17/2018 | 104 | 104 SMC4-SC-4 Document of manpower and equipment mobilization of the sub-contractor 482 JSC for construction from P32 to P35.pdf |
| 1/18/2018 | 105 | 105 SMC4-SC-05 Capacity Profile of Thang Long Bridge No.7 JSC.pdf |
| 1/18/2018 | 105 | 105 SMC4-SC-5 Capacity Profile of Thang Long Bridge No.7 JSC.pdf |
| 1/16/2018 | 106 | 106 SMC4-MS-07 Method statement for coring and concrete testing at pile tip.pdf |
| 1/16/2018 | 106 | 106 SMC4-MS-7 Method statement for coring and concrete testing at pile tip.pdf |
| 1/16/2018 | 107 | 107 SMC4-MS-08 Method Statement for ultra sonic testing of piles.pdf |
| 1/16/2018 | 107 | 107 SMC4-MS-8 Method Statement for ultra sonic testing of piles.pdf |
| 1/18/2018 | 108 | 108 SMC4-MS-09 Method statement for trial excavation of bored pile.pdf |
| 1/18/2018 | 108 | 108 SMC4-MS-9 Method statement for trial excavation of bored pile.pdf |
| 1/17/2018 | 109 | 109 SMC4-MS-11 Traffic control method statement for additional soil investigation (2nd ).pdf |
| 1/18/2018 | 110 | 110 SMC4-MA-14 Capacity Profile of Manufacturer and Supplier for material for traffic control item-TSP Service and Trading construction JSC.pdf |
| 1/18/2018 | 111 | 111 SMC4-LC-43 Manpower and Equipment Mobilization for construcion (P13 to P22).pdf |
| 1/18/2018 | 112 | 112 SMC4-LC-44 Document of manpower and equipment mobilization of the team 3 for construction from P23 to P27.pdf |
| 1/18/2018 | 113 | 113 Meeting Minutes (Agreement on Implementation of Additional geological investigation).pdf |
| 1/19/2018 | 114 | 114 SMC4-LT-13 Capacity profile of laboratory LAS-XD 668 (2nd submission).pdf |
| 1/19/2018 | 115 | 115 SMC4-MA-16 Approval of trial mixing work of concrete proportions class , E and Y.pdf |
| 1/19/2018 | 116 | 116 SMC4-MA-15 Capacity profile of Mighty Admixture Manufacturer and Supplier.pdf |
| 1/19/2018 | 117 | 117 SMC4-MC-1-18-Interim Payment Certificate Form.pdf |
| 1/19/2018 | 118 | 118 SMC4-LT-12 Capacity proffile of LAS-XD 595 of Viet Delta Consultancy JSC (3rd.pdf |
| 1/19/2018 | 119 | 119 SMC4-LC-45 Clarification location of borehole log in Contract Documents.pdf |
| 1/19/2018 | 120 | 120 SMC4-MS-12 General Traffic control plan for Construction Project.pdf |
| 1/19/2018 | 121 | 121 264-BQLDATL-DA1 Alternative of Fencing for Traffic control.pdf |
| 1/19/2018 | 122 | 122 SMC4-LP-12 Announcement of Budget plan for the year 2018.pdf |
| 1/20/2018 | 123 | 123 SMC4-SC 06 Document of Vinh Quynh Disposal Area.pdf |
| 1/20/2018 | 123 | 123 SMC4-SC-6-18 Document of Vinh Quynh Disposal Area.pdf |
| 1/22/2018 | 124 | 124 SMC4-LC-46 Notice on Tet Holiday Schedule of the contractor.pdf |
| 1/22/2018 | 125 | 125 SMC4-LP-13 Request Clarifying items Relocation of Utilities & Demolition overlapped by two projects.pdf |
| 1/22/2018 | 126 | 126 SMC4-MA-17 Capacity profile of Nghi Son cement manufacturer and supplier (3rd).pdf |
| 1/22/2018 | 127 | 127 SMC4-MA-18 Capacity profile of batching plant Transmeco (2nd submission).pdf |
| 1/23/2018 | 128 | 128 SMC4-MS-13 Method statement for grouting of sonic tube of bored pile.pdf |
| 1/23/2018 | 128 | 128 SMC4-MS-13-18-Method statement for grouting of sonic tube of bored pile.pdf |
| 1/23/2018 | 129 | 129 196 TB-BQLDATL Conclusions by PMU Thang Long on implementation progress & Schedule of PK1.pdf |
| 1/24/2018 | 130 | 130 274-TB-BQLDATL Conclusions given by PMUTL at Meeting on reviewing of implementation of MD-STL Section.pdf |
| 1/24/2018 | 131 | 131 SMC4-LP-14 Clarify completion and handing over schedule of Ring Road No.3 Widening Project - MD-STL Section.pdf |
| 1/25/2018 | 132 | 132 SMC4-MA-19 Technical profile of crushed stone quarry, yellow sand and water for ASEAn batching plant (3rd Sub.).pdf |
| 1/25/2018 | 132 | 132-MA-19 Technical profile of crushed stone quarry, yellow sand and water for ASEAn batching plant (3rd Sub.).pdf |
| 1/25/2018 | 133 | 133 SMC4-MA-20 Capacity profile of reinforcing steel manufacturer and supplier VGS-VPA (2nd Sub.).pdf |
| 1/25/2018 | 133 | 133-MA-20 Capacity profile of reinforcing steel manufacturer and supplier VGS-VPA (2nd Sub.).pdf |
| 1/25/2018 | 134 | 134 SMC4-LC-47 Adjustment of Plan and Schedule of additional geological investigation.pdf |
| 1/25/2018 | 135 | 135 SMC4-LC-48 Form of construction diary.pdf |
| 1/25/2018 | 135 | 135-LC-48 Form of construction diary.pdf |
| 1/26/2018 | 136 | 136 SMC4-LC-49 Adjusted schedule, site organization layout and document of additional manpower and equipment for soil investigation.pdf |
| 1/26/2018 | 137 | 137 353-BQLDATL-DA1 Main Acceptance Procedures during Construction Period.pdf |
| 1/26/2018 | 138 | 138 SMC4-LC-50 Manpower and equipment mobilization of Team 4 for abutment construction from A1 to P5.pdf |
| 1/26/2018 | 139 | 139 SMC4-RP-03 Report of environmental monitoring at pre-construction phase.pdf |
| 1/26/2018 | 139 | 139 SMC4-RP-3 Report of environmental monitoring at pre-construction phase.pdf |
| 1/27/2018 | 140 | 140 SMC4-LT-14 Capacity profile of Laboratory LAS-XD71-VILAS- 932 (2nd submission).pdf |
| 1/27/2018 | 141 | 141 SMC4-MA-21 Technical profile of crushed stone quarry, yellow Sand & water -TRANSMECO Batching Plant.pdf |
| 1/30/2018 | 142 | 142 SMC4-LC-51 Environmental Management Plan (2nd.pdf |
| 1/30/2018 | 143 | 143 SMC4-MA-23 Adjust Document of Mix design concrete class A,E & Y in accordance with the material test result.pdf |
| 1/30/2018 | 144 | 144 SMC4-RP-4 Report on checking benchmark system GPS of Packages 01,02(n).pdf |
| 1/30/2018 | 145 | 145 SMC4-LC-52 Capacity profile of working drawing design Contractor (3rd).pdf |
| 1/30/2018 | 146 | 146 SMC4-MA-22 Coarse aggregate for design of concrete class A.pdf |
| 2/1/2018 | 147 | 147 398-PMUTL-DA1 The Employer's Financial Arrangement (2018 Budgdet Plan).pdf |
| 2/1/2018 | 148 | 148 SMC4-MA-24 Capacity profile of Transport Materials Equipment Trading JSC-supplier for PC strand.pdf |
| 2/2/2018 | 149 | 149 SMC4-MA-25 Report on testing results of Bentonite Material for Bored Pile.pdf |
| 2/5/2018 | 150 | 150 SMC4-LC-53 Form of Construction Diary (2nd Sub).pdf |
| 2/5/2018 | 151 | 151 SMC4-RP-05 Report on actual condition of Existing utilities (on ground)-Step 1.pdf |
| 2/5/2018 | 151 | 151 SMC4-RP-5 Report on actual condition of Existing utilities (on ground)-Step 1.pdf |
| 2/6/2018 | 152 | 152 482-BQLDATL-KTTD Construction Organization and Strengthening of Traffic Safety,Labor safety and Environmental hygiene on the Site.pdf |
| 2/6/2018 | 153 | 153 SMC4-LC-55 Request for the clarification for the location of borehole log in contract documents(2nd).pdf |
| 5/15/2018 | 154 | 154 SMC4-MA-25A Report on testing results of Sonic tube material for Bored pile.pdf |
| 2/6/2018 | 155 | 155 SMC4-LC-54 Construction plan of Contractor pk1 and some unclear matters need clarifying with HRR3 Widening Project.pdf |
| 2/7/2018 | 156 | 156 SMC4-LC-58 Locations and Details design of Project information Signs Board.pdf |
| 2/8/2018 | 157 | 157 SMC4-LC-56 Request for the Clarifications of the Contract Drawings.pdf |
| 2/8/2018 | 158 | 158 SMC4-LC-57 Clarifications of Clearance of urban road under bridge in the Contract Drawings.pdf |
| 2/8/2018 | 159 | 159 SMC4-LC-59 Withdrawal of the letter SMC4-RP-0005-2018 Date 5.2.2018.pdf |
| 2/8/2018 | 160 | 160 SMC4-LC-60 Confirmation of actual Existing Utilities' Survey Date (on ground)-step 1.pdf |
| 2/9/2018 | 161 | 161 550-PMUTL-DA1 Preparation of construction plan and Schedule for Package 1 and Package 2.pdf |
| 2/9/2018 | 162 | 162 SMC4-LC-61 Confirmation of Actual Existing Trees; Survey Data P4 to P16 (Km0+487.9-Km0+967.9).pdf |
| 4/16/2018 | 163 | 163 SMC4-MA-27 Capacity profile of Reinforcing steel manufacturer Hoa Phat Steel One Member Ltd and Kyoei Steel VietNam Company.pdf |
| 2/9/2018 | 164 | 164 SMC4-MA-26 Mix Proportion for Trial Mix at Batching Plant Asean (Class B1,C1,C3,C4,D and G) (1st).pdf |
| 2/9/2018 | 165 | 165 SMC4-LT-15 Inspection Minute of Laboratory LAS-XD 71-VILAS 932.pdf |
| 2/10/2018 | 166 | 166 SMC4-MA-28 Report on testing results of Basf Admixture for cement concrete.pdf |
| 2/10/2018 | 167 | 167 SMC4-MA-29 R3,R7 Concrete compressive Strength test Result of Concrete class A, E & Y for Asean Batching plant Mixes at Laboratory.pdf |
| 2/22/2018 | 168 | 168 SMC4-SC-7 Supplement documents for Capacity Profile of Thang Long Bridge No.7JSC.pdf |
| 4/12/2018 | 169 | 169 SMC4-LC-62 Supplemental Manpower and equipment Mobilization document of Team 3(2nd ).pdf |
| 2/22/2018 | 170 | 170 SMC4-LC-63 Supplemental Manpower and equipment Mobilization document of Team 1(2nd ).pdf |
| 2/23/2018 | 171 | 171 SMC4-MA-30 Manufacturer and Supplier of PC Strand Guizhou Wire Rope Incorporated company-TRAMECO.pdf |
| 2/23/2018 | 172 | 172 SMC4-LC-64 Manpower and equipment by team for Koden Test of Bored Pile.pdf |
| 2/26/2018 | 173 | 173 SMC4-LC-65 Construction Schedule of package 1.pdf |
| 2/27/2018 | 174 | 174 SMC4-LP-11 Provision of Calculation Sheet document.pdf |
| 2/27/2018 | 175 | 175 SMC4-LC-67 Additional Request for Clarifications of Contract Drawings.pdf |
| 2/28/2018 | 176 | 176 SMC4-LC-66 Supplemental manpower and equipment mobilization of team 2 (2nd ).pdf |
| 2/28/2018 | 177 | 177 SMC4-MC-02 Interim Payment Certificate Form (2nd Submission).pdf |
| 3/1/2018 | 178 | 178 SMC4-MA-31 Report on testing results of Crushed Stone,Yellow Sand and Water for Batching Plant ASEAN.pdf |
| 3/16/2018 | 179 | 179 SMC4-LC-68 Supplemental Manpower and equipment mobilization document of Team 4(2nd ).pdf |
| 3/3/2018 | 180 | 180 SMC4-SC-08 Proposal for document of Nguyen Khe Disposal site.pdf |
| 3/3/2018 | 181 | 181 SMC4-SC-09 Supplement document of Construction and Trading JSC 423 Capacity Profile.pdf |
| 3/3/2018 | 182 | 182 SMC4-SC-10 Supplement document of Joint Stock Company 479 Capacity Profile.pdf |
| 3/3/2018 | 183 | 183 SMC4-MA-32 Report on testing results of Cement Nghi Son.pdf |
| 3/5/2018 | 184 | 184 SMC4-RP-06 Report on Environmental Monitoring at Pre-Construction Phase (2nd).pdf |
| 3/7/2018 | 185 | 185 SMC4-MA-33 Report on trial mix of concrete class A of Asean Batching Plant mixed at Laboratory.pdf |
| 3/7/2018 | 186 | 186 SMC4-LC-69 Cutting and Pruning Trees from P4 To P16 (Km0+487.9-Km0+967.9).pdf |
| 3/9/2018 | 187 | 187 SMC4-LC-70 Notice of Leave for our Key Personnel (Project Manager.pdf |
| 4/6/2018 | 188 | 188 SMC4-MA-34 Capacity profile of Manufacturer and Supplier for traffic control material (TSP)(2nd ).pdf |
| 3/12/2018 | 189 | 189 SMC4-MA-35 Technical profile of Crushed Stone quarry,Yellow sand and water for TRANSMECO Batching Plant (2nd).pdf |
| 3/12/2018 | 190 | 190 SMC4-LC-71 Notice for Location of Fabrication Yard of Super T girder No.1.pdf |
| 4/9/2018 | 191 | 191 SMC4-LC-72 Proposal for approval of Project information Signs(2 nd Submission).pdf |
| 3/13/2018 | 192 | 192 119-GM-BQLCTGT Invitation-Site inspection & Survey of water transmission pipeline D800 and others existing under embankment of Pham Van Dong Road.pdf |
| 3/13/2018 | 192 | 192-119-GM-BQLCTGT Invitation-Site inspection & Survey of water transmission pipeline D800 and others existing under embankment of Pham Van Dong Road.pdf |
| 3/13/2018 | 193 | 193 843-GM-BQLDA1 Meeting Invitation-Implementation & Construction of PK1 & PK2.pdf |
| 3/13/2018 | 193 | 193-843-GM-BQLDA1 Meeting Invitation-Implementation & Construction of PK1 & PK2.pdf |
| 3/14/2018 | 194 | 194 SMC4-MA-36 Grout Material used for Sonic tube and PC.pdf |
| 3/14/2018 | 195 | 195 SMC4-MA-37 Capacity profile of reinforcing steel manufacturer & supplier (vietnam italy steel JSC; VPA Group JSC).pdf |
| 3/14/2018 | 196 | 196 SMC4-SC-11 Manpower and equipment mobilization of the sub-contractor TSP for Traffic Control.pdf |
| 3/14/2018 | 197 | 197 SMC4-MA-38 Capacity profile of Dong-il steel MFG.Co & Vinh Hung JSC (PC Strand Manufacturer & Supplier).pdf |
| 3/14/2018 | 198 | 198-867-GM-BQLDATL-Invitation- Implementation and construction of PK1 & Pk2.pdf |
| 3/15/2018 | 199 | 199 SMC4-LC-73 Terms of Reference and cost Estimate for Environmental Monitoring Item.pdf |
| 3/16/2018 | 200 | 200 SMC4-SC-12 Mobilization of Manpower & equipment by the Infrastructure JSC for Protection & Relocation of Existing Utilites works.pdf |
| 3/15/2018 | 201 | 201 SMC4-LC-74 Proposals on Steel plate in girder, for Grading and Bearing pad.pdf |
| 3/16/2018 | 202 | 202 SMC4-LC-75 Manpower and Equipment Mobilization document of ASEAN Batching plant for concrete supplying.pdf |
| 3/19/2018 | 203 | 203 SMC4-LC-076 Report on the affected area of the existing water supply D800mm during construction of Viaduct.pdf |
| 3/19/2018 | 203 | 203 SMC4-LC-76 Report on the affected area of the existing water supply D800mm during construction of Viaduct.pdf |
| 3/19/2018 | 204 | 204 SMC4-MA-39 capacity Profile of North Binh Minh Plastics Co.,Ltd, & Tien Lam Material JSC-PVC pipe material Manufacturer & supplier .pdf |
| 3/19/2018 | 205 | 205 SMC4-RP-07 Report on additional geoglgical investigation stage 1.pdf |
| 4/3/2018 | 206 | 206 SMC4-LC-0079 Proposal for approval of Contractor's Programme.pdf |
| 4/3/2018 | 206 | 206 SMC4-LC-79 Proposal for approval of Contractor's Programme.pdf |
| 3/21/2018 | 207 | 207 SMC4-WD-0007 Proposal for Approval of General View of Main Bridge & Ramp HQV-B (2nd).pdf |
| 3/21/2018 | 207 | 207 SMC4-WD-0007 Proposal for Approval of General View of Main Bridge and Ramp HQV-B (2nd).pdf |
| 3/21/2018 | 207 | 207 SMC4-WD-07 Proposal for Approval of General View of Main Bridge and Ramp HQV-B (2nd).pdf |
| 3/21/2018 | 208 | 208 SMC4-WD-06 Working drawing of Cast-in-place concrete pile for piers P22, P31.pdf |
| 3/21/2018 | 209 | 209 SMC4-LC-0078 Adjustment of Coupler Position & Rebar Length of Super-T Girder for Crossbeams.pdf |
| 3/21/2018 | 209 | 209 SMC4-LC-78 Adjustment of Coupler Position & Rebar Length of Super-T Girder for Crossbeams.pdf |
| 3/21/2018 | 210 | 210 SMC4-LC-0077 Calculation Sheet for Soil Bearing capacity of bored pile and pre-cast pile based on additional Geological investigation report.pdf |
| 3/21/2018 | 210 | 210 SMC4-LC-77 Calculation Sheet for Soil Bearing capacity of bored pile and pre-cast pile based on additional Geological investigation report.pdf |
| 3/22/2018 | 211 | 211 SMC4-MS-0014 Method statement for Trial Excavation of Bored Pile (2 nd).PDF |
| 3/22/2018 | 211 | 211 SMC4-MS-14 Method statement for Trial Excavation of Bored Pile (2 nd).PDF |
| 3/19/2018 | 212 | 212 920-GM-BQLDATL-Meeting Invitation- Implementation and construction of PK1 & Pk2.pdf |
| 3/19/2018 | 212 | 212-920-GM-BQLDATL-Meeting Invitation- Implementation and construction of PK1 & Pk2.pdf |
| 3/22/2018 | 213 | 213 SMC4-MS-15 Method statement for Production of Super T girder.pdf |
| 3/13/2018 | 214 | 214 831-PMUTL-DA1 Implementation of Environmental Monitoring in Package 1 and Package 2.pdf |
| 3/13/2018 | 214 | 214-831-PMUTL-DA1 Implementation of Environmental Monitoring in Package 1 and Package 2.pdf |
| 3/22/2018 | 215 | 215 Site Minutes 20.03.2018.pdf |
| 3/22/2018 | 215 | 215-Site Minutes 20.03.2018.pdf |
| 3/22/2018 | 216 | 216 962-PMUTL-DA6-Construction Diary.pdf |
| 3/22/2018 | 216 | 216-962-PMUTL-DA6-Construction Diary.pdf |
| 3/24/2018 | 217 | 217 SMC4-MS-0016 Method Statement of Bored Pile Diameter D=1.2m(2nd).pdf |
| 3/24/2018 | 217 | 217 SMC4-MS-16 Method Statement of Bored Pile Diameter D=1.2m(2nd).pdf |
| 4/5/2018 | 218 | 218 - SMC4-MA-0040 Report on test Result of Reinforcing Steel of Vietnam Germany Steel Mill JSC (VGS).pdf |
| 3/24/2018 | 218 | 218 SMC4-MA-0040 Report on test Result of Reinforcing Steel of Vietnam Germany Steel Mill JSC (VGS).pdf |
| 3/24/2018 | 218 | 218 SMC4-MA-40 Report on test Result of Reinforcing Steel of Vietnam Germany Steel Mill JSC (VGS).pdf |
| 4/5/2018 | 218 | 218 SMC4-MA-40 Test Result of Reinforcing Steel of Vietnam Germany Steel Mill JSC (VGS).pdf |
| 3/24/2018 | 219 | 219 SMC4-MA-0041 Test result of PC Strand 15.2 of Guizhou Wire Rope Incorporated company.pdf |
| 3/24/2018 | 219 | 219 SMC4-MA-41 Test result of PC Strand 15.2 of Guizhou Wire Rope Incorporated company.pdf |
| 3/26/2018 | 220 | 220 1007-PMUTL-DA1-Relocation of some Utilities in the Project.pdf |
| 3/26/2018 | 220 | 220-1007-PMUTL-DA1-Relocation of some Utilities in the Project.pdf |
| 3/26/2018 | 221 | 221 1021-PMUTL-DA6 Checking Project Benchmark Data.pdf |
| 3/27/2018 | 222 | 222 SMC4-MA-0042 Manufaturer's Capacity Profile of U-clip Coupler and Steel plate for grading Vinh Thuc Co Ltd.pdf |
| 3/27/2018 | 222 | 222 SMC4-MA-42 Manufaturer's Capacity Profile of U-clip Coupler and Steel plate for grading Vinh Thuc Co Ltd.pdf |
| 3/28/2018 | 223 | 223 SCM4-MS-17 Traffic control plan for construction at sections P9-P16 and P29-P37.pdf |
| 3/28/2018 | 223 | 223- SCM4-MS-0017-Traffic control plan for construction at sections P9-P16 and P29-P37.pdf |
| 3/28/2018 | 224 | 224 SMC4-LC-80 Method Statement of Traffic control plan for Construction at sections P9-P16 and P29-37.pdf |
| 3/28/2018 | 224 | 224-SMC4-LC-080-Method Statement of Traffic control plan for Construction at sections P9-P16 and P29-37.pdf |
| 3/29/2018 | 225 | 225 SMC4-LP-15 Provision of designed drawing of Widening Project and revised drawing of drainage system.pdf |
| 3/29/2018 | 225 | 225-SMC4-LP-0015-Provision of designed drawing of Widening Project and revised drawing of drainage system.pdf |
| 4/14/2018 | 226 | 226 SMC4-MS-18 Method statement of temporary facilities arrangement at P9-P16 and P29-P37.pdf |
| 3/29/2018 | 226 | 226- SMC4-MS-0018-Proposal for method statement of temporary facilities arrangement at P9-P16 and P29-P37.pdf |
| 4/14/2018 | 226 | 226-SMC4-MS-0018-Method statement of temporary facilities arrangement at P9-P16 and P29-P37.pdf |
| 3/29/2018 | 227 | 227 SMC4-LC-81 Mobilization for manpower & equipment by SubContractor Thanh Long JSC for pile test.pdf |
| 3/29/2018 | 227 | 227-SMC4-LC-0081-Mobilization for manpower & equipment by SubContractor Thanh Long JSC for pile test.pdf |
| 3/30/2018 | 228 | 228 SMC4-MS-0019 Method statement of Demolition and Relocation of Existing Utilities (stage 1).pdf |
| 3/30/2018 | 228 | 228 SMC4-MS-19 Method statement of Demolition and Relocation of Existing Utilities (stage 1).pdf |
| 3/30/2018 | 229 | 229 SMC4-LP-0016 Submission of Contractor's Plan until 30th April 2018.pdf |
| 3/30/2018 | 229 | 229 SMC4-LP-16 Submission of Contractor's Plan until 30th April 2018.pdf |
| 3/31/2018 | 230 | 230 SMC4-MA-43 Technical Profile of yellow sand pit for cement Concrete.pdf |
| 4/4/2018 | 231 | 231 SMC4-WD-09 Working drawing of cast-in-place concrete pile for pier P29,P30.pdf |
| 4/4/2018 | 232 | 232 SMC4-WD-010 WD of demolition & Removal of Existing Utilities for concrete blocks at Median and Lighting system.pdf |
| 4/4/2018 | 232 | 232 SMC4-WD-10 WD of demolition & Removal of Existing Utilities for concrete blocks at Median and Lighting system.pdf |
| 4/4/2018 | 233 | 233 SMC4-WD-08 Working drawing of test pile of Pre-cast concrete pilling for Retaining wall of Ramp HQV-B.pdf |
| 4/4/2018 | 234 | 234 SMC4-LC-82 Proposal for changing road pavement structure for traffic control.pdf |
| 4/5/2018 | 235 | 235 1191-GM-BQLDATL Meeting Invitation.pdf |
| 4/5/2018 | 235 | 235-1191-GM-BQLDATL Meeting Invitation.pdf |
| 4/5/2018 | 236 | 236 255-TB-SGTVT Notice on Traffic Organization and Traffic Lane Distribution on Pham Van Dong Road.pdf |
| 4/5/2018 | 236 | 236-255-TB-SGTVT Notice on Traffic Organization and Traffic Lane Distribution on Pham Van Dong Road.pdf |
| 4/5/2018 | 237 | 237 Working Minutes - Agreement on Implementation Areas between Two Projects - Copy.pdf |
| 5/5/2018 | 238 | 238 SMC4-MS-0020 Method statement for Temporary facilities on site from Pier P9 to P16 and from Pier P29 to P37 - Copy.pdf |
| 5/5/2018 | 238 | 238 SMC4-MS-20 Method statement for Temporary facilities on site from Pier P9 to P16 and from Pier P29 to P37 - Copy.pdf |
| 4/5/2018 | 239 | 239 SMC4-LC-0083 Proposal for Environmental control plan.(3rd Submission ).pdf |
| 4/5/2018 | 239 | 239 SMC4-LC-83 Environmental control plan.(3rd Submission ).pdf |
| 4/7/2018 | 240 | 240 SMC4-MA-44 Capacity Profile of Bentonite Manufacturer Hung Ngoc Produce and Trading Company Limited.pdf |
| 4/10/2018 | 241 | 241 SMC4-WD-11 Working drawing of cast-in-place concrete pile for pier P36,P37.pdf |
| 4/11/2018 | 242 | 242 SMC4-LC-84 Terms of Reference and cost Estimate for Environment Monitoring item(2nd submission).pdf |
| 4/11/2018 | 243 | 243 SMC4-LC-85 Adjustment of the rebar length of Super T Girder for Crossbeams Construction.pdf |
| 4/11/2018 | 244 | 244 1250-PMUTL-DA1 Quick completion of Preparation work and Expedition of Implementation.pdf |
| 4/11/2018 | 245 | 245 Working Minutes on hand-over and take-over of the site & preparation of fencing work (stage 1).pdf |
| 4/11/2018 | 245 | 245-Working Minutes on hand-over and take-over of the site & preparation of fencing work (stage 1).pdf |
| 4/12/2018 | 246 | 246 202-GM-BQLCTGT- Meeting Invitation- Water Transmission Pipeline D800.pdf |
| 4/12/2018 | 247 | 247 1299-PMUTL-DA1-Change Name of PMD1 and PMD6.pdf |
| 4/12/2018 | 248 | 248 SMC4-MA-45 Capacity profile of PC duct manufacturer Ngoc Lam Company.pdf |
| 4/12/2018 | 248 | 248 SMC4-MA-45-Proposal for capacity profile of PC duct manufacturer Ngoc Lam Company.pdf |
| 4/12/2018 | 249 | 249 SMC4-LC-0086 Withdraw the letter Regarding Proposal for changing road pavement Structure for traffic control.pdf |
| 4/12/2018 | 249 | 249 SMC4-LC-86 Withdraw the letter Regarding Proposal for changing road pavement Structure for traffic control.pdf |
| 4/12/2018 | 250 | 250 SMC4-MA-0046 capacity profile of Hoa Phat Steel and Kyoei Vietnam Manufacturer and Supplier (2nd).pdf |
| 4/12/2018 | 250 | 250 SMC4-MA-46 Capacity profile of Hoa Phat Steel and Kyoei Vietnam Manufacturer and Supplier (2nd).pdf |
| 4/16/2018 | 251 | 251 SMC4-RP-0008 Report on additional geoglogical investigation stage 1 (2 Submission).pdf |
| 4/16/2018 | 251 | 251 SMC4-RP-08 Additional geoglogical investigation stage 1 (2 Submission).pdf |
| 4/11/2018 | 252 | 252 1259 GM-BQLDATL Invitation for Site Visit.pdf |
| 4/16/2018 | 253 | 253 SMC4-WD-12 WD of Demolition and Removal of Existing Utilities for concrete blocks at Median and Lighting system (2nd).pdf |
| 4/24/2018 | 254 | 254 SMC4-RP-9 Benchmark Analytic Grade 1 Report (2nd Submission).pdf |
| 4/19/2018 | 255 | 255 SMC4-MS-21 Method statement for trial Excavation of Confirmation the Underground Utilities(repair.PDF |
| 4/20/2018 | 256 | 256 SMC4-MS-22 Traffic control method for public roads for construction P29-37.pdf |
| 5/15/2018 | 257 | 257 SMC4-MS-23 Method statement of Bored pile Diameter D=1.0m.pdf |
| 4/21/2018 | 258 | 258 SMC4-MA-48 Report on testing results of Yellow Sand Lo River for Ceement Concrete.pdf |
| 4/21/2018 | 259 | 259 SMC4-MA-49 Mix Proportion for Trial Mix Class C1,3 ,4 (slump 13+2.5 cm) and D(Slump 10+2.5cm at Batching plant Asean.pdf |
| 4/21/2018 | 260 | 260 SMC4-MA-50 Mix Proportion for Trial Mix class A,B1,C1,C3,C4,D,E,G and Y at Batching plant TRANSMECO.pdf |
| 4/21/2018 | 261 | 261 SMC4-MA-47 Testing Results of Crushed Stone and Water for Batching Plant TRANSMECO.pdf |
| 4/23/2018 | 262 | 262 SMC4-MA-51 Capacity Profile of Manufacturer and Supplier for Vietnam-Italy Reinforcing steel Bar(VIS) (2nd ).pdf |
| 4/26/2018 | 263 | 263 SMC4-LC-87 Proposal for Confirmation and Handing over of Existing Utilities on Pham Van Dong Street for construction at P9-P16 and P29-P37.pdf |
| 4/26/2018 | 264 | 264 SMC4-LC-86 Notice on National Holiday Schedule (South Liberation Day and Labor Day) of The Contractor.pdf |
| 4/26/2018 | 265 | 265 1523-PMUTL-DHDA1 Invitation Salvage of Asset on Pham Van Dong Road.pdf |
| 4/26/2018 | 266 | 266 1524-PMUTL-DHDA1 Invitation Salvage of Asset on Pham Van Dong Road.pdf |
| 4/26/2018 | 267 | 267 4157-BGTVT-CQLXD Request for Coordination & Instruction for Expedition of implementation progress of Project.pdf |
| 4/26/2018 | 268 | 268 SMC4-MA-52 Capacity profile of Manufacturer for U-clip coupler and steel plate for gradingVinh Thuc (2nd).pdf |
| 4/27/2018 | 269 | 269 Working Minutes -Agreement on Inventory and Method of salvage.pdf |
| 4/27/2018 | 270 | 270 SMC4-MA-24 Method statement for Ultrasonic test,tip contract checking test,Static loading test and Dynamic test (PDA) ...pdf |
| 4/27/2018 | 270 | 270 SMC4-MS-24 Ultrasonic test,tip contract checking test,Static loading test and Dynamic test (PDA) ...pdf |
| 4/27/2018 | 271 | 271 1558-PMUTL-DHDA1 Invitation Site Hand-over.pdf |
| 4/27/2018 | 272 | 272 1557 PMUTL-DHDA1 Expedition of Implementation Progress.pdf |
| 4/27/2018 | 272 | 272-1557 PMUTL-DHDA1 Expedition of Implementation Progress.pdf |
| 5/3/2018 | 273 | 273 SMC4-MA-53 Capacity Profile of Manufacturer and Supplier for PVC Pipe material (2nd).pdf |
| 5/3/2018 | 274 | 274 SMC4-LP-17 Propose to Support the contractor in installation of Project information Signs and Temporary electric poles for construction work.pdf |
| 5/3/2018 | 274 | 274 SMC4-LP-17 Support the contractor in installation of Project information Signs and Temporary electric poles for construction work.pdf |
| 5/3/2018 | 275 | 275 Working Mintutes date 2.5.18.pdf |
| 5/3/2018 | 276 | 276 248 GM-BQL-CTGT INVITATION Date 4.5.18.pdf |
| 5/4/2018 | 277 | 277 SMC4-MA-54 Capacity Profile of Manufacturer and Supplier for Bentonite Pil-0-Gel.pdf |
| 5/5/2018 | 278 | 278 1612 PMUTL-DHDA1 Erection of Project information Sign.pdf |
| 5/22/2018 | 279 | 279 SMC4-LC-88 Changing of steel plate in girder and Steel plate for Grading (2nd).pdf |
| 5/7/2018 | 280 | 280 Minutes of Handing Over Section Pier P9-P16,P29-P37.pdf |
| 5/16/2018 | 281 | 281 SMC4-MA-55 Trial mix of concrete class A,B1,E,G,Y of ASEAN Batching plant.pdf |
| 5/8/2018 | 282 | 282 SMC4-MS-25 Layout of traffic control for construction at Section P29-P27.pdf |
| 5/8/2018 | 283 | 283 256-GM-BQL-CTGT Invitation for Site Handover date 10.5.18.pdf |
| 5/8/2018 | 284 | 284 SMC4-LP-18 Speed up the preparation work before land handing over.pdf |
| 5/8/2018 | 285 | 285 SMC4-LC-89 Equipment Mobilization of the Team 4.pdf |
| 5/8/2018 | 286 | 286 SMC4-MA-56 Test result of PC Strand 15.2 of Guizhou Wire Rope Incorporated.pdf |
| 5/9/2018 | 287 | 287 Working Minutes date 7.5.18.pdf |
| 5/16/2018 | 288 | 288 SMC4-LC-90 Approval of Thanh Long Group JSC Capacity Profile.pdf |
| 5/22/2018 | 289 | 289 SMC4-LC-91 Confirmation of actual underground existing utilities survey - stage 1.pdf |
| 5/22/2018 | 289 | 289- SMC4-LC-0091-Confirmation of actual underground existing utilities survey - stage 1.pdf |
| 5/18/2018 | 290 | 290 SMC4-LC-92 Reply to the Engineer's letter regarding TOR and Cost Estimate of Enviroment Monitoring Item.pdf |
| 5/18/2018 | 291 | 291 SMC4-LC-93 Repply to the Engineer's letter regarding Enviromental Control Plan - Copy.pdf |
| 5/18/2018 | 292 | 292 SMC4-LC-0094 Cost Estimate for Test on concrete piles Cast -in - Place Concrete Piles and RC 35x35 cm.pdf |
| 5/18/2018 | 292 | 292 SMC4-LC-94 Cost Estimate for Test on concrete piles Cast -in - Place Concrete Piles and RC 35x35 cm.pdf |
| 5/16/2018 | 293 | 293 SMC4-LC-0095 Enviromental Monitoring Additional at Pre-Construction phase.pdf |
| 5/16/2018 | 293 | 293 SMC4-LC-95 Enviromental Monitoring Additional at Pre-Construction phase.pdf |
| 5/15/2018 | 294 | 294 1747PMUTL-DHDA1-Execution of the Works of PK1 MD-CN Section (Km0+3--Km2+812.5).pdf |
| 5/18/2018 | 295 | 295 SMC4-RP-0010-Report on topographic survey from Km0+660-Km1+000 and Km1+540-Km1+910.pdf |
| 5/18/2018 | 295 | 295 SMC4-RP-10 Topographic survey from Km0+660-Km1+000 and Km1+540-Km1+910.pdf |
| 5/18/2018 | 296 | 296 SMC4-LC-0096-Withdrawal of the letter SMC4-LC-0089 dated 8 May 2018.pdf |
| 5/18/2018 | 296 | 296 SMC4-LC-96 Withdrawal of the letter SMC4-LC-0089 dated 8 May 2018.pdf |
| 5/18/2018 | 297 | 297 SMC4-LC-0097-Proposal for 1st documen for additional equipment mobilization of team 1.pdf |
| 5/18/2018 | 297 | 297 SMC4-LC-97 1st document for additional equipment mobilization of team 1.pdf |
| 5/21/2018 | 298 | 298 SMC4-LC-0098-Proposal for approval of environmental control plan (4th submission).pdf |
| 5/21/2018 | 298 | 298 SMC4-LC-98 Environmental control plan (4th submission).pdf |
| 5/18/2018 | 299 | 299 SMC4-MS-0026-Proposal for method statement of traffic control at P29-P37 Lighting system (2nd).pdf |
| 5/18/2018 | 299 | 299 SMC4-MS-26 Traffic control at P29-P37 Lighting system (2nd).pdf |
| 5/17/2018 | 300 | 300 SMC4-MA-0057-Report on test result of reinforcing steel of kyoei steel Vietnam Company Limited and Hoa Phat Hai Duong Steel JSC.pdf |
| 5/17/2018 | 300 | 300 SMC4-MA-57 Test result of reinforcing steel of kyoei steel Vietnam Company Limited and Hoa Phat Hai Duong Steel JSC.pdf |
| 5/18/2018 | 301 | 301 SMC4-LC-0099-Proposal for TOR and cost estimate for Protection and relocation Utilities at P26-P37.pdf |
| 5/18/2018 | 301 | 301 SMC4-LC-99 TOR and cost estimate for Protection and relocation Utilities at P26-P37.pdf |
| 5/22/2018 | 302 | 302 SMC4-LC-0100-Proposal for approval of documetn of 1st additional equipment of team 4.pdf |
| 5/22/2018 | 302 | 302 SMC4-LC-100 Document of 1st additional equipment of team 4.pdf |
| 5/18/2018 | 303 | 303 SMC4-LC-0101-Proposal for approval of breakdown for lump sum items.pdf |
| 5/18/2018 | 303 | 303 SMC4-LC-101 Breakdown for lump sum items.pdf |
| 5/18/2018 | 304 | 304 SMC4-RP-0011-Report on survey on existing trees condition from P4-P16.pdf |
| 5/30/2018 | 304 | 304 SMC4-RP-11 Survey on existing trees condition from P4-P16.pdf |
| 5/19/2018 | 305 | 305 SMC4-LC-0102-Proposal for approval of TOR and cost estimate for traffic control stage 1 at P29-P37.pdf |
| 5/19/2018 | 305 | 305 SMC4-LC-102 TOR and cost estimate for traffic control stage 1 at P29-P37.pdf |
| 5/21/2018 | 306 | 306 Minutes of Site Hand-Over (Stage 1).pdf |
| 5/21/2018 | 307 | 307 SMC4-LC-0103-Submission of weekly report No.1.pdf |
| 5/26/2018 | 307 | 307 SMC4-LC-103 Submission of weekly report No.1.pdf |
| 5/21/2018 | 308 | 308 SMC4-LC-0104-Traffic control plan for construction at sections A1-P4.pdf |
| 5/21/2018 | 308 | 308 SMC4-LC-104 Traffic control plan for construction at sections A1-P4.pdf |
| 5/21/2018 | 309 | 309 1847 BQLDATL-DA1 Site Hand-over .pdf |
| 5/22/2018 | 310 | 310 SMC4-WD-0013-Proposal for WD of cast in place pile for pier P31 (2nd).pdf |
| 5/22/2018 | 310 | 310 SMC4-WD-13 WD of cast in place pile for pier P31 (2nd).pdf |
| 6/14/2018 | 311 | 311 SMC4-WD-0014-Proposal for approval of working drawing of cast in place pile for P29, P30 (2nd).pdf |
| 5/22/2018 | 311 | 311 SMC4-WD-14 Working drawing of cast in place pile for P29, P30 (2nd).pdf |
| 5/22/2018 | 312 | 312 SMC4-WD-0015-Proposal for WD of cast in place concrete pile for pier P36, P37.pdf |
| 5/22/2018 | 312 | 312 SMC4-WD-15 WD of cast in place concrete pile for pier P36, P37.pdf |
| 5/22/2018 | 313 | 313 SMC4-SC-0013-Proposal for manpower and equipment mobilization of TRANSMECO BP.pdf |
| 5/22/2018 | 313 | 313 SMC4-SC-13 Manpower and equipment mobilization of TRANSMECO BP.pdf |
| 5/22/2018 | 314 | 314 PMUTL-1852-DA1-Approval of The Subcontractor-479 JSC and 423 Construction & Trade Company..pdf |
| 5/22/2018 | 314 | 314 PMUTL-1852-DA1-The Subcontractor-479 JSC and 423 Construction & Trade Company..pdf |
| 5/23/2018 | 315 | 315 PMUTL- 1918- Invitation- Meeting in Traffic Control.pdf |
| 6/1/2018 | 316 | 316 SMC4-WD-16 General view of Main Bridge and Ramp HQV-B (3rd).pdf |
| 5/29/2018 | 317 | 317 SMC4-SC-14 Manpower and equipment mobilization of Co.423.pdf |
| 5/29/2018 | 318 | 318 SMC4-SC-15 Manpower and equipment mobilization of Co.479.pdf |
| 5/23/2018 | 319 | 319 SMC4-LC-106 Location and layout of site office and accommodation for JV and SubContractors.pdf |
| 7/23/2018 | 320 | 320 SMC4-MA-59 Test result of Reinforcing Steel of Vietnam Italy Steel JSC.pdf |
| 5/24/2018 | 321 | 321 SMC4-WD-17 WD of cast in place pile for middle column from P32C-P35C.pdf |
| 5/30/2018 | 322 | 322 SMC4-RP-12 Topographic survey Fr Km0+660-Km1+000 and Km1+540-Km1+910 (2nd).pdf |
| 5/25/2018 | 323 | 323 Minutes of Meeting 21.05.2018.pdf |
| 5/25/2018 | 324 | 324 Minutes of Site Handover 22.05.2018.pdf |
| 5/25/2018 | 325 | 325 1160-PMUTL-DA1 Sub-consultant for implementation of HIV-AIDS prevention program.pdf |
| 5/25/2018 | 326 | 326 SMC4-MA-60 Testing Results of Bentonite Material of Hung Ngoc Co.Ltd for bored pile.pdf |
| 5/25/2018 | 327 | 327 SMC4-WD-18 WD of SuperT girder from P29-P30.pdf |
| 5/25/2018 | 328 | 328 SMC4-MA-58 Capacity Profile of Batching Plant The Gioi Nha.pdf |
| 5/26/2018 | 329 | 329 SMC4-LC-107 Calculation Sheet for Soil Bearing Capacity of Bored Pile and Pre-Cast Pile Based on Additional Geological Investigation Report (2nd).pdf |
| 5/28/2018 | 330 | 330 1978-GM-BQLDATL Meeting Invitation.pdf |
| 5/28/2018 | 331 | 331 SMC4-LC-108 Weekly Report No.2.pdf |
| 5/31/2018 | 332 | 332 1983 PMUTL-DA1 Ensuring traffic control and Traffic Safety during.pdf |
| 5/29/2018 | 333 | 333 2021-GM-BQLDATL Invitation Date 30.5.pdf |
| 5/29/2018 | 334 | 334 SMC4-LC-109 Engineer's Confirmation for Safety and Enviroment Satisfation.pdf |
| 5/31/2018 | 335 | 335 SMC4-MS-27 Traffic control plan and water drain at section A1-P4.pdf |
| 5/31/2018 | 336 | 336 SMC4-LC-110 The Contractor's Programme (2nd).pdf |
| 5/31/2018 | 337 | 337 SMC4-WD-19 WD of Relocation Diversion of Existing Utilities for Electrical and Telecommunication Cable Line (P26-P37) at Right Side.pdf |
| 6/1/2018 | 338 | 338 2074-GM-BQLDATL Invitation Date 5.6.18.pdf |
| 6/1/2018 | 339 | 339 SMC4-MC-03 Application for Interim payment Certificate No.1( period 11May to 31may2018).pdf |
| 6/1/2018 | 340 | 340 2086 PMUTLDA1 Checking and Evaluation of Sub-Contractor.pdf |
| 6/1/2018 | 341 | 341 SMC4-LC-111 TOR and Cost estimate for Environment Monitoring Items (3rd).pdf |
| 6/1/2018 | 342 | 342 SMC4-LC-112 Withdrawal of letter SMC4-LC-0071.pdf |
| 6/1/2018 | 343 | 343 SMC4-LC-113 ReNotice for Location of Fabrication Yard of Super T girder.pdf |
| 6/1/2018 | 344 | 344 SMC4-LC-114 Additional Equipment mobilization document of Team 1(2nd).pdf |
| 6/2/2018 | 345 | 345 SMC4-MA-61 Capacity Profile of Manufacturer and Supplier of Materials for Protection and Relocation of Existing Utilities System.pdf |
| 6/2/2018 | 346 | 346 2065 TB-BQLDATL Notice on Conslusions given by PMU In the Meeting on Implementation.pdf |
| 6/2/2018 | 347 | 347 SMC4-MS-28-18 Submission of Traffic control plan for public road for construction at section P18-P22.pdf |
| 6/2/2018 | 348 | 348 SMC4-LC 115 Additional Geological Investigation at P5 and P39.pdf |
| 6/2/2018 | 349 | 349 SMC4-LC 116 Notification on Arrangement of flagman for traffic control at sections P29-P37.pdf |
| 6/4/2018 | 350 | 350 SMC4-WD-20 WD of Cast in Place concrete pile for P35.pdf |
| 6/5/2018 | 351 | 351 SMC4-LC-117 Submission of weekly report No.3.pdf |
| 6/15/2018 | 352 | 352 SMC4-LC-118 Submission of monthly report No.1.pdf |
| 6/5/2018 | 353 | 353 SMC4-LP-19 Detailed plan for a Joint Inspection of Thanh Long JSC.pdf |
| 6/5/2018 | 354 | 354 SMC4-MS-29 Traffic control plan for public road for construction at section P3-P17.pdf |
| 6/6/2018 | 355 | 355 SMC4-MA-62 Addition of Capacity profiles of Manufacturer and Supplier for Traffic Control Material.pdf |
| 6/6/2018 | 356 | 356 SMC4-LC-119 Legal Document of Electric source (A1- P61) and Water source (A1- P37).pdf |
| 6/7/2018 | 357 | 357 SMC4-LC-120 Notice for Leave for our Key Personnel ( Project Manager).pdf |
| 6/7/2018 | 358 | 358 SMC4-WD-21 WD of Structure Excavation and backfill for Section P29-P37.pdf |
| 6/7/2018 | 359 | 359 SMC4-LC-124 Terms of Reference for Ultrasonic test, tip contact checking test, static loading test and dynamic test (PDA) of Pre cast concrete pile and cast in place concrete pile (2nd).pdf |
| 6/8/2018 | 360 | 360 SMC4-LC-121 Notice of Claim for Extension of time for Completion of the Works.pdf |
| 6/8/2018 | 361 | 361 SMC4-LC-122 Claim No.1 Notice of Claim for additional payment due to the difference between the actual site and the site at the time for bid submission.pdf |
| 6/8/2018 | 362 | 362 SMC4-LC-123 Report on Comparison of Economic Technical Criteria for alternation of Rotation steel Piles into Cast in place concrete piles at P9-15 & P45-P58.pdf |
| 6/8/2018 | 363 | 363 SMC4-LC-125 Breakdown for lump sum items (2nd).pdf |
| 6/8/2018 | 364 | 364 SMC4-MA-63 Capacity Profile of Manufacturer for PC Duct-NgocLam Production and Trading Co.LTD (2nd).pdf |
| 6/8/2018 | 365 | 365 SMC4-LC-126 Report Safety Trading Ducument for Crane Operators.pdf |
| 6/8/2018 | 366 | 366 SMC4-RP-13 Report For Trial Excavation of Bored Pile - Hole No.H5P31.pdf |
| 6/9/2018 | 367 | 367 SMC4-LC-127 Withdrawal of the letter AMC4-RP-0013 dated 08June18.pdf |
| 6/9/2018 | 368 | 368 SMC4-RP-14 Resubmission the RP for Trial Excavation of Bored pile- Hole No.H5P31.pdf |
| 6/11/2018 | 369 | 369 SMC4-LC-128 To Support the Contractor in Coordination with Widening Project to fix the schedule and Completion date of light system of Widening Project.pdf |
| 6/11/2018 | 370 | 370 SMC4-LC-129 Method Statement of Traffic control plan for construction at sections P18-P22.pdf |
| 6/14/2018 | 371 | 371 SMC4-LC-130 Notice of Enviromental Monitoring Schedule in June 2018 at Construction phase.pdf |
| 6/11/2018 | 372 | 372 SMC4-WD-22 WD of Cast in Place Concrete Pile for Pier P32.pdf |
| 6/11/2018 | 373 | 373 SMC4-WD-23 WD of Cast in Place Concrete Pile for Pier P33.pdf |
| 6/11/2018 | 374 | 374 SMC4-WD-24 WD of Cast in Place Concrete Pile for Pier P34.pdf |
| 6/11/2018 | 375 | 375 SMC4-LC-133 Report on Inspecting Capacity of Thanh Long Group JSC.pdf |
| 6/12/2018 | 376 | 376 SMC4-LC-132 Proposals on Adjustment of the Drainage System on Bridge.pdf |
| 6/12/2018 | 377 | 377 SMC4-LC-134 Submission of Weekly Report No.4.pdf |
| 6/12/2018 | 378 | 378 SMC4-LC-135 Confirmation of additional actual underground existing ultilities' survey data - Stage 1 P26-P37 ( 1st supplymentation).pdf |
| 6/12/2018 | 379 | 379 SMC4-MA-65 Report on frequency test of Cement, crushed stone, yellow sand, water and admixture for Cement concrete at ASEAN Batching Plant (1st).pdf |
| 6/12/2018 | 380 | 380 SMC4-MA-66 Report on Test result of Tie anchor ( U-Bolt) of Vinh Thuc Co. LTD.pdf |
| 6/12/2018 | 381 | 381 SMC4-LC-136 Withdrawal SMC4-LC-132-18 Adjustment of the Drainage System on Bridge.pdf |
| 6/12/2018 | 382 | 382 SMC4-LC-137 Proposal on Adjustment of the Drainage System on Bridge.pdf |
| 6/12/2018 | 383 | 383 SMC4-MA-64 Report on Frequency test of Reinforcing Steel for Cast in Place concrete pile Pier P31.pdf |
| 6/13/2018 | 384 | 384 3282 SGTVT-QLKCHTGT Giving opinion on traffic control plan for execution.pdf |
| 6/13/2018 | 385 | 385 2097 BQLDATL-DA1 Fencing and traffic control plan for execution.pdf |
| 6/16/2018 | 386 | 386 SMC4-MC-04 Interim payment Certificate No.1(11.5-31.5.18)(2nd).pdf |
| 6/13/2018 | 387 | 387 SMC4-MS-30 Method Statement of Structure Excavation P29-P37,P29L-P31L.pdf |
| 6/13/2018 | 388 | 388 SMC4-WD-25 WD Relocation of Existing Utilities for Electrical cable Line and Telecommunication P26-P37.pdf |
| 6/20/2018 | 389 | 389 SMC4-MA-67 Report on Frequency test of Reinforcing Steel for Cast in Place concrete pile Pier P35.pdf |
| 6/14/2018 | 390 | 390 SMC4-RP-15 Report for Trial Excavation ofCast in Place concrete pilling Hole No.H8P35.pdf |
| 6/15/2018 | 391 | 391 SMC4-LC-138 The Contractor's Programme (3rd ).pdf |
| 6/15/2018 | 392 | 392 SMC4-WD-27 WD of Super T Girder Span 31 (P30-P31).pdf |
| 6/15/2018 | 393 | 393 SMC4-WD-26 WD of Extension of Pile Top for Static Load Test of Pier P35.pdf |
| 6/16/2018 | 394 | 394 SMC4-LP-20 Notice in changing Contractor's Bank name for receiving Japanese Yen Portion of PK1.pdf |
| 7/3/2018 | 395 | 395 SMC4-MS-31 Method Statement of Temporary Facilitites Arrangement on site from P18-P22.pdf |
| 6/16/2018 | 396 | 396 SMC4-RP-16 Report on Topographic Survey - stage 2 fr Km0+328.8 to Km0+ 487.9.pdf |
| 6/19/2018 | 397 | 397 SMC4-RP-17 Report on trial excavation of cast in place concrete piling - Hole No.H9P37.pdf |
| 6/19/2018 | 398 | 398 SMC4-MA-68 Report on trial mix and proposal for proportion grouting for sonic tube.pdf |
| 6/19/2018 | 399 | 399 SMC4-MA-69 Manufacturer's and suppliers capacity profile of couple and steel plate for grading.pdf |
| 6/19/2018 | 400 | 400 SMC4-LC-139 Submission of weekly report No.5.pdf |
| 6/19/2018 | 401 | 401 SMC4-MS-32 Method Statement of Protecting and relocating utilitites, stage 1 P26-P37.pdf |
| 6/19/2018 | 402 | 402 SMC4-MS-33 Scheme of Additional geological investigation at pier P5 and P39.pdf |
| 6/19/2018 | 403 | 403 SMC4-MS-34 Traffic control Plan for Public road for Construction at section A1-P22.pdf |
| 6/19/2018 | 404 | 404 2348-PMUTL-DHDA1 18Jun Temporary Lighting during Execution of PK1.pdf |
| 6/19/2018 | 405 | 405 2346-PMUTL-DHDA1-Fencing & Traffice Control during execution of the project.pdf |
| 6/20/2018 | 406 | 406 SMC4-RP-18 The Incident report on construction of Cast in Place concrete pilling- Pier No.3 of pier P31.pdf |
| 6/19/2018 | 407 | 407 2347-PMUTL-DHDA1 Coordination between Viaduct Construction Project & Widening Project.pdf |
| 6/20/2018 | 408 | 408 SMC4-MA-70 Report on Frequency Test of Reinforcing Steel for Cast in Place concrete Pile P37.pdf |
| 6/21/2018 | 409 | 409 SMC4-WD-28 WD of Cast in Place Concrete Pile for A1.pdf |
| 6/21/2018 | 410 | 410 SMC4-WD-29 WD of Cast in Place Concrete Pile for P1.pdf |
| 6/21/2018 | 411 | 411 SMC4-WD-30 WD of Cast in Place Concrete Pile for P2.pdf |
| 6/22/2018 | 412 | 412 SMC4-LC-140 Request for Confirmation of Specification Requirement on Cement brand.pdf |
| 8/11/2018 | 413 | 413 Minutes of the Scane-Enviromental Mornitoring 17-31May18.pdf |
| 6/22/2018 | 414 | 414 SMC4-MS-35 Steel bridge Fabrication Procedure of Thanh Long Group JSC.pdf |
| 6/23/2018 | 415 | 415 SMC4-LC-141 Supplement Document of Fabrication Yard of Super T girder.pdf |
| 7/9/2018 | 416 | 416 SMC4-MS-36 Method Statement of Production of Super T girder (Rev.2).pdf |
| 6/25/2018 | 417 | 417 SMC4-LC142 Submission of Weekly Report No.6.pdf |
| 6/25/2018 | 418 | 418 SMC4-LC143 Withdrawal of the letter SMC4-LC-0140 21JUN18.pdf |
| 6/26/2018 | 419 | 419 SMC4-MS-26A Traffic Control Plan for Public Road at P45-P60.pdf |
| 7/26/2018 | 420 | 420 SMC4-LC-144 TOR for Ultrasonic Test, Tip Contract Checking Test, Static Loading Test & PDA (3rd).pdf |
| 6/28/2018 | 421 | 421 SMC4-LC-146 Request for Clarification of Detail of Basement for Traffic Sign Board.pdf |
| 6/27/2018 | 422 | 422 SMC4-LC-145 Reply to the Engineer's letter Regarding Environment Control Plan.pdf |
| 6/28/2018 | 423 | 423 498 TB-SGTVT Notice on Alternatives for Adjustment of Construction fence,Traffic diversion and Traffic control.pdf |
| 6/28/2018 | 424 | 424 SMC4-MS-37 Method Statement of Traffic control for Construction of P29-P37-Volume I.3 Layout Plan of Road Marking.pdf |
| 6/28/2018 | 425 | 425 SMC4-MS-38 General Traffic Control Plan for Public Road for Construction stage 1.pdf |
| 6/28/2018 | 426 | 426 SMC4-LC-147 Additional Equipment Mobilization Document of Team 1(3rd).pdf |
| 6/28/2018 | 427 | 427 SMC4-LC-148 Additional Report on Environmental Monitoring at Pre-Construction Phase.pdf |
| 6/28/2018 | 428 | 428 Minutes of Inspection Capability for Production Fabrication and Construction of Steel Bridge of Thanh Long.pdf |
| 6/29/2018 | 429 | 429 2511 PMUTL-DA1 Approval for Subcontrator,Thanh Long Group JSC.pdf |
| 6/29/2018 | 430 | 430 371 GM-BQLCTGT Invitation Letter.pdf |
| 6/30/2018 | 431 | 431 SMC4-LC-149 Additional Report on Comparison of Economic-Technical Criteria for Alternation of Rotation Steel Piles into CIP Concrete Pile at P9-P19 & P45-P58.pdf |
| 7/2/2018 | 432 | 432 SMC4-MS-39 Method of Traffic Control for Public Road during the Fence Trial at P18-P22.pdf |
| 7/2/2018 | 433 | 433 SMC4-LC-150 Submission of Weekly Report No.7.pdf |
| 7/2/2018 | 434 | 434 2556-GM-BQLDATL Invitation.pdf |
| 7/4/2018 | 436 | 436 SMC4-RP-19 Report on Trial Excavation of Cast in Place Concrete Pilling- Hole No.H5'P30.pdf |
| 7/4/2018 | 437 | 437 2596 GM-BQLTL Invitation Letter.pdf |
| 7/5/2018 | 438 | 438 2614 PMUTL-KTTD Strengthening of Quality Management during Construction.pdf |
| 7/5/2018 | 439 | 439 SMC4-LC-151 Submission of Monthly Report No.2.pdf |
| 7/13/2018 | 440 | 440 SMC4-MA-71 Report on Trial of Concrete Class A,B1,C1,C3,C4,D,G,Y of Transmeco Bathching Plant.pdf |
| 7/7/2018 | 441 | 441 SMC4-LC-152 New Design for Cast in Place Concrete Pile In Replacement of Rotation Steel Pile at P9-P15& P45-P58 (9 Piles per 1Pile Cap) (2nd).pdf |
| 7/7/2018 | 442 | 442 SMC4-MS-40 WD of General Layout of Road Marking in Traffic Control Method.pdf |
| 7/7/2018 | 443 | 443 SMC4-LC-153 Additional Equipment Mobilization Document of Team 1 (4th).pdf |
| 7/9/2018 | 444 | 444 2629-PMUTL Notice on Conclusions by PMUTL on the Meeting on Expedition of Construction & Disbursement Progress of PK1 & PK2.pdf |
| 7/9/2018 | 445 | 445 7303-BGTVT-CQLXD Design Change of Pilling Foundation From Rotation Steel Pile to Bored Steel Pile.pdf |
| 7/9/2018 | 446 | 446 SMC4-RP-20 Report on Trial Excavation of Cast in Place Concrete Piling - Hole H5'P31.pdf |
| 7/9/2018 | 447 | 447 SMC4-MS-41 Quality Control Method of Reinforcing Steel Bars.pdf |
| 7/9/2018 | 448 | 448 SMC4-MS-42 Detail plan on Personnel Arrangement & Traffic Control Work at P29-P37.pdf |
| 8/3/2018 | 449 | 449 SMC4-MS-43 Method Statement of Traffic Control at P29-P37-Vol I.2.2 Adjustted of Temporary lighting system.pdf |
| 7/9/2018 | 450 | 450 SMC4-LC-155 Notice on Implementation of Official Fencing Work for P18-P22.pdf |
| 7/10/2018 | 451 | 451 SMC4-LC-154 Engineer's Confirmation for Safety & Environment Satisfaction (June -2018).pdf |
| 7/10/2018 | 452 | 452 WM onTrial Fencing From Pier P18-P22 & Section P84-P96.pdf |
| 7/10/2018 | 453 | 453 2670-PMUTL-DHDA1 Design Change of Pilling Foundation for Some Piers in Project.pdf |
| 7/13/2018 | 454 | 454 SMC4-MA-72 Report on Trial Mix of Concrete Class C1,C3,C4,D of ASEAN Bathching Plant.pdf |
| 7/10/2018 | 455 | 455 SMC4-LC-156 Submission of Weekly Report No.8.pdf |
| 8/24/2018 | 456 | 456 Minutes of Site Hand-Over (stage2).pdf |
| 8/3/2018 | 457 | 457 Agreement on Additional Suppervision Costs.pdf |
| 7/26/2018 | 458 | 458 SMC4-LC-157 Design Change for Replacement of Rotation Steel Pipe with Cast in Place Concrete Pile.pdf |
| 7/12/2018 | 459 | 459 SMC4-LC-158 Response to the Engineers letter on Claim for Extension of Time for Completion.pdf |
| 7/13/2018 | 460 | 460 2682 BQLDATL-ĐHDA1 Comments on Road-Markings for Traffic Control.pdf |
| 7/13/2018 | 461 | 461 2722 PMUTL-DHDA1 Protection & Relocation of Ultilities for Construction fr P32-P35.pdf |
| 7/16/2018 | 462 | 462 SMC4-MS-44 Method Statement of Demolition & Relocation of Existing Ultilities ( Stage 2).pdf |
| 7/13/2018 | 463 | 463 SMC4-WD-31 WD of Super T Girder Span 32 (P31-P32).pdf |
| 7/13/2018 | 464 | 464 SMC4-WD-32 WD of Super T Girder Span 37 (P36-P37).pdf |
| 7/13/2018 | 465 | 465 398-GM-BQLCTGT Prepare for Construction of Substructure of 5 Pedestrian Brigde at Km0+938,5, Km1+940, Km2+ 720, Km3+745,Km4+235.pdf |
| 7/13/2018 | 466 | 466 SMC4-WD-34 D of Substructure - Pile Cap of Pier P31.pdf |
| 7/13/2018 | 467 | 467 SMC4-WD-33 WD of Substructure - Pile Cap of Pier P37.pdf |
| 7/14/2018 | 468 | 468 SMC4-MS-45 Method Statement of Traffic Control for Public Road during Trial Fencing Installation at A1-P16.pdf |
| 7/14/2018 | 469 | 469 SMC4-MA-73 Manufacturer & Supplier of Bituminous Waterproofing Material for Concrete.pdf |
| 7/16/2018 | 470 | 470 2723-GM-BQLDATL Inspect & Evaluate the Fencing Work & Traffic Control.pdf |
| 7/20/2018 | 471 | 471 SMC4-RP-21 Topographic survey report stage 2 (Km0+326.15-Km0+660 & Km1+000-Km1+300).pdf |
| 7/16/2018 | 472 | 472 SMC4-LC-159 TOR & Cost Estimate for General Traffic Control for Public Road for Construction Stage 1.pdf |
| 7/16/2018 | 473 | 473 SMC4-LC-160 Submission of Weekly Report No.9.pdf |
| 7/17/2018 | 474 | 474 SMAC4-MA-74 Report on Frequency Test of Reinforcing Steel for Cast in Place Concrete Pile P33 & P34.pdf |
| 8/3/2018 | 475 | 475 SMC4-MS-47 Method Statement of Temporary Facilities Arrangement on Site at P3-P16.pdf |
| 8/7/2018 | 476 | 476 SMC4-MS-46 Supplement & Updating the Method Statement Plan Drawing of Trial Excavation & Cast in Place Concrete Pilling from P18-P22.pdf |
| 7/17/2018 | 477 | 477 SMC4-WD-35 WD of Substructure Pile Cap of P30.pdf |
| 7/17/2018 | 478 | 478 SMC4-WD-36 WD of Substructure Pile Cap of P35.pdf |
| 7/17/2018 | 479 | 479 SMC4-WD-37 WD of Substructure Pile Cap of P36.pdf |
| 7/18/2018 | 480 | 480 SMC4-MA-75 Report on Trial Mix of Concrete Class E of TRASMECO Batching Plant.pdf |
| 7/18/2018 | 481 | 481 SMC4-LC-161 Notice of Claim Regarding Delay of Review & Approval for Working Drawing of Cast In Place Concrete Pile for P32.pdf |
| 7/18/2018 | 482 | 482-LC-162 Notice for Prevention of Typhoon No.3 ( Son Tinh).pdf |
| 7/18/2018 | 483 | 483 238-TB-SGTVT Invitation Review & Agree on Taking Over & Handing Over of the Site; Method statement & traffic control plan; Coordination for expedition of Construction Progress.pdf |
| 7/19/2018 | 484 | 484 SMC4-MA-76 Capacity Profile of Manufaturer & Supplier for PC Strand & Anchorage for Pier Head-Zhemao Science & Technology Co.,ltd- Vinh Hung Trading Consulting & Construction JSC.pdf |
| 7/20/2018 | 485 | 485 SMC4-MA-78 Capacity Profile of Zhemao Science & Technology Co.,Ltd; PC Strand Manufacturer & Vinh Hung Trading Consulting & Construction JSC, PC Strand Supplier.pdf |
| 7/20/2018 | 486 | 486 SMC4-MA-77 Capacitiy Profile of Home World Batching Plant (2nd).pdf |
| 8/18/2018 | 487 | 487 SMC4-MS-48 Method Statement of Pile Cap from P29-P37 & Ramp P29L-P31L.pdf |
| 7/20/2018 | 488 | 488 SMC4-WD-38 WD of Cast in Place Concrete Pile for P18.pdf |
| 7/20/2018 | 489 | 489 SMC4-WD-39 WD of Cast in Place Concrete Pile for P19.pdf |
| 7/20/2018 | 490 | 490 SMC4-WD-40 WD of Cast in Place Concrete Pile for P20.pdf |
| 7/20/2018 | 491 | 491 SMC4-WD-41 WD of Cast in Place Concrete Pile for P21.pdf |
| 7/20/2018 | 492 | 492 SMC4-WD-42 WD of Cast in Place Concrete Pile for P22 (2nd).pdf |
| 7/20/2018 | 493 | 493 SMC4-WD-43 WD of Substructure - Pile Cap of P34.pdf |
| 7/20/2018 | 494 | 494 SMC4-WD-44 General View of Main Bridge & Ramp HQV-B (4th).pdf |
| 8/1/2018 | 495 | 495 SMC4-MA-79 Report on Test Result of MIGHTY Admixture.pdf |
| 7/25/2018 | 496 | 496 SMC4-RP-22 Report on Additional Geological Investigation Stage 2 ( Including Drilling Holes BS P5 & P39.pdf |
| 7/23/2018 | 497 | 497 SMC4-LC-166 Submission of Weekly Report No.10.pdf |
| 7/23/2018 | 498 | 498 SMC4-LC-164 Calculation Sheet for Soil Bearing Capacity of Bored Pile of P5 & P39 based on Additional Geological Investigation Report-Stage 2.pdf |
| 7/23/2018 | 499 | 499 SMC4-LC-163 Document for Water Truck Mobilization.pdf |
| 7/26/2018 | 500 | 500 SMC4-LC-165 Cost Estimate for Test on Concrete Pile Cast in Place Concrete Piles & RC 35x35cm (2nd).pdf |
| 7/24/2018 | 501 | 501 2872 GM-BQLDATL Meeting Safety Expert of JICA with PMUTL on Labor safety for Construction Project.pdf |
| 7/24/2018 | 502 | 502 SMC4-LC-167 Notice for Leave Key Personnel ( Project manager).pdf |
| 8/11/2018 | 503 | 503 SMC4-MA-80 Capacity Profile of the Manufacturer & Spplier for Blinding Stone, Granular Backfill, Permeable Backfill, Subbases & Bases Materials.pdf |
| 8/18/2018 | 504 | 504 SMC4-MS-49 Method Statement for Assembling & Loading Test of Gantry Crane at Fabrication Yard for Super T Girder of Group No.3- 414 Co.Lt.pdf |
| 7/26/2018 | 505 | 505 SMC4-MA-76A Report on Frequency Test of Reinforcing Steel for Cast in Place Concrete P30.pdf |
| 7/26/2018 | 506 | 506 SMC4-WD-45 WD of Cast in Place Concrete Pile for P4.pdf |
| 7/26/2018 | 507 | 507 SMC4-WD-46 WD of Cast in Place Concrete Pile for P6.pdf |
| 7/26/2018 | 508 | 508 SMC4-WD-47 WD of Cast in Place Concrete Pile for P7.pdf |
| 7/26/2018 | 509 | 509 SMC4-WD-48 WD of Cast in Place Concrete Pile for P8.pdf |
| 7/26/2018 | 510 | 510 SMC4-WD-49 WD of Substructure-Pile Cap of P29.pdf |
| 7/26/2018 | 511 | 511 SMC4-WD-50 WD of SuperT Girder Span P36 (P35-P36).pdf |
| 7/26/2018 | 512 | 512 TCQM-Invitation for Site Visit.pdf |
| 8/8/2018 | 513 | 513 SMC4-MA-81 Report on Test Result of Coupler & Steel Plate for Grading of Vinh Thuc Co.,Ltd.pdf |
| 7/27/2018 | 514 | 514 SMC4-MA-82 Capacity Profile of MINH TAM Batching Plant.pdf |
| 7/27/2018 | 515 | 515 SMC4-MA-83 Capacity Profile of Manufacturer for Tie Anchor, Steel Plate for Grading & Dowel of Viet Thang Co.pdf |
| 7/28/2018 | 516 | 516 SMC4-MA-84 Report on Frequency Test of Cement, Crushed Stone, yellow Sand, Water & Admixture at Transmeco Batching Plant (1st).pdf |
| 7/28/2018 | 517 | 517 SMC4-WD-51 WD of Substructure - Pile cap of P33.pdf |
| 7/28/2018 | 518 | 518 SMC4-WD-52 WD of Super T Girder Span P35 (P34-P35).pdf |
| 8/30/2018 | 519 | 519 SMC4-LC-168 Changing Some Items of Technical Specifications.pdf |
| 7/28/2018 | 520 | 520 SMC4-LP-21 VAT Invoices for Interim Payment Certificate No.1 of PK 1.pdf |
| 7/30/2018 | 521 | 521 SMC4-LC-169 Document for Mobilization of Additional Equipment of Team 2 (2nd).pdf |
| 7/30/2018 | 522 | 522 SMC4-LC-170 Submission of Weekly Report No.11.pdf |
| 8/25/2018 | 523 | 523 SMC4-MS-50 Method Statement of Structure Excavation from P29-P37 & Ramp P29L-P31L (Rev.02).pdf |
| 8/1/2018 | 524 | 524 SMC4-LC-171 Application for Interim Payment Certificate No.02 01stJune-31stJuly,2018.pdf |
| 8/1/2018 | 525 | 525 SMC4-WD-53 WD of Cast in Place Concrete Pile for P29L.pdf |
| 8/1/2018 | 526 | 526 SMC4-WD-54 WD of Cast in Place Concrete Pile for P30L.pdf |
| 8/1/2018 | 527 | 527 SMC4-WD-55 WD of Cast in Place Concrete Pile for P31L.pdf |
| 8/1/2018 | 528 | 528 SMC4-MA-87 Reinforcing Steel-Kyoei Steel Vietnam Co.Ltd for Cast-in-place Concrete Pile Pier P30 will be used for Cast-in-place Concrete Pile Pier P29.pdf |
| 8/2/2018 | 529 | 529 SMC4-MA-85 Report on Frequency Test of Reinforcing Steel for Cast in Place Concrete Pile P36.pdf |
| 8/2/2018 | 530 | 530 SMC4-MA-86 Report on Frequency Test of Reinforcing Steel for Cast in Place Concrete Pile P33&P34 (2nd).pdf |
| 8/3/2018 | 531 | 531 SMC4-MA-89 Report on Frequency Test of Reinforcing Steel for Cast in Place Concrete Pile P29.pdf |
| 8/3/2018 | 532 | 532 SMC4-MA-88 Capacity Profile of Manufacturer & Supplier for Rubbler Bearing Kawakin Core-Tech Vietnam.pdf |
| 8/3/2018 | 533 | 533 SMC4-LC-172 Mobilization for Manpower & Equipment by Thanh Long JSC for Test of Concrete Pile & Rotation Steel Pile (2nd).pdf |
| 8/3/2018 | 534 | 534 SMC4-WD-56 WD of SuperT Girder Span 30 (P29-P30)(2nd).pdf |
| 8/3/2018 | 535 | 535 SMC4-WD-57 WD of SuperT Girder Span 31 (P30-P31) (2nd).pdf |
| 8/4/2018 | 536 | 536 SMC4-MS-30A Method Statement of Traffic Control for Public Road at A1-P4 - Vol II.1 WD of Slope for Traffic Control.pdf |
| 8/4/2018 | 537 | 537 SMC4-MS-30B Method Statement of Traffic Control for Public Road at A1-P4 - Vol II.2 WD of Drainage System.pdf |
| 8/4/2018 | 538 | 538 SMC4-RP-23 Report on Survey of Existing Traffic Light System at HQV Intersection.pdf |
| 8/4/2018 | 539 | 539 SMC4-LC-119A-Approval for Utilizing Equipment & Materals Used by Widening Project for Construction of Road Connecting at A1-P4.pdf |
| 8/4/2018 | 540 | 540 SMC4-LC-173 Report on Land Obstruction during Installation of Fence at P3-P16.pdf |
| 8/6/2018 | 541 | 541 SMC4-LC-174 Submission of Monthly Report No.3.pdf |
| 8/8/2018 | 542 | 542 SMC4-MA-90 Technical Profile of Coarse Aggregate, Fine Aggregate & Water for Minh Tam Batching Plant.pdf |
| 8/8/2018 | 543 | 543 SMC4-MA-91 Report on Frequency Test of Reinforcing Steel for Cast In Place Concrete Piles of P33 & P34 (3rd).pdf |
| 8/8/2018 | 544 | 544 SMC4-MA-92 Report on Frequency Test of Reinforcing Steel for Cast In Place Concrete piles for P35 (2nd).pdf |
| 8/8/2018 | 545 | 545 SMC4-LC-175 Document for Mobilization of Additional Equipment Team 2 (3rd).pdf |
| 8/17/2018 | 546 | 546 SMC4-LC-176 Project Health and Safety Plan (2nd).pdf |
| 8/8/2018 | 547 | 547 3014-QD-BQLDATL Decision on Coordination Mechanism for Implementation of PK1 & PK2.pdf |
| 8/8/2018 | 548 | 548 3057-BQLDATL-DHDA1 To give comments on Traffic Signs Plan.pdf |
| 8/8/2018 | 549 | 549-3058-PMUTL-ĐHDA1 Coordination in Quality Management During Construction of PK2.pdf |
| 8/8/2018 | 550 | 550 SMC4-LC-177 Engineer's Confirmation for Safety & Environment Satisfaction (July 2018).pdf |
| 8/8/2018 | 551 | 551 SMC4-LC-178 Report on Additional Environmental Monitoring at Pre-Construction Phase (2nd).pdf |
| 9/4/2018 | 552 | 552 SMC4-LC-179 Proposal for 5th Additional Equipment Mobilization Document of Team 1 (Co.414).pdf |
| 8/9/2018 | 553 | 553 SMC4-MS-51 Submission of Traffic Control Plan for public Road for Construction at Sections P23-P28 & P38-P43.pdf |
| 8/10/2018 | 554 | 554 SMC4-LC-180 Notice on Environmental Monitoring Schedule in Aug 2018.pdf |
| 8/10/2018 | 555 | 555 SMC4-MA-93 Report on Trial Mix & Proposal for Approval Mix Proportion Grouting for PC Duct.pdf |
| 8/10/2018 | 556 | 556 SMC4-LC-181 Stamp of As-Built Drawing.pdf |
| 8/10/2018 | 557 | 557 SMC4-LC-182 Withdrawal of the letter SMC4-LC-016918 dated 28Jul18 & LC-017518 dated 7Aug18.pdf |
| 8/17/2018 | 558 | 558 SMC4-LC-183 Document for Mobilization of Additional Equipment of Team 2 ( 2nd).pdf |
| 8/14/2018 | 561 | 561 SMC4-LC-184 Notice for Leave for our Key Personnel (Project Manager).pdf |
| 8/14/2018 | 562 | 562 SMC4-LC-185 Request for Review & Approval of WD of Cast In Place Pile of P29L, P30L, P31L.pdf |
| 8/14/2018 | 563 | 563 SMC4-LC-186 Request for Review & Approve WD of Cast In Place Piles of Abutment A1, P1, P2, P4, P6-P8.pdf |
| 8/14/2018 | 564 | 564 SMC4-LC-187 Submission of Weekly Report No.13.pdf |
| 8/14/2018 | 565 | 565 SMC4-WD-61 WD of SuperT girder Span 34 (P33-P34).pdf |
| 8/14/2018 | 566 | 566 SMC4-WD-59 WD of SuperT Girder Span 33 (P32-P33).pdf |
| 8/14/2018 | 567 | 567 SMC4-LC-188 Proposal for Changing the Location of Static Load Test at P22.pdf |
| 8/14/2018 | 568 | 568 SMC4-MS-52 MS of Traffic Control for Public Road at A1-P22-Layout of Flagman, Signboard.pdf |
| 8/15/2018 | 569 | 569 SMC4-MA-94 Report on Frequency Test of Reinforcing Steel for Cast In PLace Piles of P21 and P22.pdf |
| 8/14/2018 | 570 | 570 SMC4-MA-95 Proposal of Mix Proportion for Trial Mix Class B1, C1, C3, C4, D, E, G & Y at Transmeco Batching Plant.pdf |
| 8/14/2018 | 571 | 571 3146-BQLDATL-DHDA1 Design Change of Pile cap of Pier and Abutment.pdf |
| 8/16/2018 | 572 | 572 SMC4-LC-189 Notice of Envioronmental Monitoring Schedule in August 2018 at Construction Phase (2nd).pdf |
| 8/18/2018 | 573 | 573 SMC4-SC-16 Document for Mobilization of Manpower & Equipment of Sub Contractor 423 Co. (2nd).pdf |
| 8/16/2018 | 574 | 574 SMC4-WD-58 WD of Substructure - Pile Cap of P21.pdf |
| 8/16/2018 | 575 | 575 SMC4-WD-60 WD of Substructure - Pile Cap of P20.pdf |
| 8/16/2018 | 576 | 576 3186-GM-BQLDATL Traffic Management.pdf |
| 8/16/2018 | 577 | 577 408-CQLXD-DB1 Report on Result of Site Inspection.pdf |
| 8/16/2018 | 578 | 578 SMC4-WD-62 WD of Substructure - Pile cap of P22.pdf |
| 8/16/2018 | 579 | 579 SMC4-WD-63 WD of Cast In Place Concrete Pile for P17.pdf |
| 8/17/2018 | 580 | 580 SMC4-RP-26 Report on Trial Excavation of Cast In Place Concrete Piles - Hole H3P22.pdf |
| 8/17/2018 | 581 | 581 SMC4-LC-190 Withdrawal of the Letter SMC4-LC-0122.18 dated 7 June 2018.pdf |
| 8/16/2018 | 582 | 582 448-GM-BQLCTGT Invitation-Fence Installation from Mai Dich Intersection to HQV Intersection.pdf |
| 8/17/2018 | 583 | 583 SMC4-LC-191 Prevention of the Storm No.4.pdf |
| 8/17/2018 | 584 | 584 SMC4-RP-24 Topographic Survey Report of Existing Drainage System.pdf |
| 8/17/2018 | 585 | 585 SMC4-RP-25 Topographic Survey Report at Section ( fr Km0+ 880 to Km1+00) after Box Culvert is Completed by Widening Project.pdf |
| 8/23/2018 | 586 | 586 SMC-LC-192 Result of Ultrasonic Test of CIP Concrete Piles at P35C.pdf |
| 8/20/2018 | 587 | 587 SMC4-MS-53 Traffic Control Plan for Public Road for Construction at P23-P28.pdf |
| 8/20/2018 | 588 | 588 SMC4-LC-0195-Proposal for WD of Structure Excavation & Backfill for Section P29-P37 (2nd).pdf |
| 8/20/2018 | 589 | 589 SMC4-LC-196 Report of Trial Excavation of Underground Utilities on the Central Median Stage 2 P29-P37 (1st).pdf |
| 8/24/2018 | 590 | 590 SMC4-SC-17 Document for Mobilization of Equipment for Structure Excavation Work of Sub Contractor Co.479.pdf |
| 8/21/2018 | 591 | 591 SMC4-LC-194 Design Change Document for Replacement of Rotation Steel Pile with CIP Concrete Pile at P9-P15 P45-P58- Option 2.pdf |
| 9/13/2018 | 592 | 592 SMC4-LC-193 Design Change Document for Replacement of Rotation Steel Pile with CIP Concrete Pile at P9-P15 & P45-P58, Option 1- 9 Piles per 1 Pile Cap.pdf |
| 8/20/2018 | 593 | 593 SMC4-MS-54 General Traffic Control Plan for Public Road for Construction Stage 1- Construction Bored Piled Pile & Substructure.pdf |
| 8/20/2018 | 594 | 594 SMC4-MA-96 Capacity Profile of Manufaturer & Supplier for PVC Pipe Material Thuan Phat & Hiep An JSC.pdf |
| 8/30/2018 | 595 | 595 SMC4-LC-197 Result of Ultrasonic Test of CIP Concrete Piles at P31.pdf |
| 8/20/2018 | 596 | 596 SMC4-LC-198 Submission of weekly report No.14.pdf |
| 8/22/2018 | 597 | 597 SMC4-LC-199 Notice of Equipment Demobilization of Team 1.pdf |
| 8/22/2018 | 598 | 598 SMC4-MA-97 Capacity Profile of Company Carries Our Galvanizing Work An Viet Co..pdf |
| 8/22/2018 | 599 | 599 SMC4-LC-202-Notice of Equipment Demobilization of Sub Contractor Co.423.pdf |
| 8/23/2018 | 600 | 600 SMC4-MA-98-Report on Frequency Test of Cement, Crushed Stone, Yellow Sand for Cement Concrete at Asean BP (2nd).pdf |
| 8/22/2018 | 601 | 601 SMC4-MA-99 Report on Frequency Test of Reinforcing Steel for Pile Cap & Pier Column of P33, P34, P35 (1st).pdf |
| 8/22/2018 | 602 | 602 SMC4-MA-100 Additional Submission of Report on Frequency Test of Cement for Cement Concrete at ASEAN BP (1st).pdf |
| 8/22/2018 | 603 | 603 SMC4-WD-64 WD of SuperT Girder Span 20 (P19-P20).pdf |
| 8/22/2018 | 604 | 604 SMC4-WD-65 WD of Super T Girder Span 21 (P20-P21).pdf |
| 8/22/2018 | 605 | 605 SMC4-WD-66 WD of SuperT Girder Span 22 (P21-P22).pdf |
| 8/22/2018 | 606 | 606 SMC4-LC-201 Report on Environmetnal Monitoring at Construction Phase.pdf |
| 8/22/2018 | 607 | 607 287-GM-SGTVT Invitation Date 23.8.pdf |
| 8/22/2018 | 608 | 608 SMC4-LC-203 Notice of Equipment Demobilization of Team 1.pdf |
| 8/23/2018 | 609 | 609 SMC4-RP-26 Report on Trial Excavation of CIP Pile -Hole No. H9P36.pdf |
| 8/29/2018 | 610 | 610 SMC4-RP-27 Topographic Survey Report Stage 3 (Km1+300 to Km1+540).pdf |
| 8/23/2018 | 611 | 611 SMC4-MA-101 Capacity Profile of Borrow Material Manufacturer Minh Dat JSC & Supplier Diep Trang Co.LTD.pdf |
| 8/23/2018 | 612 | 612 SMC4-LC-204 TOR & Cost Estimate for Environmental Monitoring (4th).pdf |
| 8/27/2018 | 613 | 613 SMC4-MA-102 Report on Test of Coupler & Steel Plate for Grading of Viet A Machine Co.LTD.pdf |
| 8/27/2018 | 614 | 614 SMC4-LC-205 Submission of Result of Ultrasonic Test of CIP Concrete Pile at P30.pdf |
| 9/27/2018 | 615 | 615 SMC4-LC-206 Replacement of Contractor's Key Personnel.pdf |
| 8/27/2018 | 616 | 616 SMC4-LC-207 Submission of Result of Ultrasonic Test of CIP Concrete Piles at P34C.pdf |
| 8/27/2018 | 617 | 617 SMC4-LC-208 Submission of Weekly Report No.15.pdf |
| 9/18/2018 | 618 | 618 SMC4-WD-67 WD of Substructure- Pile Cap P29 (2nd).pdf |
| 9/18/2018 | 619 | 619 SMC4-WD-68 WD of Substructure- Pile Cap of P31(2nd).pdf |
| 8/27/2018 | 620 | 620 SMC4-WD-69 WD of Substructure- Column & Pier Head of P31.pdf |
| 9/18/2018 | 621 | 621 SMC4-WD-70 WD of Substructure- Pile Cap of P30 (2nd).pdf |
| 8/28/2018 | 622 | 622 SMC4-LC-209 Additional cranes Mobilization Document of Team 1 (414 Co) at Fabrication Yard.pdf |
| 8/28/2018 | 623 | 623 3313-PMUTL-DHDA1 Traffic Control, Labor Safety, Enviroment Sanotation during Construction.pdf |
| 8/28/2018 | 624 | 624 SMC4-WD-71 WD of CIP Concrete Pile for P23.pdf |
| 8/28/2018 | 625 | 625 SMC4-WD-72 WD of CIP Concrete Pile for P24.pdf |
| 8/28/2018 | 626 | 626 SMC4-WD-73 WD of CIP Concrete Pile for P28.pdf |
| 8/28/2018 | 627 | 627 3353-PMUTL-DA1 Approval of TOR & Cost Estimates for Test on RC Pile.pdf |
| 8/29/2018 | 628 | 628 Working Minutes 16Aug18 On Checking, review & Assessment of the Status of Traffic Control & Agree on the Adjustment Plan.pdf |
| 8/30/2018 | 629 | 629 3374 PMUTL-DA1 Some Contents of Detailed Design Document and Technical Specifications.pdf |
| 8/30/2018 | 630 | 630 SMC4-LC-0210 Term of Reference & Cost Estimate for General Traffic Control for Public Roads for Construction Stage 1- Construction of Bored Piles & Substructures.pdf |
| 8/30/2018 | 631 | 631 SMC4-MA-103 Capacity Profile of Manufacturer & Supplier of Bituminous Waterproofing for Concrete - Ha An JSC.pdf |
| 8/30/2018 | 632 | 632 SMC4-LC-211 Document for Mobilization of Equipments for Structure Excavation Work of 423 Co..pdf |
| 8/30/2018 | 633 | 633 SMC4-LC-212 Supplement Document of Team 1 (Co. 414).pdf |
| 8/30/2018 | 634 | 634 SMC4-LC-213 Additional Manpower Document for Foreman of Co.423.pdf |
| 9/1/2018 | 635 | 635 SMC4-LC-214 Design Change Document for Drainage System on Bridge.pdf |
| 9/1/2018 | 636 | 636 SMC4-LC-215 Notice on National Holiday Schedule of the Contractor.pdf |
| 9/1/2018 | 637 | 637 SMC4-MA-104 Additional Capacity Profile of Manufacturer & Supplier VietThang Co. for Steel Plate, Joint Steel for Head of RC Pile & Auxiliary Steel Material.pdf |
| 9/1/2018 | 638 | 638 SMC4-MA-105 Report on Frequency Test of Cement, Crushed Stone, Yellow Sand for Cement Concrete at ASEAN BP (3rd).pdf |
| 9/1/2018 | 639 | 639 SMC4-WD-74 WD of CIP Pile for P16.pdf |
| 9/1/2018 | 640 | 640 SMC4-WD-75 WD of CIP Pile for P25.pdf |
| 9/1/2018 | 641 | 641 SMC4-WD-76 WD of CIP Pile for P26.pdf |
| 9/1/2018 | 642 | 642 SMC4-WD-77 WD of CIP Pile for P27.pdf |
| 9/5/2018 | 643 | 643 SMC4-MS-56 Traffic Control Method for Public Roads- Removal Traffic Light System at HQV Intersection.pdf |
| 9/1/2018 | 644 | 644 SMC4-LC-218 Application for IPC No.3 -Period 01Aug to 31Aug18.pdf |
| 9/1/2018 | 645 | 645 SMC4-MS-55 Traffic Control Plan for Public Road at P23-P28 & P38-P43 (2nd).pdf |
| 9/1/2018 | 646 | 646 SMC4-LC-217 Changing Hook Shape of Rebar F9, C2A, C3, C4, C5, C6 of Substructure.pdf |
| 9/5/2018 | 647 | 647 Working Minutes 17Aug18 Coorperation for Construction Implementation & Traffic Control of HRR3.pdf |
| 9/5/2018 | 648 | 648 SMC4-LC-219 Engineer's Confirmation for Safety & Environment Satisfaction (Aug2018).pdf |
| 9/5/2018 | 649 | 649 SMC4-SC-19 Document for Mobilization of Drilling Machine of Team 2- 407 Co..pdf |
| 9/5/2018 | 650 | 650 SMC4-LC-220-Submission of Weekly Report No.16.pdf |
| 9/5/2018 | 651 | 651 SMC4-LC-221-Submission of Monthly Report No.4.pdf |
| 9/5/2018 | 652 | 652 3455 PMUTL-DHDA1 Coordination in Implementation of Package 11 Quality Inspection of the Works.pdf |
| 9/5/2018 | 653 | 653 3457 GM-BQLDATL Invitation date 5.9.18.pdf |
| 9/6/2018 | 654 | 654 SMC4-MA-106 Report on Frequency Test of Cement for Grouting Sonic Tube use for P29 to P37.pdf |
| 9/6/2018 | 655 | 655 SMC4-MA-107 Report on Frequency Test of Water for Grouting Sonic Tube.pdf |
| 9/6/2018 | 656 | 656 3468-GM-BQLDATL Working on the Matters of Price Adjustment & Enviromental Monitoring.pdf |
| 9/6/2018 | 657 | 657 3469-TB-BQLDATL Notice on Conclusions Given by PMUTL in the Meeting to Review the Implementation.pdf |
| 9/7/2018 | 658 | 658 SMC4-LC-222 Notice of Equipment Demobilization of Team 1.pdf |
| 9/7/2018 | 659 | 659 SMC4-MS-57-Supplement & updating the MS of Trial Excavation & CIP Concrete Piling from P23-P28.pdf |
| 9/7/2018 | 660 | 660 SMC4-LC-174A-Submission of Weekly Report No.12.pdf |
| 9/10/2018 | 661 | 661 SMC4-RP-28 Topographic Survey Report of Existing Drainage System (2nd).pdf |
| 9/10/2018 | 662 | 662 SMC4-MS-58 Method Statement of Pier Column 1st Stage from P29-P37 and Ramp (P29L to P31L).pdf |
| 9/10/2018 | 663 | 663 SMC4-LC-223 Additional Supervision Cost of Engineer's Staff (upto July 2018).pdf |
| 9/10/2018 | 664 | 664 SMC4-LC-224 Changing Blast Cleaned & Inorganic Zinc Rich Primer at Steel Mill into Blast Cleaned & Inorganic Zinc Rich Primer at Fabrication Factory.pdf |
| 9/20/2018 | 665 | 665 SMC4-LC-225 Additional Mobilization of Mainpower & Equipment by Subcontractor Thanh Long JSC for Test on RC Pile.pdf |
| 9/11/2018 | 666 | 666 SMC4-MA-108 Information on the Super T Cable Tensioning Equipment of the Constructure Team 2 -414 Co..pdf |
| 9/15/2018 | 667 | 667 SMC4-LC-227 TOR of Ultrasonic Test, Tip Contact tChecking Test, Static Loading Test and PDA of Pre cast Concrete Pile & CIP Concrete Pile(4th).pdf |
| 9/11/2018 | 668 | 668 SMC4-LC-226 Submission of Weekly Report No.17.pdf |
| 9/11/2018 | 669 | 669 836-TB-UBND Notice Conclusions by the Chairman of Hanoi People's Committee at the Meeting on Land Acquisition and Inplementation of Projects.pdf |
| 9/11/2018 | 670 | 670 3540 Notice on Conclusions Given By Leader PMUTL in the Meeting on Environmental Monitoring & Price Adjustment.pdf |
| 9/12/2018 | 671 | 671 3543 PMUTL-DHDA1 Implementation of MOT's Instructions Vide Letters No.10172-BGTVT-CQLXD & 107173-BGTVT-CQLXD.pdf |
| 9/13/2018 | 672 | 672 01-CDEDE-BCHIV-MDNTL Report on the Implementation on JULY18 HIV-AIDS Prevention Program.pdf |
| 9/13/2018 | 673 | 673 02-CDEDE-BCHIV-MDNTL Report on the Implementation on Aug18 HIV-AIDS Prevention Program.pdf |
| 9/13/2018 | 674 | 674 SMC4-LC-228 Notice on Implementation of Assembling Work for Gantry Crane Group 3 Co.414 at Super T Farbrication Yard.pdf |
| 9/13/2018 | 675 | 675 SMC4-LC-229 Result of Ultrasonic Test of CIP Concrete Piles at P37.pdf |
| 9/22/2018 | 676 | 676 SMC4-LC-230 Certification on Performance of the Laboratory Satisfying Requirement (8.2018).pdf |
| 9/25/2018 | 677 | 677 SMC4-LC-231 Certification of Satisfatory Laboratory Operation (8.2018).pdf |
| 9/13/2018 | 678 | 678 SMC4-LC-232 Submission of Updated Cost Estimate of Test on Concrete Piles.pdf |
| 9/13/2018 | 679 | 679 SMC4-MA-109 Profile of Manufacturer & Supplier for Rubber Bearing Kawakin -THQ JSC (2nd).pdf |
| 9/13/2018 | 680 | 680 SMC4-LC-233 Reply to the Engineer's Letter Regarding Document for Mobilization of Drilling Machine of Team 2 Co.407.pdf |
| 9/14/2018 | 681 | 681 SMC4-MS-59 MS of Traffic Control at section A1-P22-Vol III.2 ...- Stage 2 Open the Left Side & Right Side at P3-P16.pdf |
| 9/14/2018 | 682 | 682 SMC4-MA-110 Characteristic Strength for Concrete Class Y of Asean BP- Report No.01.pdf |
| 9/22/2018 | 683 | 683 SMC4-LC-234 Response to the Engineer's Request on Overtime Supervision Expense for Safety & Environment Monitoring Works.pdf |
| 9/14/2018 | 684 | 684 SMC4-LC-236 Submission of Result of Ultrasonic Test of CIP COncrete Piles at P33C.pdf |
| 9/19/2018 | 685 | 685 SMC4-MA-0111 Report on Test Result of Granular Backfilling Material & Blinding Stone Material at Trung Do Moutain ( KV5), Cao Duong Commune, Luong Son, Hoa Binh.pdf |
| 9/17/2018 | 686 | 686 SMC4-LC-237 Document for Addtional Mobilization of Equipments for Structure Excavation Work of the Sub Contractor 479 Co..pdf |
| 9/18/2018 | 687 | 687 SMC4-LO-23 Exchange Rate - VAT Amount.pdf |
| 9/18/2018 | 688 | 688 SMC4-LC-238 Notice of Equipment Demobilization of Sub Contractor 423 Co..pdf |
| 9/18/2018 | 689 | 689 SMC4-LC-239 Submission of weekly report No.18.pdf |
| 9/21/2018 | 690 | 690 SMC4-MS-60 Method statement of Demolition & Relocation of Existing Utilities (stage 1).pdf |
| 9/19/2018 | 691 | 691 SMC4-MS-61 MS of Temporary Facilities Arrangement on Site from P38-P43.pdf |
| 9/19/2018 | 692 | 692 SMC4-MS-62 MS of Temporary Facilities Arrangement on Site from P23-P29.pdf |
| 9/19/2018 | 693 | 693 SMC4-MA-114 Capacity of Anufacturer & Supplier of Bolds & Stud Shear Connectors of Steel Bridge.pdf |
| 9/19/2018 | 694 | 694 SMC4-WD-78 WD of SuperT Girder Span 10-16 and 23-26.pdf |
| 9/19/2018 | 695 | 695 SMC4-MA-112 Report on Frequency Test of Reinforcing Steel for Pile Cap & Column of P29, 30, 31(1st).pdf |
| 9/19/2018 | 696 | 696 SMC4-MA-113 Capacity Profile of Building Material & Geotechnics Laboratories LAS-XD 175.pdf |
| 9/19/2018 | 697 | 697 SMC4-LC-240 Request for Detail Instruction on Legal Basis of Flagman for Traffic Control.pdf |
| 9/19/2018 | 698 | 698 SMC4-LC-241 Reply to The Consultant's Letter RE1-0263 Regarding Confirmation of Safety & Environmental Satisfaction (Aug2018).pdf |
| 9/19/2018 | 699 | 699 SMC4-MA-115 Minutes of Checking Hot Dip Galvanized Factory An Viet Company.pdf |
| 9/19/2018 | 700 | 700 SMC4-MA-116 Report on Frequency Test of Reinforcing Steel for Pile Cap & Column of P36, P37.pdf |
| 9/19/2018 | 701 | 701 SMC4-Acceptance Invitation 19Sep2018.pdf |
| 9/20/2018 | 702 | 702 SMC4-AD-01 As-Built Drawings of CIP Concrete Pile for Pier P31.pdf |
| 9/20/2018 | 703 | 703 SMC4-MA-118 Report on Frequency Test of PC Strand for Super T Girder (1st).pdf |
| 9/20/2018 | 704 | 704 SMC4-MA-117 Report on Frequency Test of Cement for Grouting Sonic Tube (2nd).pdf |
| 9/20/2018 | 705 | 705 SMC4-RP-29 Submision of Report on Trial Excavation of CIP Concrete Piles- Hole H3'P20.pdf |
| 9/21/2018 | 706 | 706 SMC4 Acceptance Invitation.pdf |
| 9/21/2018 | 707 | 707 SMC4-MA-119 Capacity Profile of Manufacturer & Supplier of No-Shrink, Flowable Grout -Nutech Jsc.pdf |
| 9/21/2018 | 708 | 708 SMC4-WD-79 WD of Substructure - Pile cap of P34 (2nd).pdf |
| 9/21/2018 | 709 | 709 SMC4-WD-80 WD of Substructure - Pile cap of P36 (2nd).pdf |
| 9/21/2018 | 710 | 710 SMC4-WD-81 WD of Substructure - Pile cap of P37 (2nd).pdf |
| 9/21/2018 | 711 | 711 SMC4-LC-242 Notice on Enviromental Monitoring Schedule in Sep18 in the Construction Phase.pdf |
| 9/22/2018 | 712 | 712 SMC4-LC-243 Report on Environmental Monitoring at Construction Phase (August 2018).pdf |
| 9/24/2018 | 713 | 713 SMC4-MS-65 Method Statement of Structure Excavation from P19-P22.pdf |
| 9/24/2018 | 714 | 714 SMC4-MS-64 Traffic Control Plan for Public Road at P23-P28 & P38-P43 Left Side (3rd).pdf |
| 9/24/2018 | 715 | 715 SMC4-WD-83 WD of SuperT Girder Span P37 (2nd).pdf |
| 9/24/2018 | 716 | 716 SMC4-WD 82 WD of Super T Girder Span 36 (P35-P36) (2nd).pdf |
| 9/24/2018 | 717 | 717 SMC4-WD-84 WD of Substruture - Pile Cap of P33 (2nd).pdf |
| 9/24/2018 | 718 | 718 SMC4-WD-85 WD of Substruture - Pile Cap of Pier P35 (2nd).pdf |
| 9/25/2018 | 719 | 719 SMC4-MA-121 Report on Frequency Test of Cemen, Crushed Stone, Yellow Sand for Cement Concrete at Asean BP (4th).pdf |
| 9/25/2018 | 720 | 720 SMC4-LC-246 Submission of Weekly Report No.19.pdf |
| 9/25/2018 | 721 | 721 SMC4-MA-120 Profile of Manufacturer & Supplier for Steel Plate, Shape, Filler Metal for Steel Bridge Hyundai Cor. Thanh Long Group JSC.pdf |
| 11/13/2018 | 722 | 722 SMC4-LC-245 Variation Order 001- Test on Concrete Piles & Rotation Steel Piles - Part 1 Test in Concrete Piles.pdf |
| 9/27/2018 | 723 | 723 SMC4-LC-244 Report on Environmental Monitoring in Construction Phase in Aug 2018 ( base on Specification).pdf |
| 9/26/2018 | 724 | 724 SMC4-LC-247 Submission of Environmental Protection Plan for Fabrication Yard.pdf |
| 9/26/2018 | 725 | 725 SMC4-MS-66 MS of Traffic Control for PR at A1-P22 - Vol III.3 Playout of Flag man, Signboard for Traffic Control ( Stage 3- Construction P7-P17 & P18-P22).pdf |
| 9/26/2018 | 726 | 726 SMC4-MA-122 Capacity Profile of Manufacturer & Supplier of Bridge Bearings ( Elastomeric Bearing & Pot Bearing).pdf |
| 9/26/2018 | 727 | 727 SMC4-MA-123 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P19 & P20.pdf |
| 10/3/2018 | 728 | 728 SMC4-RP-30 Topographic Survey Report at Km1+910-Km2+150 (left side).pdf |
| 9/26/2018 | 729 | 729 SMC4-LC-248 Schedule for Document Submission & Organization Chart of Steel Bridge.pdf |
| 9/26/2018 | 730 | 730 SMC4-MA-124 Report on Frequency Test of Reinforcing Steel for Super T Girder (1st) of Team 1.pdf |
| 9/26/2018 | 731 | 731 SMC4-LC-249 Request for Speeding up Land Handover for PK1 (Km0+130-Km2+812.5).pdf |
| 9/26/2018 | 732 | 732 3773-PMUTL-DHDA1 Interim Payment Certificate (ICP) No.2 PK1.pdf |
| 9/27/2018 | 733 | 733 540-GM-BQLCTGT Meeting for Agreement on Relocation-Connection Raw Water Pipeline DN500 & Fresh Water Pipeline DN300.pdf |
| 9/28/2018 | 734 | 734 SMC4-MA-125 Report on Test Result of uPVC Pipe - North Binh Minh Co.,ltd.pdf |
| 9/28/2018 | 735 | 735 SMC4-MA-126 Capacity Profile of Manufacturer for PC duct - Ngoc Lam Co LTD (3rd).pdf |
| 9/28/2018 | 736 | 736 SMC4-MA-127 Capacity Profile of Manufacturer & Supplier for Epoxy Coated PC Trand & Anchorage- ZHEMAO Co.,ltd - Vinh Hung JSC(2nd).pdf |
| 9/29/2018 | 737 | 737 SMC4-MA-128 Report on Test Result of Steel Plate for Grading, Steel Plate, Joint Steel for RC Pile Head & Auxiliary Steel Material- Viet Thang Co.,Ltd.pdf |
| 9/28/2018 | 738 | 738 SMC4-AD-02 As-built Drawing of CIP Concrete Pile for P34C.pdf |
| 9/28/2018 | 739 | 739 SMC4-MA-121A Report on Ferequency Test of Reinforcing Steel fo CIP Concrete Pile P36, P38, P39, P40.pdf |
| 9/28/2018 | 740 | 740 SMC4-LC-241A Report for Static Loading Test of CIP Concrete Piling C5-P35.pdf |
| 9/28/2018 | 741 | 741 SMC4-WD-86 WD of CIP Concrete Pile for P38.pdf |
| 9/28/2018 | 742 | 742 SMC4-WD-87 WD of CIP Concrete Pile for P39.pdf |
| 9/28/2018 | 743 | 743 SMC-WD-88 WD of CIP Concrete Pile for P40.pdf |
| 9/28/2018 | 744 | 744 SMC4-MS-67 MS of Assembling & Loading Test of Gantry Crane at Fabrication Yard for Super T Girder of Group 2 Co.407.pdf |
| 9/28/2018 | 745 | 745 SMC4-MS-68 MS of Temporary Facilities Arrangement on Site from P38-P43 (2nd).pdf |
| 9/28/2018 | 746 | 746 SMC4-LT-16 Inspection Minute of Building Material & Geotechnics Laboratories LAS-XD 175.pdf |
| 9/29/2018 | 747 | 747 3812-BQLDATL-DA1 Approval for Contractor's Proposal of Key Personnel.pdf |
| 10/1/2018 | 748 | 748 SMC4-MS-69 MS of Traffic Control for Public Road during the Trial Fencing Installation at P23-P28 & P38-P43 left side.pdf |
| 10/1/2018 | 749 | 749 SMC4-MS-70 Calculation for Pre-Stressing of Super TGirder 38m - Group 3 (414 Co.).pdf |
| 10/1/2018 | 750 | 750 SMC4-MA-129 Report on Test Result of Jack, Anchorage & Synchronous Experiment of Jack, PC Strand, Anchorage for Construction Super T Girder(1st).pdf |
| 10/1/2018 | 751 | 751 SMC4-LC-251 Engineer's Confirmation for Safety & Environment Satisfaction (Aug2018).pdf |
| 10/1/2018 | 752 | 752 SMC4-LC-250 Resubmit Additional Supervision Cost of Engineer Staff ( Up to July2018).pdf |
| 10/1/2018 | 753 | 753 SMC4-LC-252 Design Change of Foundation Structure at Some Location of Piers, Abutments.pdf |
| 10/1/2018 | 754 | 754 SMC4-LC-253 Notice of Equipment Demobilization of Team 2- 407 Co..pdf |
| 10/2/2018 | 755 | 755 3855-BQLDATL-DHDA1 Invitation letter of Fencing & Traffic Lane Distribution on PVD Road for Execution of the PVD Road for Execution of the Project (Stage 3).pdf |
| 10/2/2018 | 756 | 756 769-TB-SGTVT Notice on Fencing & Traffic Lane Distribution on PVD Road for Execution of the Project (stage 3).pdf |
| 10/3/2018 | 757 | 757 SMC4-LC-254 Withdrawal of Letter MS-57 dated 7 Sep 2018.pdf |
| 10/3/2018 | 758 | 758 SMC4-MS-72 Supplement & Updating the MS Plan Drawing of CIP Concrete Pile P38-P43.pdf |
| 10/3/2018 | 759 | 759 SMC4-MS-71 Supplement & Re Updating the MS Plan Drawing of Trial Excavation & CIP Concrete Pile P23-P28.pdf |
| 10/3/2018 | 760 | 760 3827-BQLDATL-DHDA1 The Payment for the Interim Payment Certificate No.02 of PK1.pdf |
| 10/16/2018 | 761 | 761 SMC4-LC-255 Resubmit for Interim Payment Certificate No.03 ( period 1Aug2018 to 31Aug2018).pdf |
| 10/4/2018 | 762 | 762 SMC4-LC-256 Reply to the Letter RE1-0316-1.70 dated 27 Sep 2018.pdf |
| 10/4/2018 | 763 | 763 SMC4-LC-257 Changing Position of Cable C7, C8, C9 in Pier Head - B24M-Type CA1, CB1.pdf |
| 10/4/2018 | 764 | 764 SMC4-LC-258 Submission of Weekly Report No.20.pdf |
| 10/4/2018 | 765 | 765 SMC4-LC-259 Submission of Monthly Report No.5.pdf |
| 10/12/2018 | 766 | 766 SMC4-MS-73 MS of Temporary Facilities Arrangement on Site from P23-P29 (2nd).pdf |
| 10/4/2018 | 767 | 767 SMC4-LC-260 Notice on Implementation of Assembling Work for Gantry Crane Group 2-407 Co. at Super T Fabrication Yard.pdf |
| 10/5/2018 | 768 | 768 SMC4-LC-254A Interim Payment Certificate No.02 Period 01June2018 to 31July2018.pdf |
| 10/4/2018 | 769 | 769 SMC4-LC-262 Submission of Result of Tip Contact Checking Test of CIP Concrete Piles at C3-P30.pdf |
| 10/4/2018 | 770 | 770 SMC4-MA-130 Technical Profile of Coarse Aggregae, Fine Aggegate & Water for Home World Batching Plant.pdf |
| 10/4/2018 | 771 | 771 SMC4-LC-261 Withdrawal of the Letter SMC4-LC-0254A18 dated 03 October, 2018.pdf |
| 10/5/2018 | 772 | 772 SMC4-LP-25 Submission of VAT Invoices for Interim Payment Certificate No.02 PK1.pdf |
| 10/6/2018 | 773 | 773 SMC4-LC-264 Notice of Environmental Monitoring Schedule in Oct 2018 at Construction Phase.pdf |
| 10/6/2018 | 774 | 774 SMC4-LC-263 Notice on Temporary Suspension of Environmental Monitoring at Some Locations.pdf |
| 10/6/2018 | 775 | 775 SMC4-WD-90 WD of CIP Concrete Pile for P41.pdf |
| 10/6/2018 | 776 | 776 SMC4-MS-74 MS of Demolition & Relocation of Existing Utilities (stage 3).pdf |
| 10/6/2018 | 777 | 777 SMC4-MA-131 Capacity Profile of Manufacturer & Supplier for Painting Material for Steel Bridge Hai Phong Paint JSC.pdf |
| 10/6/2018 | 778 | 778 SMC4-MA-133 Report on Test Result of PC Strand 15.2 of Dong il Steel MFG Co.Ltd.pdf |
| 10/6/2018 | 779 | 779 SMC4-MA-130A Report on Frequency Test of Cement, Cushed Stone, Yellow Sand, Admixture & Water for Cement Concrete at ASEAN (5th).pdf |
| 10/6/2018 | 780 | 780 SMC4-WD-89 WD of SuperT Girder Span 35 (P34-P35) (2nd).pdf |
| 10/6/2018 | 781 | 781 SMC4-MA-132 Capacity Profile of Batching Plant Viet Tiep.pdf |
| 10/6/2018 | 782 | 782 Working Minutes 03Oct2018 Evaluation of the Actual Situation of Traffic Division & Organization under the 225 & Checking the Trial Fencing Work under 769 of DOT.pdf |
| 10/6/2018 | 783 | 783 Minutes of Handing Over Traffic Signal System 09 Oct 2018 in HQV & Nam Cuong Intersection.pdf |
| 10/6/2018 | 784 | 784 SMC4-LC-265 Engineer's Confirmation for Safety & Environment Satisfation ( Sep2018).pdf |
| 10/6/2018 | 785 | 785 SMC4-LC-266 Notice of Equipment Re Mobilization for Construction.pdf |
| 10/8/2018 | 786 | 786 SMC4-AD-03 Proposal for Approval of As-Built Drawing of CIP Concrete Pile for Pier P33C.pdf |
| 10/8/2018 | 787 | 787 SMC4-MA-134 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P33, P34 (4th).pdf |
| 10/9/2018 | 788 | 788 SMC4-MA-135 Report on Test Result of uPVC Pipe for SuperT Gider & Proposal for uPVC Pipe used for Drainage System of Thuan Phat JSC.pdf |
| 10/9/2018 | 789 | 789 SMC4-LC-267 Submission of Weekly Report No.21.pdf |
| 10/9/2018 | 790 | 790 SMC4-WD-91 WD of CIP Concrete Pile for P42.pdf |
| 10/9/2018 | 791 | 791 SMC4-WD-92 WD of CIP Concrete Pile for Pier P43.pdf |
| 10/9/2018 | 792 | 792 SMC4-WD-93 Calculation Sheet for Camber Steel Girder.pdf |
| 10/11/2018 | 793 | 793 SMC4-WD-94 WD of Substructure - Column and Pier Head of P31 (2nd).pdf |
| 10/10/2018 | 794 | 794 Acceptance Invitation 09Oct2018 of Completion of Pile Foundation at P33C.pdf |
| 10/10/2018 | 795 | 795 SMC4-LC-268 Design Change of Foundation Structure at Some Location of Piers, Abutments.pdf |
| 10/11/2018 | 796 | 796 SMC4-AD-04 Approval of As built Drawings of Cast In Place Concrete Pile for P37.pdf |
| 11/1/2018 | 797 | 797 SMC4-MS-75 Temporary Traffic Control Plan at Sections A1-P22 & P29-P37.pdf |
| 10/11/2018 | 798 | 798 SMC4-LC-269 Result of Environment Monitoring at Construction Phase (1st Sep2018. Parameter TSP).pdf |
| 10/11/2018 | 799 | 799 SMC4-MS-76 Traffic Control Method for Public Roads - Relocation of Light System at HQV (2nd).pdf |
| 10/11/2018 | 800 | 800 SMC4-MA-136 Report on Test Result of Bituminous Waterproofing for Concrete HAN BT.pdf |
| 10/11/2018 | 801 | 801 SMC4-MA-137 To Choose the Paint for Concrete Structure & Completion Paint Layer of Steel Structure.pdf |
| 10/11/2018 | 802 | 802 SMC4-WD-95 WD of CIP Concrete Pile for P32C (2nd).pdf |
| 10/11/2018 | 803 | 803 SMC4-MS-77 MS of Temporary Facilities Arrangement on Site From P38-P43 (3rd).pdf |
| 10/12/2018 | 804 | 804 Acceptance Invitation of Completion of Pile Foundation at P37 11Oct18.pdf |
| 10/12/2018 | 805 | 805 SMC4-MA-138 Report on Test of Reinforcing Steel for Pile Cap, Pile Column, Pier Head P29, P30, P31.pdf |
| 10/12/2018 | 806 | 806 SMC4-MA-139 Report on Test Result of Borrow Material.pdf |
| 10/17/2018 | 807 | 807 SMC4-WD-96 WD of Substructure - Pile Cap P20 (2nd).pdf |
| 10/17/2018 | 808 | 808 SMC4-WD-97 WD of Substructure - Pile Cap of P21 (2nd).pdf |
| 10/17/2018 | 809 | 809 SMC4-WD-98 WD of Substructure of Substructure - Pile Cap of P22 (2nd).pdf |
| 10/12/2018 | 810 | 810 SMC4-WD-99 WD of Demolition & Removal of Existing Utilities - Drainage System from P26-P35.pdf |
| 10/12/2018 | 811 | 811 SMC4-WD-100 WD of Structure Excavation & Backfill for P29-P37 (3rd).pdf |
| 10/12/2018 | 812 | 812 SMC4-MC-05 Application for IPC No.4.pdf |
| 10/12/2018 | 813 | 813-03-CDECE-Report on Implementation HIV-AIDS Prevention Program (Sept.2018).pdf |
| 10/15/2018 | 814 | 814 4004 GM-BQLDATL Invitation Letter.pdf |
| 10/22/2018 | 815 | 815 SMC4-LC-270 Result of Ultrasonic Test of CIP Concrete Piles at P21.pdf |
| 10/15/2018 | 816 | 816 SMC4-MA-142 Report on Test Result of Jack, Anchorage & Synchronous Experiment of Jack, PC Strand, Anchorage for Construction Super T Girder (2nd).pdf |
| 10/15/2018 | 817 | 817 SMC4-MA-141 Report on Frequency Test of PC Strand for SuperT Girder (2nd time).pdf |
| 10/15/2018 | 818 | 818 SMC4-MA-140 Report on Frequency Ttest of Reinforcing Steel for CIP Concrete Piles of Pier P35 (3rd time).pdf |
| 10/15/2018 | 819 | 819 SMC4-MS-78 Calculation for Pre-Stressing of SuperT Girder 28m-Group No.2 (407 Co).pdf |
| 10/15/2018 | 820 | 820 SMC4-MA-143 Report on Frequency Test of Reinforcing Steel for SuperT Girder (1st time) of Team 2.pdf |
| 10/16/2018 | 821 | 821 SMC4-AD-05 As-built Drawing of CIP Concrete Pile for P21 (1).pdf |
| 10/16/2018 | 822 | 822 SMC4-LC-271 Additional Supervision Cost of Engineers Staff (August 2018).pdf |
| 10/16/2018 | 823 | 823 SMC4-WD-100A WD of Substructure- Column & Pier Head of P34.pdf |
| 10/17/2018 | 824 | 824 SMC4-LC-272 Schedule for Document Submission & Organization Chart of Steel Bridge.pdf |
| 10/17/2018 | 825 | 825 SMC4-LC-273 Submission of Weekly Report No.22.pdf |
| 10/17/2018 | 826 | 826 SMC4-MS-79 Traffic Control Plan for Public Road for Construction at P7-P17 (2nd).pdf |
| 10/17/2018 | 827 | 827 SMC4-MA-144 Profile of Supplier Thang Long JSC for Borrow Material of Minh Dat JSC.pdf |
| 10/17/2018 | 828 | 828 SMC4-AD-06 Proposal for AD of CIP Concrete Pile for P29.pdf |
| 10/17/2018 | 829 | 829 SMC4-AD-07 Proposal for AD of CIP Cocrete Pile P30.pdf |
| 10/17/2018 | 830 | 830 SMC4-MS-80 MS for Assembling & Loading Test of Gantry Crane at Fabrication Yard for Super T Girder of Group No.01 -Co.422.pdf |
| 10/17/2018 | 831 | 831 SMC4-LC-274 Submission of Result of Ultrasonic Test of CIP Concrete Piles at P22.pdf |
| 10/17/2018 | 832 | 832 SMC4-LC-275 Submission of Result of Ultrasonic Test of CIP Concrete Piles at P29.pdf |
| 10/17/2018 | 833 | 833 4055 PMUTL-DHDA1 Implementation of MOT Decision No.2172-QD-BGTVT Date 9.10.18.pdf |
| 11/15/2018 | 834 | 834 SMC4-WD-101 WD of Substructure - Column & Pier Head of P36.pdf |
| 11/2/2018 | 835 | 835 SMC4-WD-102 WD of Substructure - Column & Pier Head of P37.pdf |
| 10/18/2018 | 836 | 836 4071-BQLDATL-DHDA1 Evaluate the Actual Traffic Control & Traffic Organization of PK1.pdf |
| 10/19/2018 | 837 | 837 SMC4-MS-81 Supplement Method for Lifting Super T Girder by Cranes at Fabrication Yard of Group 2 - 407 Co..pdf |
| 10/19/2018 | 838 | 838 SMC4-MA-145 Capacity Profile of Manufacturer & Supplier of Non-woven Geotextile-VN Geotextile JSC.pdf |
| 10/19/2018 | 839 | 839 SMC4-LC-276 Result of Ultrasonic Test of CIP Concrete Piles at P33L.pdf |
| 10/19/2018 | 840 | 840 SMC4-LC-277 Result of Ultrasonic Test of CIP Concrete Pile P34L.pdf |
| 10/19/2018 | 841 | 841 SMC4-WD-103 WD of Substructure - Column & Pier Head P33.pdf |
| 10/19/2018 | 842 | 842 SMC4-AD-08 As Built Drawings of CIP Concrete Pile at P36.pdf |
| 10/26/2018 | 843 | 843 SMC4-MA-146 Report on Test Result of Base & Subbase Material at Trung Do Moutain (KV5) , Cao Duong Commune, Luong Son, Hoa Binh.pdf |
| 10/22/2018 | 844 | 844 SMC4-LC-278 Changing Road Pavement Structure for Temporary Road at the U turn Areas P24-P25 & P37-P38.pdf |
| 10/22/2018 | 845 | 845 SMC4-LC-0273A Report for Static Loading Test of CIP Concrete Piling, Pile No.C4-P22.pdf |
| 10/22/2018 | 846 | 846 SMC4-LC-0279 Result of Ultrasonic Test of CIP Concrete Piles at P36.pdf |
| 10/22/2018 | 847 | 847 SMC4-WD-104 WD of CIP Concrete Pile for P17 (2nd ).pdf |
| 10/22/2018 | 848 | 848 SMC4-MS-82 Method Statement of Pile Cap From P23-P28.pdf |
| 10/22/2018 | 849 | 849 SMC4-MS-83 Method Statement of Structure Excavation from P23-P28.pdf |
| 11/6/2018 | 850 | 850 SMC4-MS-84 Method Statement for Lower Part of Pier Head from P29-P37.pdf |
| 10/22/2018 | 851 | 851 SMC4-WD-105 WD of CIP Concrete Pile for Pier P18 (2nd ).pdf |
| 10/22/2018 | 852 | 852 1910-CDECE-KHHIV-MDNTL Changing 01 training course Location 10.2018.pdf |
| 10/23/2018 | 853 | 853 SMC4-WD-110 WD of Substructure - Column & Pier Head of P21.pdf |
| 11/2/2018 | 854 | 854 SMC4-WD-112 WD of Substructure - Column & Pier Head of P30.pdf |
| 11/10/2018 | 855 | 855 SMC4-WD-111 WD of Substructure - Column & Pier Head of P29.pdf |
| 10/23/2018 | 856 | 856 SMC4-WD-113 WD of Structure Excavation & Backfill for Section P18-P28.pdf |
| 10/23/2018 | 857 | 857 SMC4-WD-108 WD of SuperT girder span 27 (P26-P27).pdf |
| 10/23/2018 | 858 | 858 SMC4-MA-147Capacity Profile of Manufacturer & Supplier Vinh Thuc Co.,LTD for Auxiliary Steel Material for Super T Girder.pdf |
| 10/23/2018 | 859 | 859 SMC4-LC-280 Withdrawal of the Letter SMC4-MA-0132 dated 05Oct2018.pdf |
| 10/23/2018 | 860 | 860 SMC4-WD-109 WD of Super T Girder Spans 28 & 29.pdf |
| 10/23/2018 | 861 | 861 SMC4-WD-106 WD of CIP Concrete Pile for P23 (2nd).pdf |
| 10/23/2018 | 862 | 862 SMC4-WD-107 WD of CIP Concrete Pile for P27 (2nd).pdf |
| 10/23/2018 | 863 | 863 SMC4-MS-86 MS of Pile Cap P19-P22.pdf |
| 10/23/2018 | 864 | 864 SMC4-MS-85 Supplement & Updating the MS Plan Drawing of Trial Excavation Hole No. H10P42- 422 Co..pdf |
| 10/23/2018 | 865 | 865 SMC4-LC-281 Site Hand Over of PK1 (Km0+130-Km2+812.5).pdf |
| 10/26/2018 | 866 | 866 SMC4-MA-146A Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P19 & P20 (2nd).pdf |
| 10/25/2018 | 867 | 867 SMC4-LC-282 Submission of Weekly Report No.23.pdf |
| 10/26/2018 | 868 | 868 SMC4-MA-148 Profile of Anchorage 15-19 Manufactured by Zhemao Science and Technology,Supplier By Vinh Hung Trading Consulting.pdf |
| 11/13/2018 | 869 | 869 SMC4-MA-0149 The Characteristic Strength for Concrete class Y of Asean Batching plant-Report No.2.pdf |
| 10/26/2018 | 870 | 870 SMC4-LC-285 Detail Schedule of Super-T Fabrication Yard and Steel Bridge.pdf |
| 10/29/2018 | 871 | 871 SMC4-LC-283 Updates Environmental Control Plan (5th Submission).pdf |
| 10/26/2018 | 872 | 872 SMC4-LC-284 Acceptance of CIP Concrete Pile Foundation Construction atage and Transfer to Construction of Substructure work for P21.pdf |
| 10/26/2018 | 873 | 873 Site Minutes Date 24.10.18.pdf |
| 10/27/2018 | 874 | 874 SMC4-MA-146B Notice on Changing Name of Supplier for Reinforcing Steel of Vietnam Germany Steel Mill JSC(VGS) & Vietnam Italy Steel (VIS).pdf |
| 11/16/2018 | 875 | 875 SMC4-MA-150 Drawing & Calculation Sheet for Laminated Elastomeric Bearings.pdf |
| 10/27/2018 | 876 | 876 SMC4-WD-114 WD of CIP Concrete Pile for P9.pdf |
| 10/27/2018 | 877 | 877 SMC4-WD-115 WD of CIP Concrete Pile for P10.pdf |
| 10/27/2018 | 878 | 878 SMC4-WD-116 WD of CIP Concrete Pile for P11.pdf |
| 10/27/2018 | 879 | 879 SMC4-WD-117 WD of CIP Concrete Pile for P12.pdf |
| 10/27/2018 | 880 | 880 SMC4-WD-118 WD of CIP COncrete Pile for P13.pdf |
| 10/27/2018 | 881 | 881 SMC4-WD-119 WD of CIP Concrete Pile for P14.pdf |
| 10/27/2018 | 882 | 882 SMC4-WD-120 WD of CIP Concrete Pile for P15.pdf |
| 10/27/2018 | 883 | 883 SMC4-WD-121WD of CIP Concrete Pile for P43C (2nd).pdf |
| 10/27/2018 | 884 | 884 4181-PMUTL-DA1-Implementation of MOT's Letter No.12023-BGTVT-TCQM 23.10.2018.pdf |
| 10/27/2018 | 885 | 885 SMC4-MA-155 Report on Frequency Test of Reinforcing Steel for Super T Girder (1st) of Team 4.pdf |
| 10/27/2018 | 886 | 886 SMC4-MA-151 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile at P38, P39, P40 (2nd).pdf |
| 10/27/2018 | 887 | 887 SMC4-MA-152 Report on Frequency Test of Reinforcing Steel for Pile Cap & Pier Column of P21.pdf |
| 10/27/2018 | 888 | 888 SMC4-MA-153 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile of P18.pdf |
| 10/27/2018 | 889 | 889 SMC4-MA-154 Capacity Profile of Manufacturer & Supplier for Welding Material for Steel Bridge-Hyundai Welding Co..pdf |
| 10/27/2018 | 890 | 890 SMC4-RP-31 Report on Checking the Periodic Benchmarks System (1st).pdf |
| 10/29/2018 | 891 | 891 SMC4-MS-87 MS of Traffic Control at P23-P28 & P38-P43.pdf |
| 10/29/2018 | 892 | 892 SMC4-AD-09 As Built Drawings of CIP Concrete Pile for P22.pdf |
| 10/30/2018 | 893 | 893 SMC4-MS-88 Method of Protection Cable Head after Finish Cutting Tenden Cable Work of SuperT Girder.pdf |
| 10/30/2018 | 894 | 894 SMC4-MA-156 Report on Frequency Test of Reinforcing Steel of VN Germany Steel for SuperT Girder (2nd) of Team 2.pdf |
| 10/30/2018 | 895 | 895 SMC4-WD-122 WD of Substructure - Pile Cap of P40.pdf |
| 12/5/2018 | 896 | 896 SMC4-WD-123 WD of Precast Plank for SuperT Girder.pdf |
| 10/31/2018 | 897 | 897 SMC4-WD-124 WD of Substructure - Column and Pier Head P22.pdf |
| 10/31/2018 | 898 | 898 SMC4-WD-125 WD of Substructure - Column and Pier Head of P35.pdf |
| 10/31/2018 | 899 | 899 SMC4-LC-287 Submission of Weekly Report No.24.pdf |
| 10/31/2018 | 900 | 900 SMC4-LC-286 Resubmit for Interim Payment Certificate No.02 ( Period 01June2018 to 31July2018).pdf |
| 11/1/2018 | 901 | 901 SMC4-LC-287A Withdrawal of the Letter SMC4-LC-025518 dated 03Oct2018.pdf |
| 11/2/2018 | 902 | 902 SMC4-MA-159 Report on Frequency Test of Reinforcing Steel of VN Germany Steel for Pile Cap,Pier Column & Pier Head of P36, P37 (2nd).pdf |
| 11/2/2018 | 903 | 903 SMC4-MS-89 Calculation for Pre-Stressing of SuperT Girder 38m Group No.1 (422 Co.).pdf |
| 11/2/2018 | 904 | 904 SMC4-MA-157 Report on Frequency Test of PC Strand for Super T Girder (3rd).pdf |
| 11/2/2018 | 905 | 905 SMC4-MA-158 Report on Test Result of Jack, Anchorage & Synchrounous Experiment for SuperT Girder (3rd).pdf |
| 11/2/2018 | 906 | 906 SMC4-LC-289 Notice of Environmental Monitoring Schedule in Nov 2018 at Construction Phase.pdf |
| 11/2/2018 | 907 | 907 SMC4-WD-126 WD of Substructure - Pile Cap of P19.pdf |
| 11/2/2018 | 908 | 908 SMC4-LC-288 Application for Interim Payment Certificate No.03 ( Period 01AUG2018 to 30SEP2018).pdf |
| 11/1/2018 | 909 | 909 4247 GM BQLDATL Invitation date 6.11 Review the Progress & Implementation of the Project.pdf |
| 11/2/2018 | 910 | 910 SMC4-LP-26 Report on the Work Suspension of Traffic Signs at HQV Intersection.pdf |
| 11/3/2018 | 911 | 911 SMC4-MA-161 Report on Frequency Test of Steel for Pier Column & Pier Head P31, Pile Cap & Column P29 & P30.pdf |
| 11/3/2018 | 912 | 912 SMC4-MA-160 RP on Frequency Test of Reinforcing Steel for CIP CP of P32,P33,(5th), Substructure of P33,P34,P35 (2nd), PileCap of P36 (2nd) & PierColumn of P36(1st).pdf |
| 11/3/2018 | 913 | 913 SMC4-LC-290 Submission of Environment Monitoring Data at Pre-Construction & Construction Phases.pdf |
| 12/28/2018 | 914 | 914 SMC4-LC-291 TOR & Cost Estimate for General Traffic Control for Public Roads.pdf |
| 11/5/2018 | 915 | 915 SMC4-LC-292 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P36.pdf |
| 11/5/2018 | 916 | 916 SMC4-AD-10 Proposal for AD of CIP Concrete Pile of P36.pdf |
| 11/23/2018 | 917 | 917 SMC4-LC-293 Document for 2nd Additional Mobilization of Team 4 -Co.422.pdf |
| 11/6/2018 | 918 | 918 SMC4-LC-294 Design Change Document for Drainage System on Bridge.pdf |
| 11/27/2018 | 919 | 919 SMC4-LC-295 Design Change Document for Foundation Structure at P4-P8,P44,P59 & Change Elevation of Pile Cap at P1-P3,P60.pdf |
| 11/6/2018 | 920 | 920 SMC4-MA-162 Report on Frequency Test of PC Ctrand for Super T Girder (4th).pdf |
| 11/7/2018 | 921 | 921 SMC4-LT-17 Capacity Profile of Laboratory LAS-XD 1733 of TIEN THANH JSC.pdf |
| 11/7/2018 | 922 | 922 SMC4-MA-163 Mix Proportion for Trial Mix Class A ( Version 2) & Y (Version 2) at Batching Plant ASEAN.pdf |
| 11/7/2018 | 923 | 923 SMC4-LC-296 Engineer's Confirmation for Safety & Environment Satisfaction (October 2018).pdf |
| 11/7/2018 | 924 | 924 SMC4-LC-297 Submission of Weekly Report No.25.pdf |
| 11/7/2018 | 925 | 925 SMC4-WD-127 WD of Substructure- Column & Pier Head P20.pdf |
| 11/7/2018 | 926 | 926 SMC4-WD-128 WD of Substructure- Column & Pier Head P17.pdf |
| 11/7/2018 | 927 | 927-SMC4-WD-129 WD of Substructure- Column & Pier Head P18.pdf |
| 11/7/2018 | 928 | 928 SMC4-WD-130 WD of Substructure-P23.pdf |
| 11/7/2018 | 929 | 929 SMC4-WD-131 WD of Substructure- P24.pdf |
| 11/7/2018 | 930 | 930 SMC4-WD-132 WD of Substructure-P38.pdf |
| 11/7/2018 | 931 | 931 SMC4-WD-133 WD of Substructure-P39.pdf |
| 11/7/2018 | 932 | 932 SMC4-WD-134 WD of Substructure- P40.pdf |
| 11/8/2018 | 933 | 933 4283-BQLDATL-DHDA1 Traffic Control during Construction of Project- MD-STL Section.pdf |
| 11/8/2018 | 934 | 934 4015-PMUTL-DA1 Approval of Variation Order No. VO-HRR3-PK1-001 of Test on Concrete Piles.pdf |
| 11/9/2018 | 935 | 935 SMC4-MS-90 Supplement Method Drawing Divided Layer of Backfilling Foundation P29-P37.pdf |
| 11/8/2018 | 936 | 936 SMC4-LC-298 Submission of Monthly Report No.6.pdf |
| 11/8/2018 | 937 | 937 SMC4-MA-164 Capacity Profile of Viet Tiep Batching Plant.pdf |
| 11/9/2018 | 938 | 938 SMC4-WD-148 WD of CIP Concrete Pile for P58.pdf |
| 11/9/2018 | 939 | 939 SMC4-WD-147 WD of CIP Concrete Pile for P57.pdf |
| 11/9/2018 | 940 | 940 SMC4-WD-146 WD of CIP Concrete Pile for P56.pdf |
| 11/9/2018 | 941 | 941 SMC4-WD-135 WD of CIP Concrete Pile for P45.pdf |
| 11/9/2018 | 942 | 942 SMC4-WD-136 WD of CIP Concrete Pile for P46.pdf |
| 11/9/2018 | 943 | 943 SMC4-WD-137 WD of CIP Concrete Pile for P47.pdf |
| 11/9/2018 | 944 | 944 SMC4-WD-138 WD of CIP Concrete Pile for P48.pdf |
| 11/9/2018 | 945 | 945 SMC4-WD-139 WD of CIP Concrete Pile for P49.pdf |
| 11/9/2018 | 946 | 946 SMC4-WD-140 WD of CIP Concrete Pile for P50.pdf |
| 11/9/2018 | 947 | 947 SMC4-WD-141 WD of CIP Concrete Pile for P51.pdf |
| 11/9/2018 | 948 | 948 SMC4-WD-142 WD of CIP Concrete Pile for P52.pdf |
| 11/9/2018 | 949 | 949 SMC4-WD-143 WD of CIP Concrete Pile for P53.pdf |
| 11/9/2018 | 950 | 950 SMC4-WD-144 WD of CIP Concrete Pile for P54.pdf |
| 11/9/2018 | 951 | 951 SMC4-WD-145 WD of CIP Concrete Pile for P55.pdf |
| 11/9/2018 | 952 | 952 SMC4-LC-299 Report on Environment Monitoring at Pre Construction & Construction Phases (8.2018).pdf |
| 11/12/2018 | 953 | 953 SMC4-MA-165 Report on Frequency Test of PC Strand for Super T Girder (5th).pdf |
| 11/9/2018 | 954 | 954 04-CDECE-MDNTL Report on the Implementation on October 2018 HIV-AIDS Prevention Program for Project.pdf |
| 11/12/2018 | 955 | 955 SMC4-MS-91 MS of Traffic Control at P7-P18.pdf |
| 11/10/2018 | 956 | 956 SMC4-WD-149 WD for Miscellaneous-Drainage-Genenal Layout of Drainage under Viaduct.pdf |
| 11/12/2018 | 957 | 957 SMC4-LC-300 Proposal for Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Constructure of Substruction Work for P29.pdf |
| 11/12/2018 | 958 | 958 SMC4-LC-301 Proposal for Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P22.pdf |
| 11/12/2018 | 959 | 959 SMC4-LC-302 Report on Environment Monitoring at Construction Phases (June and July 2018).pdf |
| 11/12/2018 | 960 | 960 SMC4-MA-168 Report on Test Result of PC duct of Ngoc Lam Production & Trading Co..pdf |
| 11/12/2018 | 961 | 961 SMC4-AD-11 AD of CIP Concrete Pile for P22.pdf |
| 11/12/2018 | 962 | 962 SMC4-AD-12 AD of CIP Concrete Pile for P29.pdf |
| 11/12/2018 | 963 | 963 SMC4-MS-92 MS of Pier Column P19-P22.pdf |
| 11/10/2018 | 964 | 964 4356 TB BQLDATL Notice on Conclusions Given by PMU Thang Long in the Meeting to Review the Implementation.pdf |
| 11/13/2018 | 965 | 965 SMC4-MA-169 Report on Trial Mix of Concrete Class A,B1,C1,C3,C4,D,G,Y of Transmeco BP (used Mighty Admixture).pdf |
| 11/13/2018 | 966 | 966 SMC4-MA-170 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P41 & P42.pdf |
| 11/13/2018 | 967 | 967 SMC4-MA-171-Report on Test Result of Tie Anchoe (U-Bolt) & Dowel of Viet Thang Co..pdf |
| 11/13/2018 | 968 | 968 SMC4-MA-166 Report on Frequeny Test of Reinforcing Steel for Pile Cap, Column & Pier Head of P21(2nd).pdf |
| 11/13/2018 | 969 | 969 SMC4-LC-303 Notice on Re Mobilization of Drilling Machine of Team 4- 422 Co..pdf |
| 11/13/2018 | 970 | 970-SMC4-LC-304 Submission of Weekly Report No.26.pdf |
| 11/14/2018 | 971 | 971 SMC4-LC-305 TOR & Cost Estimate for Environment Monitoring Item Part 1-Base on Appendix A of the Technical Specifications.pdf |
| 11/14/2018 | 972 | 972 SMC4-LC-306 TOR & Cost Estimate for Environment Monitoring Part 2- Base on Clause S1.43 of Technical Specification.pdf |
| 11/14/2018 | 973 | 973 SMC4-LC-307 Withdrawal of Letter SMC4-MA-0082 dated 27 July 2018.pdf |
| 11/14/2018 | 974 | 974 SMC4-LC-308 Result of Ultrasonic Test of CIP Concrete Piles at P19.pdf |
| 11/14/2018 | 975 | 975 SMC4-LC-309 Result of Ultrasonic Test of CIP Concrete Piles at P20.pdf |
| 11/14/2018 | 976 | 976 SMC4-MA-167 Profile of Manufacturer & Supplier for Painting Material for Steel Bridge- Jotun Paints VN Co.,Ltd.pdf |
| 11/14/2018 | 977 | 977 SMC4-MS-93 Supplement Method Drawing the Divided Layer of Backfilling Foundation from P19-P22.pdf |
| 11/14/2018 | 978 | 978 SMC4-WD-150 WD of Substructure - Pier P25.pdf |
| 11/14/2018 | 979 | 979 SMC4-WD-151 WD of Substructure P27.pdf |
| 11/14/2018 | 980 | 980 SMC4-WD-152 WD of Substructure - Pier P41.pdf |
| 11/14/2018 | 981 | 981 SMC4-MA-172 Mix Proportion for Trial Mix Class B1, C1,C3,C4,D,E,G,Y at Home World BP (using Mighty Admixture).pdf |
| 11/15/2018 | 982 | 982 SMC4-MA-173 Capacity Profile of Manufacturer Posco for Steel Plate, Shape & Filler Metal for Steel Bridge.pdf |
| 11/14/2018 | 983 | 983 SMC4-MA-175 The Plan of Relocation of ASEAN BP & Proposal for Early Approval of Viet Tiep BP.pdf |
| 11/16/2018 | 984 | 984 SMC4-LC-310 Proposal for Payment for SuperT girders & Excavation with Cofferdam.pdf |
| 11/16/2018 | 985 | 985 SMC4-LC-311 Submission for Result of Internal Inspection at Fabrication Yard.pdf |
| 11/16/2018 | 986 | 986 SMC4-MA-174 Capacity Profile of Coupler Manufacturer Tran Huy Construction Trading JSC.pdf |
| 11/16/2018 | 987 | 987 SMC4-MA-176 Report on Frequency Test of Reinforcing Steel Vn Germany Steel for Pile Cap, Pier Column Pier Head P28(1st) P29(4th), Pier Head P30 & P31 (4th).pdf |
| 11/16/2018 | 988 | 988 SMC4-MA-177 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P28.pdf |
| 11/16/2018 | 989 | 989 SMC4-MS-94 Traffic Control Method for Public Roads- Arranging of Traffic Control at P24-P25 & P37-P38.pdf |
| 11/21/2018 | 990 | 990 SMC4-MS-95 MS of Traffic Control for Public Road at P38-P43-Volume VI.1 Plan Layout of Flagman, Signboard & Detour Road.pdf |
| 11/26/2018 | 991 | 991 SMC4-LC-312 Changing Road Pavement Structure for Detour Road at P38-P43 Right Side.pdf |
| 11/16/2018 | 992 | 992 SMC4-LC-313 Report on Environment Monitoring at Construction Phases (September & October 2018).pdf |
| 11/16/2018 | 993 | 993 SMC4-MC-06 Interim Payment No 4 ( Period 01 Oct2018 to 31 Oct2018).pdf |
| 11/16/2018 | 994 | 994 SMC4-WD-153 WD of SuperT Girder Span 38 (P37-P38).pdf |
| 11/16/2018 | 995 | 995 SMC4-LC-314 Proposal for Replacement of Structure Engineer for Project-PK1.pdf |
| 11/19/2018 | 996 | 996 SMC4-MA-178 Report on Frequency Test of Reinforcing Steel-VN Germany Steel for Pile Cap, Pier Column, Pier Head P19,P20 &P22 (1st).pdf |
| 11/19/2018 | 997 | 997 SMC4-MS-96 Supplement the Method Darwing of CIP Concrete Piling.pdf |
| 11/20/2018 | 998 | 998 SMC4-MS-97 Traffic Control Method for Public Roads- Arranging ofr Temporary Lighting System at P24-P25 & P37-P38.pdf |
| 11/19/2018 | 999 | 999 SMC4-MA-179 Submission of Characteristic Strenghth for Concrete Class Y of ASEAN BP - Report No.3.pdf |
| 11/19/2018 | 1000 | 1000 SMC4-MS-98 Traffic Control Plan for Public Road at P46-P49 Left Side & P55-P60.pdf |
| 11/20/2018 | 1001 | 1001 SMC4-WD-154 WD for Miscellaneous - Basement for Traffic Sign Board at P37.pdf |
| 11/20/2018 | 1002 | 1002 SMC4-LC-315 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P35C.pdf |
| 11/21/2018 | 1003 | 1003 SMC4-MA-180 Inspection Minutes of Home World BP & Report on Solving all Remaining Content.pdf |
| 11/21/2018 | 1004 | 1004 SMC4-MA-181 Capacity Profile of VIET TIEP BatchingPlant (2nd ).pdf |
| 11/21/2018 | 1005 | 1005 SMC4-MA-182 Technical Profile of Coarse Aggregate, Fine Aggregate & Water & Mix Proportion of Concrete for Viet Tiep BP.pdf |
| 11/21/2018 | 1006 | 1006 SMC4-MA-183 Report on Frequency Test of Cement, Crushed Stone, Yellow Sand for Cement Concrete at ASEAN BP (6th).pdf |
| 11/21/2018 | 1007 | 1007 SMC4-AD-13 AD of CIP Concrete Pile for P35C.pdf |
| 11/21/2018 | 1008 | 1008 SMC4-LC-316 Contractor's Programme (Rev 1).pdf |
| 11/21/2018 | 1009 | 1009 SMC4-MA-184 Report on Testing Results of Water for Home World Batching Plant.pdf |
| 11/21/2018 | 1010 | 1010 SMC4-WD-155 WD of Column and Pier Head of P19.pdf |
| 11/22/2018 | 1011 | 1011 SMC4-MA-185 Proposal for Approval of Report on Frequency test of Reinforcing Steel for Pier Column and Pier Head of Pier P33,P34,P35,P36 and P37 (3rd Time).pdf |
| 11/22/2018 | 1012 | 1012 SMC4-MA-186 Proposal for Approval of Report on Frequency test of Reinforcing Steel for Pier Column and Pier Head of Pier P36 (4th Time).pdf |
| 11/22/2018 | 1013 | 1013 SMC4-LC-317 Submission of Manpower Report No.1 (407 ,423 Co).pdf |
| 11/27/2018 | 1014 | 1014 SMC4-LC-323 Document for Additional Mobilization of Team 3 - 412 Co.pdf |
| 11/27/2018 | 1015 | 1015 SMC4-LC-318A Submission of Weekly Report No.27.pdf |
| 11/24/2018 | 1016 | 1016 SMC4-LC-319 Cost Estimate from Rotation Steel Pile into CIP Concrete Pile Item.pdf |
| 11/24/2018 | 1017 | 1017 SMC4-LC-321 Result of Ultrasonic Test of CIP Concrete Piles at P34R.pdf |
| 11/24/2018 | 1018 | 1018 SMC4-LC-322 Result of Ultrasonic Test of CIP Concrete Piles at P35L,P35R.pdf |
| 11/24/2018 | 1019 | 1019 SMC4-MA-187 Capacity Profile of Manufacturer & Supplier for Bearing-Kwang Won Industrial Company-Transport Materials Equipment Trading JSC (2nd).pdf |
| 11/24/2018 | 1020 | 1020 SMC4-LC-320 Submission Breakdown of Cost for Changing Foundation Design at Some Locations of Piers.pdf |
| 11/24/2018 | 1021 | 1021 SMC4-WD-156 Working Drawings - General View of Main Bridge & Ramp HQV-B(5th).pdf |
| 11/24/2018 | 1022 | 1022 SMC4-WD-157 Working Drawings of Substructure of Pier P16.pdf |
| 11/24/2018 | 1023 | 1023 SMC4-MS-100 MS of Traffic Control for Public Road at Section P38-P43-Volume VI.3-Construction Method for Detour Road at P38-P43.pdf |
| 11/24/2018 | 1024 | 1024 SMC4-LC-318 Proposal for Using Subbase Material for Subgrade Layer of Road Structure for Traffic Control.pdf |
| 12/28/2018 | 1025 | 1025 SMC4-MS-101 MS of Pier Head from P28-P31.pdf |
| 11/26/2018 | 1026 | 1026 SMC4-WD-159 Working Drawings of Substructure of Pier P26.pdf |
| 11/26/2018 | 1027 | 1027 SMC4-RP-32 Report on Trial Excavation of Cast in Place Concrete Piles-Hole No.H4P23.pdf |
| 11/26/2018 | 1028 | 1028 SMC4-LC-324 Notice on Demobilization of Service Crane of Team 2-407 Co.pdf |
| 11/26/2018 | 1029 | 1029 13372-BGTVT-VP Invitation to Attend Working Delegation by Minister of MOT for Site Inspection of Some Transport Construction & Investment Projects.pdf |
| 11/26/2018 | 1030 | 1030 4547-PMUTL-DA6 Strengthening Quality Control for the Whole Project.pdf |
| 11/26/2018 | 1031 | 1031 SMC4-WD-160 WD of Extension of Pile Top for PDA Test at P23.pdf |
| 11/26/2018 | 1032 | 1032 SMC4-WD-161 WD of Substructure of P28.pdf |
| 11/26/2018 | 1033 | 1033 SMC4-WD-162 WD of Extention of Pile Top for PDA Test at P42.pdf |
| 11/26/2018 | 1034 | 1034 SMC4-WD-158 WD of Substructure of P42.pdf |
| 11/28/2018 | 1035 | 1035 SMC4-LC-325 Additional Supervision Cost of Engineer's Staff (September 2018).pdf |
| 11/28/2018 | 1036 | 1036 SMC4-MA-189 Report on Frequency Test of Reinforcing Steel - VGS for Pile Cap, Pier Column, Pier Head P33, P34, P35 (4th).pdf |
| 11/28/2018 | 1037 | 1037 SMC4-MA-188 Capacity Profile of Manufacturer & Supplier for Bolts & Stud Shear Connectors for Steel Bridge-Daewoo & Khai Nguyen.pdf |
| 11/30/2018 | 1038 | 1038 SMC4-MS-102 MS of Temporary Facilities Arrangement on Site form P8-P17.pdf |
| 11/28/2018 | 1039 | 1039 SMC4-MS-99 MS for Transportation of SuperT Girder.pdf |
| 11/28/2018 | 1040 | 1040 SMC4-MA-190 Report on Frequency Test of Reinforcing Steel- VGS for CIP Concrete Pile of P23,P24,P25,P26 & P27 (1st).pdf |
| 11/28/2018 | 1041 | 1041 SMC4-LC-327 Submission of video CDs No.1 (May 2018- October 2018).pdf |
| 11/28/2018 | 1042 | 1042 SMC4-MA-191 Changing Steel Plate SM400 with the Filler Steel Plate 2mm & 5mm in Thickness & Changing the Thickness of the Filler Steel Plate from 5mm to 6mm.pdf |
| 11/28/2018 | 1043 | 1043 SMC4-LC-326 Submission of Weekly Report No.28.pdf |
| 11/28/2018 | 1044 | 1044 SMC4-LC-328 Acceptance of CIP Concrete Pile Construction Stage & Transfer to Contruction of Substructure Work for P34L.pdf |
| 11/28/2018 | 1045 | 1045 SMC4-LC-329 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Contruction of Substructure Work at P20.pdf |
| 11/30/2018 | 1046 | 1046 SMC4-AD-14 As-Built Drawings of CIP Concrete Pile for P20.pdf |
| 11/30/2018 | 1047 | 1047 SMC4-AD-15 As-Built Drawings of CIP Pile for Pier P34L.pdf |
| 11/30/2018 | 1048 | 1048 SMC4-MA-192 Capacity Profile of Manufacturer & Supplier for Stud Shear Connectors - Samjin Fastners Co.Ltd - Duc Son Construction Material Co.Ltd.pdf |
| 11/30/2018 | 1049 | 1049 SMC4-LC-330 Manpower & Equipment Mobilization Document of Viet Tiep Batching Plant for Concrete Suppling.pdf |
| 12/3/2018 | 1050 | 1050 SMC4-MA-193 Report on Frequency Test of PC Strand for Super T Girder (6th).pdf |
| 11/30/2018 | 1051 | 1051 SMC4-LC-332 Notice of Environmental Monitoring Schedule in December 2018 at Construction Phase.pdf |
| 11/30/2018 | 1052 | 1052 SMC4-LC-331 Result of Environment Monitoring in Construction Phase (1st Phase in Nov 2018 Parameter TSP).pdf |
| 3/29/2018 | 1052 | 1052-BQLDATL-DA1 Works affected to Construction of Viaduct Investment Project.pdf |
| 12/1/2018 | 1053 | 1053 661-CQLXD-ĐB1 Result of Site Inspection & Treatment of Some Shortcomings of Construction Quality at HRR3.pdf |
| 3/29/2018 | 1053 | 1053-BQLDATL-DA1 Agreement on Fencing installation method for traffic control for construction.pdf |
| 12/1/2018 | 1054 | 1054 13575-BGTVT-CQLXD Treatment of Some Errors of Construction Quality in HRR3.pdf |
| 12/3/2018 | 1055 | 1055 SMC4-MS-103 Supplement & Updating the Method Statement Plan Drawing of Trial Excavation & CIP Concrete Piling form P11-P17.pdf |
| 12/3/2018 | 1056 | 1056 SMC4-MS-104 Supplement the MS of Structure Excavation from P32R-P35R.pdf |
| 12/3/2018 | 1057 | 1057 SMC4-MS-105 Outline for Loading Test of Pier Head'S Supporting System fromP28-P31.pdf |
| 12/3/2018 | 1058 | 1058 SMC4-LC-334 Changing PDA Test Pile at P23.pdf |
| 12/3/2018 | 1059 | 1059 SMC4-LP-27 Payment for Super T Girders & Structure Excavation with Coffedam.pdf |
| 12/3/2018 | 1060 | 1060 SMC4-MA-194 Report on Test of PC Strand for Girder (7th).pdf |
| 12/3/2018 | 1061 | 1061 SMC4-LC-333 Detail Environment Protection Project & Report on Environment Monitoring of Thanh Long Steel Structure Plant.pdf |
| 12/3/2018 | 1062 | 1062 SMC4-MA-195 Report on Frequency Test of Reinforcing Steel of VGS for Super T Girder (3rd) of Team 2.pdf |
| 12/3/2018 | 1063 | 1063 SMC4-MA-196 Report on Frequency Test of Steel VGS for Pile Cap, Column, oier head P19, P20, P22 (2nd).pdf |
| 12/3/2018 | 1064 | 1064 SMC4-MA-197 Report on Frequency Test of Reinforcing Steel for Super T Girder (2nd) of Team 1.pdf |
| 12/5/2018 | 1065 | 1065 SMC4-MA-198 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P17(1st).pdf |
| 12/3/2018 | 1066 | 1066 SMC4-WD-163 WD of Super T Girder Span 41(P40-P41).pdf |
| 12/3/2018 | 1067 | 1067 SMC4-WD-164 WD of Substructure - Pile Cap Center of P32.pdf |
| 12/3/2018 | 1068 | 1068 SMC4-WD-165 WD of Diaphragm from Span 10-16 and 20-32.pdf |
| 12/3/2018 | 1069 | 1069 SMC4-WD-166 WD of Detail of Test Pile 35x35cm.pdf |
| 12/4/2018 | 1070 | 1070 SMC4-MS-106 MS for Lower Part of Pier Head P19-P22.pdf |
| 12/6/2018 | 1071 | 1071 SMC4-MS-107 MS for Production of Precast RC Plank of SuperT Girder.pdf |
| 12/4/2018 | 1072 | 1072 SMC4-MA-199 Report on Test of Reinforcing Steel VGS for Pile Cap,Pier Column, Pier Head P32, P33, P34, P35 (5th).pdf |
| 12/4/2018 | 1073 | 1073 SMC4-LC-335 Notice of the Leave of our Key Personnel (Safety Manager).pdf |
| 12/5/2018 | 1074 | 1074 SMC4-MA-201 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P27.pdf |
| 12/5/2018 | 1075 | 1075 SMC4-LC-0336 Engineer's Confirmation for Safety & Environment Satisfaction (Nov 2018).pdf |
| 12/5/2018 | 1076 | 1076 SMC4-LC-0337 Document for 3rd Additional Mobilization of Team 4 - Co.422.pdf |
| 12/5/2018 | 1077 | 1077 SMC4-MA-200 Report on Test of PC Strand for Super T Girder (8th).pdf |
| 12/6/2018 | 1078 | 1078 SMC4-MA-202 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P16.pdf |
| 12/6/2018 | 1079 | 1079 SMC4-WD-167 WD of Elastomric Bearing (P19-P61).pdf |
| 12/6/2018 | 1080 | 1080 SMC4-LC-338 Replacement of Quality Control Manager.pdf |
| 12/6/2018 | 1081 | 1081 SMC4-LC-339 TOR & Cost Estimate for Environment Monitoring Part 1- Base on Appendix A of the Technical Specifications (2nd).pdf |
| 12/6/2018 | 1082 | 1082 SMC4-LC-340 Submission of Weekly Report No.29.pdf |
| 12/6/2018 | 1083 | 1083 SMC4-MS-54A MS of Traffic Control for Public Road A1-P4-Volume II.3- Additional Slope for Traffic Control Document.pdf |
| 12/6/2018 | 1084 | 1084 SMC4-LC-341 Changing Position of Supper Coupler & Rebar B1, B2a of Super T Girder.pdf |
| 12/7/2018 | 1085 | 1085 4637 QD-BQLDATL Approval Decision Design Change Document of Foundation Structure & Raising Elevation of Pile Cap of P44,P59,P60 & Piers from P87 -P98 under HCRR3.pdf |
| 12/7/2018 | 1086 | 1086 SMC4-LC-342 Reply to the Engineer's Letter Regarding Arrangement of Temporary Facilities on Site at the Section from P8-P43.pdf |
| 12/7/2018 | 1087 | 1087 SMC4-LC-344 Submission of Monthly Report No.7.pdf |
| 12/7/2018 | 1088 | 1088 SMC4-LC-345 Report on Environment Monitoring in Construction Stage (2nd Phase in Nov 2018, Parameter TSP).pdf |
| 12/7/2018 | 1089 | 1089 SMC4-WD-168 Calculation Sheet for Camber of Steel Girder (2nd).pdf |
| 12/7/2018 | 1090 | 1090 SMC4-LC-346 Notice for Leave of Our Key Personnel (Project Manager).pdf |
| 12/8/2018 | 1091 | 1091 4715-TB-BQLDATL Notice on Conclusions given by PMUTL on the Meeting to Review the Implementation of PK1 & PK2 under the HCRR3 Construction Project.pdf |
| 12/10/2018 | 1092 | 1092 SMC4-WD-169 Changing Dimension of Wing of Super T Girder.pdf |
| 12/10/2018 | 1093 | 1093 SMC4-LC-347 Improvement of Quality for Pier Head's Lower Part Formwork.pdf |
| 12/10/2018 | 1094 | 1094 SMC4-LC-343 Result of Ultrasonic Test of CIP Concrete Pile at p18.pdf |
| 12/10/2018 | 1095 | 1095 SMC4-MA-203 Report on Test of Reinforcing Steel VGS for CIP Concrete Piel of P23, P24, P25, P26 (2nd).pdf |
| 12/10/2018 | 1096 | 1096 SMC4-MA-206 Report on Test Result of Epoxy Coated PC Strand & Anchorage of Zhemao Science and Technology Co..pdf |
| 12/10/2018 | 1097 | 1097 SMC4-MA-191 Changing Steel Plate SM400 w the Filler Steel Plate 2mm & 5mm in Thickness & Changing the Thickness of the Filler Steel Plate fr 5mm to 6mm.pdf |
| 12/10/2018 | 1098 | 1098 SMC4-MA-204 Capacity Profile of MINH TAM Batching Plant.pdf |
| 12/10/2018 | 1099 | 1099 SMC4-LC-348 Result of Tip Contact Checking Test of CIP Concrete Piles C5 at P18.pdf |
| 12/10/2018 | 1100 | 1100 SMC4-LC-349 Report on Environment Monitoring in Construction Stage (3rd Phase in Nov 2018, Parameter TSP).pdf |
| 12/10/2018 | 1101 | 1101 SMC4-LO-37 Urgent Request to Import Steel Material to the Mill as Committed Schedule.pdf |
| 12/11/2018 | 1102 | 1102 SMC4-RP-33 Report on Trial Excavation of CIP Concrete Piles - Hole No. H1P14.pdf |
| 12/11/2018 | 1103 | 1103 SMC4-MS-108 Outline for Loading Test of Pier Head's Supporting System at P31.pdf |
| 12/11/2018 | 1104 | 1104 SMC4-MA-207 TOR for Testing of Elastomeric Bearing.pdf |
| 1/23/2019 | 1105 | 1105 SMC4-MA-205 Report on Test of Cement,Coarse Aggregates, Fine Aggregates for Cement Concrete at ASEAN Batching Plant ( 7th to 13th).pdf |
| 12/11/2018 | 1106 | 1106 SMC4-MA-208 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head of P19 (3rd).pdf |
| 12/11/2018 | 1107 | 1107 4757-BQLDATL-DHDA1 Invitation to attend the Site Inspection in order to Evaluate the Actual Traffic Control.pdf |
| 12/13/2018 | 1108 | 1108 SMC4-MC-07 Interim Payment Certificate No.05 ( Period 1Nov2018 to 30Nov2018).pdf |
| 12/12/2018 | 1109 | 1109 SMC4-MS-107A MS of Structure Excavation from P15-P18.pdf |
| 12/12/2018 | 1110 | 1110 SMC4-LC-350 Inspection Minutes & Quantity Summary Table of Waste Disposal Implemented by the Subcontractors at Nguyen Khe Disposal fr Jun-Oct2018.pdf |
| 12/13/2018 | 1111 | 1111 SMC4-LT-18 Additional Submission of Profile of Laboratory LAS-XD 1733 of Tien Thanh JSC..pdf |
| 12/12/2018 | 1112 | 1112 SMC4-MA-209 Capacity Profile of Supplier JV of New Link-Nhan Luat Corp. for Reinforcing Steel of Hoa Phat Hai Duong JSC.pdf |
| 12/13/2018 | 1113 | 1113 SMC4-LC-351 Submission of Weekly Report No.30.pdf |
| 12/13/2018 | 1114 | 1114 SMC4-MA-210 capacity profile of manufacturer & Suppier for Expansion Admixture VT-TN01 Center for Corrosion Prevention & Construction Consultancy of IBST.pdf |
| 12/14/2018 | 1115 | 1115 SMC4-LC-352 Report on Environment Monitoring in Construction Stage (1st Phase in Dec 2018, Parameter TSP).pdf |
| 12/14/2018 | 1116 | 1116 SMC4-LC-353 Result of Ultrasonic Test of CIP Concrete Piles at P28.pdf |
| 12/14/2018 | 1117 | 1117 SMC4-MS-109 MS of Pier Column from P23-P28.pdf |
| 12/15/2018 | 1118 | 1118 SMC4-LC-355 Acceptance of CIP Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P34R.pdf |
| 12/17/2018 | 1119 | 1119 SMC4-LC-354 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Subtructure Work for P19.pdf |
| 12/17/2018 | 1120 | 1120 4810-PMUTL-DA6 Settlement of Some Construction Quality Defects in the Project.pdf |
| 12/17/2018 | 1121 | 1121-SMC4-MA-211 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head of P18.pdf |
| 12/17/2018 | 1122 | 1122 SMC4-MA-212 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P16& P17 (2nd).pdf |
| 12/17/2018 | 1123 | 1123 SMC4-MA-213 Report on Frequency Test of Reinforcing Steel for Super T Girder (2nd) of Team 4 Co.422.pdf |
| 12/18/2018 | 1124 | 1124 SMC4-MA-214 Report on Frequency Test of Reinforcing Steel for CIP Pile P12 & P13.pdf |
| 12/17/2018 | 1125 | 1125 SMC4-MA-215 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head P32,P33,P34 & P35 (6th).pdf |
| 12/17/2018 | 1126 | 1126 SMC4-AD-16 As Built Drawings of CIP Concrete Pile for Pier P19.pdf |
| 12/17/2018 | 1127 | 1127 SMC4-AD-17 As Built Drawings of CIP Concrete Pile for Pier P34R.pdf |
| 12/18/2018 | 1128 | 1128 SMC4-LC-356 Design Change Document for Foundation Structure & Elevation of Pile Cap of Piers P44, P59, P60.pdf |
| 12/18/2018 | 1129 | 1129 SMC4-LC-358 Submission of Weekly Report No.31.pdf |
| 12/18/2018 | 1130 | 1130 SMC4-LC-357 Reply to the Engineer's Letter Regarding Document of Manpower & Equipment Mobilization of Viet Tiep BP.pdf |
| 12/18/2018 | 1131 | 1131 SMC4-MA-216 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P38, P39, P40 (3rd).pdf |
| 12/18/2018 | 1132 | 1132 SMC4-MA-217 Capacity Profile of Manufacturer & Supplier for Expansion Admixture Denka Power CSA type S & R for Concrete.pdf |
| 12/19/2018 | 1133 | 1133 SMC4-MS-110 MS of Steel Bridge Fabrication of Thanh Long Group JSC.pdf |
| 12/19/2018 | 1134 | 1134 SMC4-WD-171 Calculation Sheet & WD of Deck sSab of Steel Bridge( Including Kadawa Certification & A11,02(1)(a) & S11,18 (1)(c) of Japan Bridge Association.pdf |
| 12/19/2018 | 1135 | 1135 SMC4-WD-170 WD of Substructure - Pile Cap of P15.pdf |
| 12/20/2018 | 1136 | 1136 SMC4-MA-219 Report on Trial Mix of Concrete Class A,B1,C1,C3,C4,D, E,G,Y for Viet Tiep BP ( used BASF Admixture).pdf |
| 12/20/2018 | 1137 | 1137 SMC4-LC-316A Changing the Location of PDA Test from Pile No.4 Abutment A1 to No.2 of P23 & No.4 of P60 to No.4 of P42.pdf |
| 12/20/2018 | 1138 | 1138 SMC4-MA-215A Capacity Profile of Manufacturer Posco for Steel Plate, Shape & Filler Metal for Steel Bridge (2nd).pdf |
| 3/20/2019 | 1139 | 1139 SMC4-LC-359 Report on the Phenomenon of CIP Concrete Pile D1.2m - Pile 5 of P27.pdf |
| 12/20/2018 | 1140 | 1140 SMC4-MS-111 Quality Control Quality Assurance Plan and Welding Plan for Steel Bridge Fabrication of Thanh Long Group JSC.pdf |
| 12/21/2018 | 1141 | 1141 SMC4-LC-360 Changing the Type of Welding Line of Pier Head & Girder of Steel Bridge.pdf |
| 12/22/2018 | 1142 | 1142 SMC4-MA-220 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile of O38,P39,P40 ( 4th).pdf |
| 12/22/2018 | 1143 | 1143 SMC4-MA-221 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile of P41,P42,P43 (2nd).pdf |
| 12/22/2018 | 1144 | 1144 SMC4-LC-361 Document for Mobilization of Subcontractor Thang Long Group JSC for Construction of Steel Bridge.pdf |
| 12/22/2018 | 1145 | 1145 SMC4-LC-362 Document for Mobilization of Subcontractor Thang Long Builtding & Consulting Experiment JSC for PDA Test.pdf |
| 12/22/2018 | 1146 | 1146 SMC4-LC-363 Document for Additional Manpower & Equipment Mobilization of Subcontractor Thang Long Building & Consulting Experiment JSC for Ultrasonic Test.pdf |
| 12/22/2018 | 1147 | 1147 SMC4-LC-364 Notice for the Schedule of Mobilization & Inspection of Steel Material at the Factory of Thang Long.pdf |
| 12/22/2018 | 1148 | 1148 SMC4-WD-172 WD of Substructure - Pier P18 (2nd).pdf |
| 12/24/2018 | 1149 | 1149 SMC4-MA-222 Report on Test Result of Compressive Strength for 28 days of Trial Mix Concrete Class A,B1,C1,C3,C4,D,E,G,Y for Viet Tiep Batching Plant.pdf |
| 12/24/2018 | 1150 | 1150 SMC4-MA-223 Test Result of Water used for Cement Concrete of Viet Tiep Batching Plant.pdf |
| 12/25/2018 | 1151 | 1151 SMC4-AD-18 As Built Drawings of CIP Concrete Pile for Pier P18.pdf |
| 12/25/2018 | 1152 | 1152 SMC4-LP-29 To Support the Contractor in Extending the Method of Fencing, Traffic Congtrol at Sections A1-P17 & P18-P22.pdf |
| 12/26/2018 | 1153 | 1153 SMC4-LC-366 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction Substructure Works for P18.pdf |
| 12/26/2018 | 1154 | 1154 SMC4-LP-30 To Support the Contractor in Relocating the Drainage Culvert at P26.pdf |
| 12/27/2018 | 1155 | 1155 SMC4-MS-112 Submission of Traffic Control Plan for Public Road for Construction at P44-P60.pdf |
| 12/26/2018 | 1156 | 1156 SMC4-LC-367 Reply to the Engineer's Letter on Report on Environmental Monitoring in Construction Stage(1st Phase -Dec2018,Parameter TSP).pdf |
| 12/26/2018 | 1157 | 1157 SMC4-MA-224 Report on Test of Cement, Coarse Aggregate, Fine Aggregate and admixture of Viet Tiep BP (1st)& Admixture for Cement Concrete at Viet Tiep BP (1st).pdf |
| 12/26/2018 | 1158 | 1158 SMC4-MA-225 Report on Frequency Test of PC Strand for Super T Girder (9th).pdf |
| 12/26/2018 | 1159 | 1159 SMC4-MA-226 Report on Frequency Test of PC Strand for Super T Girder (10th).pdf |
| 12/26/2018 | 1160 | 1160 SMC4-LC-368 Submission of Weekly Report No.32.pdf |
| 12/26/2018 | 1161 | 1161 SMC4-MA-227 Report on Frequency Test of PC Strand for Super T Girder (11th).pdf |
| 12/27/2018 | 1162 | 1162 SMC4-MS-113 Method Statement for Pile Cap P17, P18.pdf |
| 12/28/2018 | 1163 | 1163 SMC4-WD-173 WD for General Arrangement of Traffic Sign for Expressway.pdf |
| 12/28/2018 | 1164 | 1164 SMC4-MA-228 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P11, P12, P13, P14 (2nd).pdf |
| 12/28/2018 | 1165 | 1165 SMC4-MA-229 Report on Frequency Test of Reinforcing Steel for Super T Girder (3rd) of Team 4 ( Co. 422).pdf |
| 12/28/2018 | 1166 | 1166 SMC4-LC-369 Notice on Carrying Out PDA Test by Thanh Long JSC by Existing Crane At Site.pdf |
| 12/28/2018 | 1167 | 1167 SMC4-LC-370 Notice on New Year 2019 Holiday Schedule of the Contractor.pdf |
| 12/28/2018 | 1168 | 1168 SMC4-MA-230 Approval of Report on Frequency Test of Reinforcing Steel CGS for Precast Panel of Super T Girder.pdf |
| 12/28/2018 | 1169 | 1169 SMC4-MA-231 Approval Manufacturer & Supplier of Coupler D25 & Coupler D32.pdf |
| 12/28/2018 | 1170 | 1170 SMC4-LC-371 Report on Incident of Installation of Manufactured Reinforcing Steel at P21 & P22.pdf |
| 12/28/2018 | 1171 | 1171 SMC4-LC-373 Notice on New Year 2019 Holiday Schedule of the Contractor ( on Site).pdf |
| 12/28/2018 | 1172 | 1172 SMC4-LC-372 Notice of Environmental Monitoring Schedule in January 2019 at Construction Phase.pdf |
| 12/28/2018 | 1173 | 1173 SMC4-LC-374 Notice for Leave for Our Key Personnel (Project Manager).pdf |
| 12/28/2018 | 1174 | 1174 SMC4-LT-19 Inspection Minute of Laboratory LAS-XD 1733 of TIEN THANH JSC.pdf |
| 12/29/2018 | 1175 | 1175 SMC4-LC-378 Notice òn Demobilization of Drilling Machine of Team10 414 Co..pdf |
| 12/29/2018 | 1176 | 1176 SMC4-LC-376 Slope Protection of Detour Road on the Right Side from P38-P43 (Km1+990-Km2+010).pdf |
| 1/2/2019 | 1177 | 1177 SMC4-LC-377 Changing Design of Drainage Pipe Culvet D500.pdf |
| 1/2/2019 | 1178 | 1178 SMC4-LC-379 Report on Environment in Construction Stage (2nd Phase in December 2018, Parameter TSP).pdf |
| 12/29/2018 | 1179 | 1179 SMC4-LC-380 Position of the Upper Coupler & Upper Rebar B1, B2A of Super T Girder for Crossbeam Construction.pdf |
| 1/2/2019 | 1180 | 1180 SMC4-AD-19 As Built Drawings of CIP Concrete Pile for P28.pdf |
| 1/2/2019 | 1181 | 1181 SMC4-AD-20 As Built Drawings of CIP Concrete Pile for P33L.pdf |
| 1/3/2019 | 1182 | 1182 SMC4-MA-232 Report on Frequency Test of Reinforcing Steel of VGS for Super T Girder (4th) of Team 2 (407).pdf |
| 1/3/2019 | 1183 | 1183 SMC4-LC-381 Reult of Ultrasonic Test of CIP Piles at P27.pdf |
| 1/3/2019 | 1184 | 1184 SMC4-WD-174 WD for General Layout Drainage (2nd).pdf |
| 1/3/2019 | 1185 | 1185 SMC4-WD-175 WD of Superstructure - Steel Bridge - Detail of Segment 7 & 15-Ridig Pier Head.pdf |
| 1/3/2019 | 1186 | 1186 SMC4-WD-176 WD of Superstructure - General Dimension of Steel Girder.pdf |
| 1/3/2019 | 1187 | 1187 SMC4-LC-379A Document of Steel Import for Steel Bridge Fabrication of Thanh Long JSC.pdf |
| 1/3/2019 | 1188 | 1188 SMC4-LC-382 Acceptence of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Subtructure Work for P33L.pdf |
| 1/3/2019 | 1189 | 1189 SMC4-LC-383 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Constructure Work for P28.pdf |
| 1/2/2019 | 1190 | 1190 05-BQLDATL-GM Inviatation Letter Date 3.1.19.pdf |
| 1/3/2019 | 1191 | 1191 SMC4-MA-231A Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P38,P39 & P40 (5th).pdf |
| 1/4/2019 | 1192 | 1192 SMC4-WD-177 WD of Substructure pier P17 (2nd).pdf |
| 1/4/2019 | 1193 | 1193 SMC4-LC-384 Submission of weekly report No.33.pdf |
| 1/10/2019 | 1194 | 1194 SMC4-MS-114 MS of Gate Arrangment at P18-P19, P21-P22, P32-P33.pdf |
| 1/4/2019 | 1195 | 1195 SMC4-LC-385 Result of Ultrasonic Test of CIP Concrete Pile at P33R.pdf |
| 1/4/2019 | 1196 | 1196 SMC4-MA-233 Proposal of Mix Proportion for Trial Mix Class B2 at Viet Tiep & Batching Plant Transmeco.pdf |
| 1/4/2019 | 1197 | 1197 SMC4-LC-386 Propose to Use the Gate at P18-P19 for Casting Concrete at Piers P18, P19.pdf |
| 1/4/2019 | 1198 | 1198 SMC4-MA-234 Report on Frequency Test of Reinforcing Steel VGS Steel for Pile Cap, Pier Column, Pier Head P32, P33, P34, P35 (7th).pdf |
| 1/4/2019 | 1199 | 1199 SMC4-MC-08 Application for Interim Payment Certificate No.06 (Period 01Dec2018 to 31Dec2018).pdf |
| 1/5/2019 | 1200 | 1200 SMC4-LC-381A Engineer's Confirmation for Safety & Environmental Satisfaction (Dec2018).pdf |
| 1/5/2019 | 1201 | 1201 SMC4-MA-235 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile Pier P25 & P26 ( 1st).pdf |
| 1/5/2019 | 1202 | 1202 SMC4-LC-387 Replacement of Utility Engineer for HCRR3 Construction Project-PK1.pdf |
| 1/8/2019 | 1203 | 1203 SMC4-MA-237 Report on Test Result of Coupler D32 of Vinh Thuc Co.Ltd.pdf |
| 1/8/2019 | 1204 | 1204 SMC4-MA-238 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P25 & P26 (2nd).pdf |
| 1/9/2019 | 1205 | 1205 SMC4-MA-237A Profile of Manufacturer & Supplier for Painting Material for Steel Bridge Hai Phong Paint JSC (2nd).pdf |
| 1/9/2019 | 1206 | 1206 SMC4-LC-388-Notice of Equipment Demobilization of Team 4 - Co.422.pdf |
| 1/9/2019 | 1207 | 1207 SMC4-MA-236 Report on Frequency Test of PC Strand for Super T Girder (13th & 14th).pdf |
| 1/10/2019 | 1208 | 1208 SMC4-LC-389 Submission of Monthly Report No.8.pdf |
| 1/10/2019 | 1209 | 1209 SMC4-LC-390 Correction Items of the Design Drawing of Steel Pier Head & Girders of Steel Bridge.pdf |
| 1/24/2019 | 1210 | 1210 SMC4-MS-115 MS of Pier Head from P20-P22.pdf |
| 1/14/2019 | 1211 | 1211 SMC4-MS-116 Outline for Loading Test of Pier Head's Supporting System at P21.pdf |
| 1/9/2019 | 1212 | 1212 118-BQLDATL-DA1 Approval for Replacement of Key Personnel ( Quality Control Manager).pdf |
| 1/10/2019 | 1213 | 1213 SMC4-MA-236A Report on Frequency Test of PC Strand for Super -T Girder (12th).pdf |
| 1/10/2019 | 1214 | 1214 SMC4-MA-239 Report on Frequency Test on Reinforcing Steel Vietnam Germany Steel for Pile Cap, Pier Column, Pier Head P28(2nd); Pier Column, Pier Head P29 (5th); Pier Head P30 &P31 (5th).pdf |
| 1/10/2019 | 1215 | 1215 SMC4-RP-34 Report for Loading Test of Pier Head's Supporting System at P31.pdf |
| 1/10/2019 | 1216 | 1216 SMC4-LC-391 Submission of Weekly Report No.34.pdf |
| 1/10/2019 | 1217 | 1217 SMC4-MA-240 Report on Test Result of Epoxy Coated PC Strand & Anchorage of Zhemao Science & Technology Co.,Ltd.pdf |
| 2/20/2019 | 1218 | 1218 SMC4-MS-117 MS of Pier Head from P32-P35.pdf |
| 1/12/2019 | 1219 | 1219 SMC4-WD-178 WD of Substructure - Pier P23 (2nd).pdf |
| 1/12/2019 | 1220 | 1220 SMC4-WD-179 WD of Substructure P27 (2nd).pdf |
| 1/12/2019 | 1221 | 1221 SMC4-MA-242 Report on Frequency Test of Epoxy Coated PC Strand & Anchorage of Zhemao Science & Technology Co.,LTd (1st).pdf |
| 1/12/2019 | 1222 | 1222 SMC4-MA-243 Report on Test Result of Jack & Synchronous Experiment of Jack, PC Strand, Anchorage for Post- Tensioning Pre Stressed Cantilever Pier Head (1st).pdf |
| 1/14/2019 | 1223 | 1223 SMC4-MA-241 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of Pier P23 & P24 (1st).pdf |
| 1/22/2019 | 1224 | 1224 SMC4-LC-392 Additional Supervision Cost of Engineer's Staff ( Oct2018).pdf |
| 1/14/2019 | 1225 | 1225 SMC4-MA-244 Report on Frequency Test of PC Strand for Super T Girder (15th).pdf |
| 1/14/2019 | 1226 | 1226 SMC4-LC-393 Term of Reference for Ultrasonic Test, Tip Contact Checking Test ( Stage 2).pdf |
| 1/14/2019 | 1227 | 1227 SMC4-MA-245 Report on Frequency Test of Reinforcing Steel Vietnam Germany Steel for CIP Concrete Pile of P14,P15.pdf |
| 1/14/2019 | 1228 | 1228 SMC4-MA-246 Mix Proportion for Mix Class A ( Ver.2) at Batching Plant Viet Tiep.pdf |
| 1/14/2019 | 1229 | 1229 SMC4-MA-247 Capacity Profile of Manufacturer & Supplier for Welding Material for Steel Bridge- Huyndai Welding Co.,Ltd (2nd).pdf |
| 1/14/2019 | 1230 | 1230 SMC4-LC-334 Notice on Tet Holiday Schedule of The Contractor.pdf |
| 1/14/2019 | 1231 | 1231 SMC4-LC-395 Reply to Engineer's Letter on Disposal Area.pdf |
| 1/14/2019 | 1232 | 1232 SMC4-LC-396 Report on Environment Monitoring in Construction Stage (erd Phase in Dec2018 & 1st Jan 19, Parameter TSP).pdf |
| 1/15/2019 | 1233 | 1233 SMC4-AD-21 As Build Drawings of CIP Concrete Pier P33R.pdf |
| 1/21/2019 | 1234 | 1234 SMC4-MS-118 Calculation of Tendon cable Elongation for Pier Head from P30-P31.pdf |
| 1/15/2019 | 1235 | 1235 SMC4-MS-119 Outline for loading test of Pier head's Supporting System at P34.pdf |
| 1/15/2019 | 1236 | 1236 SMC4-LP-0033-Report and proposal for countermeasures for detour road slope protection P38-P40.pdf |
| 1/15/2019 | 1237 | 1237 SMC4-MA-0248 Report on Frequency test of Reinforcing Steel-VN Germany steel for Pile Cap,Pier column,pier head of Pier P19(4th).pdf |
| 1/15/2019 | 1238 | 1238 SMC4-251 Report on frequency test of cement and water for Grouting Sonic tube(3rd ).pdf |
| 1/15/2019 | 1239 | 1239 SMC4-MA-250 Report on Frequency test of Reinforcing steel for Pier Column and Pier head of Pier P36,P37(5th)...Pier P38.pdf |
| 1/15/2019 | 1240 | 1240 SMC4-MA-249 Report on Frequency test of Reinforcing steel-VN For Pile cap,Pier Column,pier head P32,33,34,35.pdf |
| 1/15/2019 | 1241 | 1241 SMC4-LC-0397 Proposal for Acceptance of CIP Concrete Pile Foundation Construction stage and transfer to construction of Substructure work for P33R.pdf |
| 2/16/2019 | 1242 | 1242 SMC4-MA-243A Report on Test Result of Expansion Admixture VT-TN01.pdf |
| 1/16/2019 | 1243 | 1243 SMC4-LC-398 Submission of Weekly Report No.35.pdf |
| 1/16/2019 | 1244 | 1244 SMC4-MS-120 Outline for Loading Test of Pier Head Supporting System P37.pdf |
| 1/16/2019 | 1245 | 1245 SMC4-RP-35 Report for Loading Test of Pier Head's Supporting System P21.pdf |
| 1/16/2019 | 1246 | 1246 SMC4-RP-36 Topographic Survey Report at section from Km2+225 to Km2+350.pdf |
| 1/16/2019 | 1247 | 1247 Working Minutes on Hand-over and Take-over of the Site.pdf |
| 1/15/2019 | 1248 | 1248 183 QD BQLDATL Approval Decision on Design Change document of Drainage System on Bridge at The Piers.pdf |
| 1/16/2019 | 1249 | 1249 191 BQLDATL-DHDA1 Road Marking for Traffic Control on Pham Van Dong Road.pdf |
| 1/16/2019 | 1250 | 1250 Invitation for Site Visit Date 18.1.19.pdf |
| 1/18/2019 | 1251 | 1251 SMC4-MS-121 Supplement Drawing the Divided Layer of Backfilling Foundation from P23-P28.pdf |
| 1/19/2019 | 1252 | 1252 SMC4-MA-252 Report on Frequency Test of Reinforcing Steel of Vietnam Germany Steel for Super T Girder (5th) of Team 2 (407Co.).pdf |
| 1/23/2019 | 1253 | 1253 SMC4-MA-253 Report on Frequency Test of Cement, Coarse Aggregates, Fine Aggregates, Water for Cement Concrete at ASEAN Batching ( 14th to 16th).pdf |
| 1/23/2019 | 1254 | 1254 SMC4-MA-254 Report on Frequency Test of Cement, Coarse Aggregate, Fine Aggregate & Admixture for Cement Concrete at Transmeco Batching Plant (2nd & 4th).pdf |
| 1/22/2019 | 1255 | 1255 SMC4-MA-255 Report on Trial Mix of Concrete Class A (Cement 525kg) for Viet Tiep Batching Plant (used BASF Admixture).pdf |
| 1/19/2019 | 1256 | 1256 SMC4-WD-180 WD for General Arrangement Location of Traffic Signs Expressway Section Km0+700-Km2+812.5 (2nd).pdf |
| 1/19/2019 | 1257 | 1257 SMC4-WD-181 WD of Structure Excavation for Section P11-P17, P38-P43.pdf |
| 1/19/2019 | 1258 | 1258 SMC4-WD-182 WD of CIP Pile for P46 (2nd).pdf |
| 1/19/2019 | 1259 | 1259 SMC4-WD-183 WD of CIP Concrete Pile P47 (2nd).pdf |
| 1/19/2019 | 1260 | 1260 SMC4-WD-184 WD of CIP Concrete Pile for P48 (2nd).pdf |
| 1/22/2019 | 1261 | 1261 SMC4-LC-399 Report on Incidents of SuperT Girder Using Concrete Privided by Viet Tiep Batching Plant.pdf |
| 1/19/2019 | 1262 | 1262 SMC4-MA-256 TOR of Concrete Quality Control.pdf |
| 1/21/2019 | 1263 | 1263 SMC4-MS-122 MS for Lower Part of Pier Head from P23-P28.pdf |
| 1/21/2019 | 1264 | 1264 SMC4-MS-123 Supplement Method Drawing the Divided Layer of Backfilling Foundation from P15-P18.pdf |
| 1/21/2019 | 1265 | 1265 SMC4-MS-124 Supplement Method Drawing the Lower Part of Pier Head P19.pdf |
| 1/21/2019 | 1266 | 1266 SMC4-LC-400 Changing Diameter of Shear Stud of Girder of Steel Bridge.pdf |
| 1/21/2019 | 1267 | 1267 SMC4-MS-125 Outline for Loading Test of Pier Head's Supporting System at P22.pdf |
| 1/21/2019 | 1268 | 1268 SMC4-WD-185 WD of Adjustment for Exterior Girder, Spans 10-16, 24-28 & 32.pdf |
| 1/21/2019 | 1269 | 1269 SMC4-WD-186 WD of Substructure - Pier P16 (2nd ).pdf |
| 1/22/2019 | 1270 | 1270 SMC4-MA-257 Using Mix Proportion Class A ( Cement 525 kg) at Viet Tiep Batching Plant for Construction of Super T Girder.pdf |
| 1/22/2019 | 1271 | 1271 SMC4-LC-401 Result of Ultrasonic Test of CIP Concrete Piles at P24.pdf |
| 1/23/2019 | 1272 | 1272 SMC4-MS-126 Document of Protection & Relocation Existing Utilities at P26.pdf |
| 1/23/2019 | 1273 | 1273 SMC4-RP-37 Report for Pile Dynamic Analysis Test of CIP Concrete Pilling, Pile C4-P42.pdf |
| 1/22/2019 | 1274 | 1274 SMC4-MS-127 MS for Transportation of Super T Girder.pdf |
| 1/23/2019 | 1275 | 1275 SMC4-MA-258 Report on Frequency Test of Reinforcing Steel VGS Steel for Pile Cap, Pier Column, Pier Head P32, P33, P34, P35 (9th).pdf |
| 1/23/2019 | 1276 | 1276 SMC4-LC-402 Report on Environment Monitoring in Construction Stage (Dec 18 base on EMP).pdf |
| 1/23/2019 | 1277 | 1277 SMC4-LC-403 Result of Ultrasonic Test of CIP Concrete Piles at P32C.pdf |
| 1/23/2019 | 1278 | 1278 SMC4-LC-404 Result of Tip Contact Checking Test of CIPConcrete Pile C5-P23.pdf |
| 1/23/2019 | 1279 | 1279 SMC4-RP-38 Report on Loading Test of Pier Head's Supporting System at P34.pdf |
| 1/23/2019 | 1280 | 1280 SMC4-MA-259 Report on Frequencry Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head P20, P22 (3rd).pdf |
| 1/23/2019 | 1281 | 1281 SMC4-LC-405 The Contractors Schedule Plan Until 31st Mar 2019.pdf |
| 1/23/2019 | 1282 | 1282 SMC4-MS-128 MS of Pier Column from P17 to P18.pdf |
| 3/5/2019 | 1283 | 1283 SMC4-MS-129 MS of Pier Head from P36-P37.pdf |
| 1/24/2019 | 1284 | 1284 SMC4-AD-22 AsBuilt Drawings of CIP Concrete Pile for P24.pdf |
| 1/24/2019 | 1285 | 1285-NST-1112 Proposal for Applying the Primer Coating Layer.pdf |
| 1/25/2019 | 1286 | 1286 SMC4-LC-408 Breakdown of Cost for Changing Foundation Structure from Rotation Steel Pile to CIP Concrete Pile P9-P15, P45-P58.pdf |
| 1/25/2019 | 1287 | 1287 SMC4-LC-406 Report on Environment Monitoring in Construction Stage (2nd Phase in Jan 2019, Parameter TSP).pdf |
| 1/25/2019 | 1288 | 1288 SMC4-LC-407 Submission of Weekly Report No. 36.pdf |
| 1/25/2019 | 1289 | 1289 SMC4-LP-34 VAT Invoices for Interim Payment Certificate No.04 of PK1.pdf |
| 1/25/2019 | 1290 | 1290 SMC4-LP-35 VAT Invoices for Interim Payment Certificate No.05 off PK1.pdf |
| 1/25/2019 | 1291 | 1291 SMC4-LP-36 VAT Invoices for Interim Payment Certificate No.06 of PK1.pdf |
| 1/28/2019 | 1292 | 1292 SMC4-LC-409 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P24.pdf |
| 1/28/2019 | 1293 | 1293 SMC4-LC-410 Engineer's Confirmation for Safety & Environment Satisfaction ( January-2018).pdf |
| 1/29/2019 | 1294 | 1294 SMC4-MC-09 Interim Payment Certificate No.07 ( Period 01st Jan2019 to 25th Jan2019).pdf |
| 1/28/2019 | 1295 | 1295 SMC4-MA-260 Report on Test of Cement, Coarse Aggregate, Fine & Water for Cement Conscrete at Transmeco BP ( 5th to 7th).pdf |
| 1/28/2019 | 1296 | 1296 SMC4-MA-261 Report on Result of Jack & Experiment of Jack, PC Strand, Anchorage for Post- Tensioning Pre Stressed Cantilever Pier Head (2nd sub).pdf |
| 1/28/2019 | 1297 | 1297 SMC4-LC-411 Report on Inspection of Current Pavement Structure at Section P12=P43 & Proposed Backfill Structure at P12-P43.pdf |
| 1/28/2019 | 1298 | 1298 SMC4-LC-412 Report on Environment Monitoring in Construction Stage- 3rd Phase of Dec2018 & 1st Phase of Jan2019 (2nd submission).pdf |
| 1/28/2019 | 1299 | 1299 SMC4-LC-413 Notice of Environnmental Monitoring Schedule in Feb 2019 at Construction Phase.pdf |
| 1/29/2019 | 1300 | 1300 SMC4-RP-39 Incident Report on Construction of CIP Concrete Pilling- Pile No.9 of Pier 25.pdf |
| 1/29/2019 | 1301 | 1301 SMC4-MS-130 Traffic Control Plan for Public Road for Construction at Sectiont P46-P60.pdf |
| 1/29/2019 | 1302 | 1302 SMC4-MS-131 Calculation of Tendon Cable Elongation for Pier Head from P21-P22.pdf |
| 1/29/2019 | 1303 | 1303 SMC4-MA-262 Report on Frequency Test of Epoxy Coated PC Strand of Zhemao Science & Technology Co. LTD Used for Pier Head (2nd).pdf |
| 1/29/2019 | 1304 | 1304 SMC4-MA-263 Report on Test Result of No Shrink, Flowable Gout NUCEMIX G50, NUCTECH-CT JSC.pdf |
| 1/29/2019 | 1305 | 1305 SMC4-MA-264 Report on Frequency Test of PC Strand for Super T Girder (16th).pdf |
| 1/28/2019 | 1306 | 1306 93-GEN-0689-1.01 Lunar Tet Holiday Notice.pdf |
| 1/30/2019 | 1307 | 1307 SMC4-MA-265 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile pier P11, P12, P13 (3rd).pdf |
| 1/30/2019 | 1308 | 1308 SMC4-RP-40 Report for Pile Nynamic Analysis Test of CIP Concrete Pilling. Pile C2-P23.pdf |
| 1/30/2019 | 1309 | 1309 SMC4-LC-415 Submission of Weekly Report No.37.pdf |
| 1/30/2019 | 1310 | 1310 SMC4-LC-414 Submission of Inspection Minutes & Quantity Table of Waste Disposal Implemented by the Subcontractors at Nguyen Khe from Nov till Dec 2018.pdf |
| 1/31/2019 | 1311 | 1311 SMC4-LC-416 Report on Environment Monitoring in Construction Stage (3rd Phase in Jan 2019. Parameter TSP).pdf |
| 1/30/2019 | 1312 | 1312 400 PMUTL-DHDA1 Assurance of safety and Environmental hygiene During Lunar Tet of the Year of Pig 2019.pdf |
| 1/31/2019 | 1313 | 1313 SMC4-WD-187 WD of Backfill for Section P19-P31.pdf |
| 1/31/2019 | 1314 | 1314 SMC4-WD-188 WD for Basement for Traffic Sign Board at Pier P34.pdf |
| 1/31/2019 | 1315 | 1315 SMC4-MA-267 TOR for Testing of Elastomeric Bearing (2nd).pdf |
| 2/27/2019 | 1316 | 1316 SMC4-MS-132 Resubmission of Method Statement of Steel Bridge Fabrication of Thanh Long Group JSC (2nd).pdf |
| 1/31/2019 | 1317 | 1317 SMC4-MA-266 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column and Pier Head of Pier P23 and P24 (2nd).pdf |
| 1/31/2019 | 1318 | 1318 SMC4-LC-417 Report of Cracks on Super T Girders Found in November.pdf |
| 1/31/2019 | 1319 | 1319 SMC4-LC-189 Calculation Sheet for Camber of Steel Girder (3rd).pdf |
| 1/31/2019 | 1320 | 1320 SMC4-LC-118 Notification of Working Plan for Tet Holiday 2019 ( 1Feb2019-10Feb2019).pdf |
| 1/31/2019 | 1321 | 1321 426 PMUTL-DHDA1 Traffic Control and Environmental Hygiene in the Hanoi City.pdf |
| 2/12/2019 | 1322 | 1322 433 PMUTL-DHDA1 Design Modification of Relocation of Abutment A1.pdf |
| 2/12/2019 | 1323 | 1323 55 CQLXD-DB1 Report on Result of Site inspection.pdf |
| 2/12/2019 | 1324 | 1324 SMC4-MA-268 Improvement of Steel Storage and Arrangement on Site.pdf |
| 2/12/2019 | 1325 | 1325 905 TB-SGTVT Notice on Alternative for traffic diversion and Traffic control on Pham Van Dong.pdf |
| 2/12/2019 | 1326 | 1326 SMC4-LC-419 Notification of the Replacement of the Contractor's Deputy Project Manager.pdf |
| 2/13/2019 | 1327 | 1327 SMC4-LC-421 Notice for leave for our key Personnel(Project Manager and Structure.pdf |
| 4/26/2019 | 1328 | 1328 SMC4-LC-420 Proposal for Changing Shape of Parapet's Start Rebar.pdf |
| 3/1/2019 | 1329 | 1329 SMC4-MS-133 Quality control-Assurance plan and Welding plan for steel Bridge Fabrication at Factory of Thanh Long Group JSC(2nd).pdf |
| 2/14/2019 | 1330 | 1330 23-TTHNDTNN-GD3 Notice on Plan for Site Inspection to the HCRR3 Construction Project MD-STL Section.pdf |
| 2/13/2019 | 1331 | 1331 126 GM-BGTVT Invitattion Letter Date 13.2.19.pdf |
| 2/14/2019 | 1332 | 1332 1014-BGTVT-CQLXD Strengthening Quality Control, Progress & Labor Safety in HCRR3 Construction Project MD-STL Section.pdf |
| 2/19/2019 | 1333 | 1333 SMC4-LC-422 Additional Supervision Cost of Engineer's Staff ( Nov 2018).pdf |
| 2/14/2019 | 1334 | 1334 SMC4-WD-190 WD for Basement for Traffic Sign Board at P34 & P37.pdf |
| 2/15/2019 | 1335 | 1335 Minutes of Discussion on Addendum No.02 PK1.pdf |
| 2/15/2019 | 1336 | 1336 SMC4-RP-41 Report for Loading Test of Pier Head's Supporting System at P22.pdf |
| 2/15/2019 | 1337 | 1337 SMC4-RP-42 Report for Loading Test of Pier Head's Supporting System at P37.pdf |
| 2/15/2019 | 1338 | 1338 SMC4-LC-424 Submission of Monthly Report No.9.pdf |
| 2/16/2019 | 1339 | 1339 SMC4-MS-134 Outline for Loading Test of Pier Head's Supporting System at P30.pdf |
| 2/16/2019 | 1340 | 1340 SMC4-LC-423 Report on Inspection of Current Pavement Structure at Section P12-P43 & Backfill Structure at Section P12-P43.pdf |
| 2/16/2019 | 1341 | 1341 SMC4-MS-136 Outline for Loading Test of Pier Head's Supporting System at P19.pdf |
| 2/21/2019 | 1342 | 1342 SMC4-MS-135 Document of Protection & Relocation Existing Utilities P26 (2nd).pdf |
| 2/18/2019 | 1343 | 1343 SMC4-LC-425 Breakdown of Cost for Changing Foundation & Pile Cap Elevation P44, P59, P60.pdf |
| 2/19/2019 | 1344 | 1344 1279-BGTVT-CQLXD Modification of Some Contracts for PK1 & PK2.pdf |
| 2/19/2019 | 1345 | 1345 SMC4-LC-426 Submission of Weekly Report No.38.pdf |
| 2/20/2019 | 1346 | 1346 SMC4-MS-138 MS of Gate Arrangement at P19-P20.pdf |
| 2/20/2019 | 1347 | 1347 SMC4-MS-137 MS of Traffic Control for Public Road at P38-P60- Vol VII-1 Arranging Traffic Control at P46-P48 &P57-P60.pdf |
| 2/20/2019 | 1348 | 1348 SMC4-MS-139 MS of Temporary Facilities Arrangement on Site from P46-P48.pdf |
| 2/20/2019 | 1349 | 1349 SMC4-LC-427 Result of Ultrasonic Test of CIP Piles P27.pdf |
| 2/20/2019 | 1350 | 1350 SMC4-LC-428 Result of Ultrasonic Test of CIP Concrete Piles P23.pdf |
| 2/22/2019 | 1351 | 1351 SMC4-MA-269 Capacity Profile of Manufacturer & Supplier for Connectors for Steel Bridge-Samjin Fastners - Duc Son (2nd submission).pdf |
| 2/22/2019 | 1352 | 1352 SMC4-MA-273 Report on Trial Mix of Concrete Class B2 of Transmeco BP.pdf |
| 2/22/2019 | 1353 | 1353 SMC4-MA-274 Report on Trial Mix of Concrete Class B2 of Viet Tiep.pdf |
| 3/1/2019 | 1354 | 1354 SMC4-MS-140 The Pile Head Treatment Method for CIP Concrete Pilling- Pile No C5 of P27.pdf |
| 2/22/2019 | 1355 | 1355 SMC4-WD-191 WD of Backfill for Section P12-P18 & P33-P40.pdf |
| 2/22/2019 | 1356 | 1356 SMC4-WD-192 WD for Basement for Traffic Sign Board at P37 (2nd).pdf |
| 2/22/2019 | 1357 | 1357 SMC4-WD-193 Calculation Sheet & WD of Deck Slab of Steel Bridge Including KAWADA Certification & JBA (2nd).pdf |
| 2/22/2019 | 1358 | 1358 SMC4-MS-142 MS for Transportation of Super T Girder.pdf |
| 2/22/2019 | 1359 | 1359 SMC4-AD-23 As Built Drawings of CIP Concrete Pile for P23.pdf |
| 2/25/2019 | 1360 | 1360 1182-SGTVT-QLKCHTGT Suspension of Works in Service of Diplomatic Delegations in Feb2019 in Hanoi.pdf |
| 2/22/2019 | 1361 | 1361 549-PMUTL-DA1 Approval of TOR & Cost Estimates for Traffic Control ( Stage 1).pdf |
| 2/22/2019 | 1362 | 1362 SMC4-MA-275 Capacity Profile of Minh Tam BP (2nd).pdf |
| 2/22/2019 | 1363 | 1363 SMC4-WD-195 WD of Adjustment for Exterior Girder Span 36 (P35-P36).pdf |
| 2/22/2019 | 1364 | 1364 SMC4-LC-429 Submission of Weekly Report No.40.pdf |
| 2/22/2019 | 1365 | 1365 SMC4-RP-43 Topographic Survey Report at Section From Km2+640-Km2+812.50.pdf |
| 2/22/2019 | 1366 | 1366 SMC4-WD-194 WD of CIP Concrete Pile for P57.pdf |
| 3/6/2019 | 1367 | 1367 SMC4-LC-430 Cost Estimate for Test on Concrete Pile- Ultrasonic Test, Tip Contact Checking Test on CIP Concrete Piles (Stage 2).pdf |
| 2/23/2019 | 1368 | 1368 SMC4-WD-196 WD of Adjustment for Exterior Girder Span 38 (P37-P38).pdf |
| 2/23/2019 | 1369 | 1369 SMC4-WD-197 WD for Basement for Traffic Sign Board at Pier P35.pdf |
| 2/23/2019 | 1370 | 1370 SMC4-WD-198 WD of CIP Concrete Pile for P59 (2nd).pdf |
| 2/23/2019 | 1371 | 1371 SMC4-WD-199 WD of CIP Concrete Pile for Pier P60 (2nd).pdf |
| 2/23/2019 | 1372 | 1372 SMC4-LC-431 Acceptance of Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P23.pdf |
| 2/25/2019 | 1373 | 1373 SMC4-MA-270 Capacity Profile of Manufacturer & Supplier of Drainage Pipe Material.pdf |
| 3/18/2019 | 1374 | 1374 SMC4-MA-271 Capacity Profile of Manufacturer & Supplier of Membrane on Pier Head for Friction Cut Material-SBS.pdf |
| 2/25/2019 | 1375 | 1375 SMC4-MA-272 Capacity Profile of Manufacturer& Supplier of Membrane on Pier Head for Friction Cut Material -LEMAX 4mm PE-APP.pdf |
| 3/14/2019 | 1376 | 1376 SMC4-MS-143 MS of Pier Head from P19 and P23-P26.pdf |
| 2/25/2019 | 1377 | 1377 SMC4-MS-144 Outline for Loading Test of Pier Head's Supporting System at P33.pdf |
| 2/25/2019 | 1378 | 1378 SMC4-MS-145 Supplement & Updating MS Plan Drawing of CIP Concrete Pilling from P46-P48 & P57-P60.pdf |
| 2/25/2019 | 1379 | 1379 SMC4-LC-432 Additional Supervision Cost of Engineer's Staff ( Dec2019).pdf |
| 2/25/2019 | 1380 | 1380 580 PMUTL-DHDA1 Suspension of Works for Services of Diplomatic Delegation in February 2019 in Ha Noi.pdf |
| 3/4/2019 | 1381 | 1381 SMC4-WD-200 WD of CIP Concrete Pile for P58 (2nd).pdf |
| 2/26/2019 | 1382 | 1382 SMC4-MS-146 MS of Temporary Facilities Arrangement on Site from Pier P57-P60.pdf |
| 2/26/2019 | 1383 | 1383 SMC4-LC-433 Notice of Environmental Monitoring Schedule in Mar2019 at Construction Phase.pdf |
| 2/26/2019 | 1384 | 1384 SMC4-MA-276 Capacity Profile of Supplier & Manufacturer of Shape Steel for Steel Bridge Hanwa Co.Ltd-Nippon Steel & Sumitomo Metal Corp.pdf |
| 2/26/2019 | 1385 | 1385 SMC4-MA-277 Report on Frequency Test of Reinforcing Steel for Super T Girder (3rd) of Team 1.pdf |
| 2/26/2019 | 1386 | 1386 SMC4-MA-278 Report on FrequencyTest of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head of P19 (5th).pdf |
| 2/27/2019 | 1387 | 1387 SMC4-MA-279 Primer Coating of Paining Material for Steel Bridge of Manufacturer & Supplier Hai Phong Paint JSC.pdf |
| 2/27/2019 | 1388 | 1388 SMC4-MA-280 Capacity Profile of Manufacturer & Supplier Viet Thang LTD Co for Stainless Steel 3mm of Super Structure.pdf |
| 2/27/2019 | 1389 | 1389 SMC4-LC-434 Reply to the Engineer's Letter Regarding Document for Manpower & Equipment Mobilization of Thanh Long Gr JSC.pdf |
| 3/1/2019 | 1390 | 1390 SMC4-LC-435 Submission of Weekly Report No.41.pdf |
| 3/1/2019 | 1391 | 1391 634-PMUTL-DHDA1 Approval of TOR & Cost Estimate of Environmental Monitoring.pdf |
| 3/1/2019 | 1392 | 1392 SMC4-LC-436 Report on Environment Monitoring in Construction Stage (1st Phase in Feb 2019, Parameter TSP).pdf |
| 3/1/2019 | 1393 | 1393 SMC4-MA-281 Report on Frequency Test of Reinforcing Steel for Super T Girder (4th) of Team 4(Co 422).pdf |
| 3/1/2019 | 1394 | 1394 SMC4-WD-201 WD of Structure Excavation for Section P11-P17, P38-P43 (2nd).pdf |
| 3/2/2019 | 1395 | 1395 SMC4-LC-437 Result of Ultrasonic Test of CIP Concrete Piles at P17.pdf |
| 3/2/2019 | 1396 | 1396 SMC4-MA-282 Capacity Profile of Manufacturer for Steel Plate for Grading & Stainless Steel 3mm -412 JSC.pdf |
| 3/2/2019 | 1397 | 1397 SMC4-MA-283 Report on Test Result of Coupler D25 of Vinh Thuc Co..pdf |
| 3/2/2019 | 1398 | 1398 SMC4-MA-284 Report on Frequency Test of Reinforcing Steel VGS for Piel Cap, Pier Column of P17.pdf |
| 3/2/2019 | 1399 | 1399 SMC4-LC-438 Notice for leave for key personnel (Quality Control Manager).pdf |
| 3/2/2019 | 1400 | 1400 SMC4-LC-439 Notice of possibility of the prolongation of Project Completion Period.pdf |
| 3/2/2019 | 1401 | 1401 SMC4-MS-147 Method Statement of Strucure Excavation from P38-P40.pdf |
| 3/2/2019 | 1402 | 1402 SMC4-MS-148 Outline for Loading Test of Pier Head's Supporting System at P20.pdf |
| 3/14/2019 | 1403 | 1403 SMC4-MS-149 MS of Structure Excavation from P41-P42.pdf |
| 3/2/2019 | 1404 | 1404 SMC4-MA-285 Report on Frequency Test of PC Strand for Super T Girder (17th).pdf |
| 3/4/2019 | 1405 | 1405 SMC4-WD-202 WD of Superstructure -Steel Bridge- Detail of Segment 7 & 15 - Ridig Pier Head (2nd).pdf |
| 3/4/2019 | 1406 | 1406 SMC4-WD-203 WD General View of Main Bridge & Ramp HQV-B (6th).pdf |
| 3/4/2019 | 1407 | 1407 689-GM-BQLDATL Invitation Monthly Meeting.pdf |
| 3/4/2019 | 1408 | 1408 SMC4-MA-286 Report on Frequency Test of Epoxy Coated PC Strand & Anchorage(2nd) of Zhemao for Used for Pier Head.pdf |
| 3/4/2019 | 1409 | 1409 SMC4-AD-24 Asbuilt Drawings of CIP Concrete Pile for Pier P17.pdf |
| 3/6/2019 | 1410 | 1410 SMC4-LC-441 Notice on Mobilization of Team 5.pdf |
| 3/6/2019 | 1411 | 1411-SMC4-MS-150 Calculation of Tendon Cable Elongation for Pier Head from P37.pdf |
| 3/7/2019 | 1412 | 1412 SMC4-AD-25 As Built Drawings of CIP Concrete Pile for Pier P27.pdf |
| 3/7/2019 | 1413 | 1413 SMC4-MA-287 Report on Test Result of Axiliary Steel Material of Super T Girder of Vinh Thuc Co.Ltd.pdf |
| 3/7/2019 | 1414 | 1414 SMC4-LC-442 Replacing Some Girders On Span 31 of the Same Type during Launching.pdf |
| 3/7/2019 | 1415 | 1415 SMC4-WD-204 WD of Backfill Structure at P21, P22, P30, P31.pdf |
| 3/8/2019 | 1416 | 1416 SMC4-MA-286A Capacity Prifile of Manufacturer and Supplier for HPDE Conduit Santos JSC.pdf |
| 3/8/2019 | 1417 | 1417 SMC4-LC-443 Report on Environment Monitoring in Consruction Stage (2nd Phase in Feb 2019, Parameter TSP).pdf |
| 3/8/2019 | 1418 | 1418 SMC4-LC-444 Notice of Environmental Monitoring Schedule in Mar 2019 at Construction Phase (2nd).pdf |
| 3/8/2019 | 1419 | 1419 SMC4-RP-44 Pile Head Treatment Report for CIP Concrete Pile No.05 of P27.pdf |
| 3/8/2019 | 1420 | 1420 SMC4-WD-205 WD of Substructure - Pile Cap of Pier P40 (2nd).pdf |
| 3/8/2019 | 1421 | 1421 SMC4-WD-206 WD of Substructure - Pile Cap of Pier P41.pdf |
| 3/8/2019 | 1422 | 1422 SMC4-WD-207 WD of Substructure - Pile Cap of Pier P42.pdf |
| 3/8/2019 | 1423 | 1423 SMC4-WD-208 WD of Substructure - Pile Cap of Pier P38.pdf |
| 3/8/2019 | 1424 | 1424 SMC4-WD-209 WD of Substructure - Pile Cap of Pier P39.pdf |
| 3/12/2019 | 1425 | 1425 SMC4-LC-445 Mobilization Document for Manpower & Equipment of BOT Vinh City Bypass Branch for Substructure Work.pdf |
| 3/12/2019 | 1426 | 1426 SMC4-LC-447 Proposal for 2 Crane Mobilization Documents for Superstructure Work at the Area P28-P31 under Scope Co.414.pdf |
| 3/8/2019 | 1427 | 1427 SMC4-LC-446 Notice of Equipment Demobilization - Bored Pile Drilling Machine at P38-P40 of 423.pdf |
| 3/8/2019 | 1428 | 1428 SMC4-RP-45 Report on Loading Test of Pier Head's Supporting System at P19.pdf |
| 3/12/2019 | 1429 | 1429 SMC4-MA-288 Capacity Profile Manufacturer & Supplier for Bolts for Steel Bridge Oriental Metal - Duc Son Construction Material Co.,LTD.pdf |
| 3/8/2019 | 1430 | 1430 SMC4-LC-444A-Result of Ultrasonic Test of CIP Concrete Piles at P42C.pdf |
| 3/12/2019 | 1431 | 1431 SMC4-LC-444B Result of Ultrasonic Test of CIP Concrete Piles at P40.pdf |
| 3/12/2019 | 1432 | 1432 SMC4-MA-444C Result of Ultrasonic Test of CIP Concrete Piles at P41C.pdf |
| 3/8/2019 | 1433 | 1433 SMC4-MA-444D Result of Ultrasonic Test of CIP Concrete Pile at P41L.pdf |
| 3/8/2019 | 1434 | 1434 SMC4-MA-444E Result of Ultrasonic Test of CIP Concrete Piles at P42L.pdf |
| 3/20/2019 | 1435 | 1435-SMC4-LT-20-Update and extend document of LAS-XD668.pdf |
| 3/12/2019 | 1436 | 1436-SMC4 -LC-0448 Variation Oder No.VO-HRR3-PK1-002.pdf |
| 3/12/2019 | 1437 | 1437-SMC4-LC-450 Proposal for mobilization document of Co.422.pdf |
| 3/12/2019 | 1438 | 1438 SMC4-MA-289 Report on test result of coating paint Galbon.pdf |
| 3/12/2019 | 1439 | 1439 SMC4-449 Engineer's Confirmation for Safety & Environment Satisfaction (Jan 26 to Feb 28,2019).pdf |
| 3/12/2019 | 1440 | 1440 SMC4-MA-290 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column of P27.pdf |
| 3/29/2019 | 1441 | 1441 SMC4-MS-151 MS for Erection of Super T Girder S22(P21-P22) & S31(P30-P31).pdf |
| 3/12/2019 | 1442 | 1442-SMC4-WD-0210 Proposal for WD of substructure - pier P46.pdf |
| 3/12/2019 | 1443 | 1443 SMC4-AD-26 As Built Drawings of CIP Concete Pile for Pier P35R.pdf |
| 3/13/2019 | 1444 | 1444 SMC4-LC-451 Submission of Monthly Report No.10.pdf |
| 3/13/2019 | 1445 | 1445 SMC4-MS-152 MS of Structure Excavation from P11-P14.pdf |
| 3/12/2019 | 1446 | 1446 SMC4-LC-452 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Subtructure Work for P35R.pdf |
| 3/13/2019 | 1447 | 1447 SMC4-MS-153 MS of Traffic Control for Public Road at P38-P60- Vol VII.2 Arranging Traffic Control at P46-P60 Stage 1.pdf |
| 3/13/2019 | 1448 | 1448 SMC4-MA-291Capacity Profile of Manufacturer & Supplier for Steel Plate for Grading & Stainless Steel 3mm- Co.412 (2nd).pdf |
| 3/13/2019 | 1449 | 1449 SMC4-LC-453 Result of Ultrasonic Test ofCIP Concrete Piles at P12.pdf |
| 3/13/2019 | 1450 | 1450 SMC4-LC-454 Result of Ultrasonic Test of CIP Concrete Pile at P13.pdf |
| 3/13/2019 | 1451 | 1451 SMC4-LC-455 Result of Tip Contact Checking Test of CIP Concrete Piles C6-P12.pdf |
| 3/13/2019 | 1452 | 1452 SMC4-LC-456 Result of Tip Contact Checking Test of CIP Conrete Piles C6-P41.pdf |
| 3/12/2019 | 1453 | 1453 Addendum No.2 PK1.pdf |
| 3/13/2019 | 1454 | 1454-MS-155 Report on Result of Pile Head Remedy of CIP Concrete Pile C5-P27.pdf |
| 3/13/2019 | 1455 | 1455 SMC4 - MC -10 Interim Payment Certificate No.08 (Period 26 Jan 2019, 28 Feb 2019 ).pdf |
| 3/13/2019 | 1456 | 1456 SMC4-MS-154 MS of Pile Cap P41-P42.pdf |
| 3/13/2019 | 1457 | 1457 SMC4-WD-211 WD of Backfill at Pier P18-P20.pdf |
| 3/13/2019 | 1458 | 1458 SMC4-LC-458 Report on Environment Monitoring in Construction Stage (3rd Phase in Feb. 2019, Parameter TSP).pdf |
| 3/13/2019 | 1459 | 1459 SMC4-MA-292 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column of P17 (2nd).pdf |
| 3/13/2019 | 1460 | 1460 SMC4-LC-459 Notice of Equipment Demobilization- Bored Pile Drilling Machine Soilmec SR-60 at P11-P13 of Co.422.pdf |
| 3/13/2019 | 1461 | 1461 SMC4-LC-460 Equipment Mobilization Document of IRE VN for Road Reinstatement Work.pdf |
| 3/14/2019 | 1462 | 1462 SMC4-MA-293 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of P23,P24(3rd) &P25,P26 (1st).pdf |
| 3/14/2019 | 1463 | 1463 SMC4-MA-294 Result of Ultrasonic Test of CIP Concrete Piles at P16.pdf |
| 3/14/2019 | 1464 | 1464 4715-TB-BQLDATL Notice on Conclusions Given by PMUTL in the Meeting to Review the Implementation of PK1,PK2.pdf |
| 3/14/2019 | 1465 | 1465 823-BALDATL-DHDA1 Invitation Letter to pay a site Inspection of Girder Transpotation Routs.pdf |
| 3/16/2019 | 1466 | 1466 SMC4-LC-156 Submission of Weekly Report No.42.pdf |
| 3/16/2019 | 1467 | 1467 SMC4-LC-157 Submission of Weekly Report No.43.pdf |
| 3/16/2019 | 1468 | 1468 SMC4-WD-212 WD of Deck Slab & Link Slab from Span P21-P31.pdf |
| 3/16/2019 | 1469 | 1469 SMC4-AD-27 AD of CIP Concrete Pile for P35L.pdf |
| 3/16/2019 | 1470 | 1470 SMC4-MA-295 Capacity Profile of Supplier & Manufacturer of Concrete Painting Material -Hiep An LTD.pdf |
| 3/16/2019 | 1471 | 1471 SMC4-MA-296 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of P38 (2nd), P39 P40(1st).pdf |
| 3/16/2019 | 1472 | 1472 SMC4-LP-37 Report on the Land Obstruction at Sections P38-P39, P44-P45 & P49-P55.pdf |
| 3/22/2019 | 1473 | 1473 SMC4-LC-460A Result of Ultrasonic Test of CIP Concrete Piles at P25.pdf |
| 3/22/2019 | 1474 | 1474 SMC4-LC-460B Result of Ultrasonic Test of CIP Concrete Piles at P43C.pdf |
| 3/19/2019 | 1475 | 1475 SMC4-RP-46 Report on Loading Test of Pier Head's Supporting System at P33.pdf |
| 3/18/2019 | 1476 | 1476 SMC4-MS-158 MS of Pile Cap from P14-P16.pdf |
| 3/18/2019 | 1477 | 1477 SMC4-LC-461 Adjusting Top Elevation of Bearing Pad in Accordance with Actual Camber of Super T Girders 38m & 37.3m.pdf |
| 3/18/2019 | 1478 | 1478 SMC4-LC-462 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Subtructure Work for P35L.pdf |
| 3/19/2019 | 1479 | 1479 SMC4-LC-463 Document for Mobilization of Subconstractor Multinational Transport JSC for Transportation & Erection Work of Super T Girders.pdf |
| 3/19/2019 | 1480 | 1480 SMC4-MS-159 Method Statement of Pile Cap P38-P40.pdf |
| 3/19/2019 | 1481 | 1481 SMC4-MA-298 Report on Frequency Test of Cement, Coarse Aggregate for Class A, Fine Aggregate for Cement Concrete at Viet Tiep BP (2nd to 4th).pdf |
| 3/27/2019 | 1482 | 1482 SMC4-WD-213 WD of General Dimension of Steel Girder (2nd).pdf |
| 3/19/2019 | 1483 | 1483 SMC4-MA-299 Grading Steel Plate & Stainless Steel 3mm Manufactured of KITCON Truong Thanh Co.Ltd & Supplied by 412 (3rd).pdf |
| 3/19/2019 | 1484 | 1484 SMC4-LC-464 Acceptance of CIP Concrete Pile Foundation Construction Stage & Tranfer to Construction of Substructure Work for P40.pdf |
| 3/21/2019 | 1486 | 1486 SMC4-WD-214 WD of Backfill for Section P11-P17, P23-P29, P33-P40.pdf |
| 3/21/2019 | 1487 | 1487 SMC4-LC-465 Variation Order No. VO-HRR3-PK1-003 - Environmental Monitoring.pdf |
| 3/19/2019 | 1488 | 1488 SMC4-MS-161 MS for Confirmation Quality of Concrete of CIP Concrete Pilling - C6P25.pdf |
| 3/19/2019 | 1489 | 1489 SMC4-AD-28 As Built Drawings of CIP Concrete Pile for Pier P40.pdf |
| 3/19/2019 | 1490 | 1490 SMC4-MA-232A Report on Test Result of Posco Steel Plate for Steel Bridge.pdf |
| 3/19/2019 | 1491 | 1491 SMC4-MS-162 Adjusted MS ofTraffic Control for Public Road at Section P46-P60 (phase 1).pdf |
| 3/20/2019 | 1492 | 1492 SMC4-LC-467 Notice of Delayed Instruction Regard WD of Section from A1-P10.pdf |
| 3/20/2019 | 1493 | 1493 SMC4-LC-466 Top Elevation of Bearing Pad in Accordance with Actual Camber of SPT Girder at Span S34.pdf |
| 3/20/2019 | 1494 | 1494 SMC4-WD-215 WD for Basement for Traffic Sign Board at P16.pdf |
| 3/20/2019 | 1495 | 1495 SMC4-WD-216 WD for Basement for Traffic Sign Board at P26.pdf |
| 3/20/2019 | 1496 | 1496 SMC4-MS-163 Supplement of Method Drawing of the Pier Column at P27.pdf |
| 3/20/2019 | 1497 | 1497 SMC4-LT-21 Capacity Profile of PHATECO JSC for Quality Control of Steel Structure.pdf |
| 4/5/2019 | 1498 | 1498 SMC4-MS-164 MS of Temporary Facilities Arrangement on Site from P49-P56.pdf |
| 3/21/2019 | 1499 | 1499 SMC4-MS-165 MS for Transportation the Test Model of Super T Girder.pdf |
| 3/21/2019 | 1500 | 1500 SMC4-MA-300 Report on Test Result of Elastomeric Bearing of Kawakin Co.Ltd & supplied by THQ Global JSC.pdf |
| 3/21/2019 | 1501 | 1501 SMC4-MA-301 Drawings & Calculation Sheet of Pot Bearing.pdf |
| 3/21/2019 | 1502 | 1502 SMC4-LC-468 Report on Environment Monitoring in Construction Stage (1st & 2nd Phase of Mar2019, Parameter TSP).pdf |
| 3/21/2019 | 1503 | 1503 SMC4-MS-166 Calculation of Tendon Cable Elongation for Pier Head P19.pdf |
| 3/21/2019 | 1504 | 1504 SMC4-MA-301A Capacity Profile of Manufacturer & Supplier for Bolts for Steel Bridge-Oriental & Duc Son Co.Ltd (2nd).pdf |
| 3/22/2019 | 1505 | 1505 SMC4-LC-469 Report on Obstructions & Recommendations for the Construction Area P38-P43.pdf |
| 3/22/2019 | 1506 | 1506 898-PMUTL-DA1 Approval of Variation Order No.VO-HRR3-PK1-002 Traffic Control for Public Roads (Stage 1).pdf |
| 3/22/2019 | 1507 | 1507 SMC4-LC-464A Notice for Leave of Key Personnel (Quality Control Manager).pdf |
| 3/22/2019 | 1508 | 1508 SMC4-AD-29 Asbuilt Drawing of CIP Concrete Pile for P16.pdf |
| 3/22/2019 | 1509 | 1509 SMC4-LC-471 Acceptance of PileFfoundation Stage & Transfer to Substructure Work P16.pdf |
| 3/22/2019 | 1510 | 1510 SMC4-LC-470 Submission of Weekly Report No.44.pdf |
| 3/22/2019 | 1511 | 1511 SMC4-MA-302 Test Result of Jack & Experiment of Jack, PC Strand, Anchorage for Post-Tesioning Pre Stressed Cantilever Pier Head (3rd).pdf |
| 3/22/2019 | 1512 | 1512 SMC4-MA-303 Report Frequency Test of PC Strand Type Guizhou for Super T Girder (19th).pdf |
| 3/22/2019 | 1513 | 1513 SMC4-MA-304 Report on Frequency Test of PC Strand Type Dong - il for Super T Girder (18th).pdf |
| 3/25/2019 | 1514 | 1514 SMC4-MA-308 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column, Pier Head of P36(6th),P38(3rd), P39 P40(2nd).pdf |
| 4/8/2019 | 1515 | 1515 SMC4-MA-307-Report on Frequency Test of Elastomeric Bearing of Manufactured by Kawakin CT VN Ltd, Supplied by THQ Global JSC.pdf |
| 3/25/2019 | 1516 | 1516 SMC4-MA-306 Report on Frequency Test of PC Strand Type Guizhou for Super T Girder (20th).pdf |
| 3/25/2019 | 1517 | 1517 SMC4-MA-305Capacity Profile of Manufacturer & Supplierfor Stud Connectors for Steel Bridge- Samjin Fastners-Duc Son Ltd (3rd).pdf |
| 3/25/2019 | 1518 | 1518 SMC4-WD-217 WD of Adjustment for Exterior Girder Span 33(P32-P33).pdf |
| 3/25/2019 | 1519 | 1519 SMC4-WD-218 WD of Diaphragm from Span 33 to 37.pdf |
| 3/25/2019 | 1520 | 1520 SMC4-WD-219 WD of Backfill for Sections P32, P41-P43, P46-P60.pdf |
| 3/25/2019 | 1521 | 1521 SMC4-WD-220 WD of Structure Excavation for P46-P60.pdf |
| 3/25/2019 | 1522 | 1522 SMC4-MS-167 MS of Adjusted Traffic Control for Public Road at Section P3-P17.pdf |
| 3/25/2019 | 1523 | 1523 SMC4-LC-474 Propose to Apply the Primer Coating Paint GALBON SP.pdf |
| 3/25/2019 | 1524 | 1524 SMC4-LC-473 Result of Ultrasonic Test of CIP Concrete Piles at P11.pdf |
| 3/25/2019 | 1525 | 1525 SMC4-RP-47 Topographic Survey Report at Section From Km2+350 to Km2+640.pdf |
| 3/25/2019 | 1526 | 1526 SMC4-LC-472 To Support the Contractor in Extending & Adjusting the Validity of the Method of Fencing, Traffic Control for Construction Project.pdf |
| 3/25/2019 | 1527 | 1527 970 BQLDATL-DHDA1 Invitation Letter date 26.3.19.pdf |
| 3/26/2019 | 1528 | 1528 SMC4-MA-310 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column of P16.pdf |
| 3/26/2019 | 1529 | 1529 SMC4-MA-309 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap,Pier Column, Pier Head of P32, P33,P34,P35(10th) & P41,P42,P43(1st).pdf |
| 3/26/2019 | 1530 | 1530 SMC4-LC-475 Additional Document for Manpower & Equipment Mobilization for Backfilling Work & Driving Sheet Pile Under Scope of 422 Co..pdf |
| 3/28/2019 | 1531 | 1531 SMC4-MS-168 Outline for Loading Test of Pier Head's Supporting System at P28, P29.pdf |
| 3/28/2019 | 1532 | 1532 SMC4-MS-169 Supplement of Method Drawing of Pier Head P28.pdf |
| 3/28/2019 | 1533 | 1533 SMC4-MS-170 Calculation of Tendon Cable Elongation for Pier Head at P20.pdf |
| 3/28/2019 | 1534 | 1534 SMC4-LC-476 Adjusting Top Elevation of Bearing Pad Girder in Accordance with Actual Camber of Super T Girders 34.3m.pdf |
| 3/28/2019 | 1535 | 1535 SMC4-AD-30 Asbuilt Drawings of Pre-Tensioning Pre Stressed Super T Girder Span 22(P21-P22).pdf |
| 3/28/2019 | 1536 | 1536 SMC4-MS-171 MS of Pre-Assembly for Steel Bridge at Thanh Long Factory.pdf |
| 3/28/2019 | 1537 | 1537 SMC4-MS-172 MS for Erection of Super T Girder.pdf |
| 3/28/2019 | 1538 | 1538 SMC4-AD-31 Asbuilt Drawings of Pre-Tensioning Pre Stressed Super T Girder Span 31(P30-P31).pdf |
| 3/28/2019 | 1539 | 1539 SMC4-WD-221 WD of CIP Concrete Pile for P53 (2nd).pdf |
| 3/28/2019 | 1540 | 1540 SMC4-WD-222 WD of CIP Concrete Pile for P54 (2nd).pdf |
| 3/28/2019 | 1541 | 1541 SMC4-WD-223 WD of CIP Concrete Pile for P55 (2nd).pdf |
| 3/28/2019 | 1542 | 1542 SMC4-WD-224 WD of Column & Pier Head of P41.pdf |
| 3/28/2019 | 1543 | 1543 SMC4-WD-225 WD of Column & Pier Head of P42.pdf |
| 3/28/2019 | 1544 | 1544 SMC4-LC-477 Report on Incident of Transformer Station No.2 at P39 on the Right Side.pdf |
| 3/28/2019 | 1545 | 1545 SMC4-LC-478 Submission of Weekly Report No.45.pdf |
| 3/28/2019 | 1546 | 1546 SMC4-LC-479 Replacement of Quality Control Manager - Mr. Nguyen Viet Hung.pdf |
| 3/28/2019 | 1547 | 1547 SMC4-LC-480 Acceptance of Sub-Structure Stage & Transfer to Superstructure Work for P21, P22.pdf |
| 3/29/2019 | 1548 | 1548 SMC4-MA-301B Report on Frequency Test of Reinforcing Steel VGS for PreCast Panel of Super T Girder (2nd).pdf |
| 3/29/2019 | 1549 | 1549 SMC4-LC-481 Comparison Table Structure Excavation Quantity Between Contract Drawing & Design Following Actual Existing Ground.pdf |
| 3/29/2019 | 1550 | 1550 SMC4-LC-482 Expected Plan of Transport & Eriction of the First Super T Girder Span S22.pdf |
| 4/1/2019 | 1551 | 1551 SMC4-AD-32 AsBuilt Drawings of CIP Concrete Piles for P41C.pdf |
| 4/1/2019 | 1552 | 1552 SMC4-LC-484 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P41C.pdf |
| 4/1/2019 | 1553 | 1553 SMC4-RP-48 Report on Survey of Existing Culvert Pipe D1250 of Ministry of Police Public.pdf |
| 4/1/2019 | 1554 | 1554 SMC4-WD-226 WD of Substructure P15.pdf |
| 4/1/2019 | 1555 | 1555 SMC4-WD-227 WD of Backfill for Sections P32, P41-P43, P46-P60 (2nd).pdf |
| 4/1/2019 | 1556 | 1556 SMC4-MA-312 Supplier Co.412 JSC for Steel Plate for Grading of Vinh Thuc Co. LTD.pdf |
| 4/1/2019 | 1557 | 1557 SMC4-MA-313 TOR for Testing of Pot Bearing.pdf |
| 4/1/2019 | 1558 | 1558 SMC4-LC-483 Result of Ultrasonic Test of CIP Concrete Piles at P14.pdf |
| 4/1/2019 | 1559 | 1559 SMC4-LC-486 Result of Ultrasonic Test of CIP Concrete Piles at P15.pdf |
| 4/1/2019 | 1560 | 1560 SMC4-LC-485 Result of Tip Contact Checking Test of CIP Concrete Pile C4-P15.pdf |
| 4/1/2019 | 1561 | 1561 SMC4-LC-489 Notice of Environmental Monitoring Schedule in April 2019 at Construction Phase.pdf |
| 4/1/2019 | 1562 | 1562 SMC4-LC-487 Result of Tip Contact Checking Test of CIP Concrete Pile -Pile No.C6P25.pdf |
| 4/4/2019 | 1563 | 1563 SMC4-LC-488 Report of Result for Confirmation Quality of Concrete of CIP Concrete Pile- Pile No.C6P25.pdf |
| 4/1/2019 | 1564 | 1564 SMC4-MS-176 Reconnect Culvert Pipe D1250 of Ministry of Police Public Plan (1).pdf |
| 4/1/2019 | 1565 | 1565 SMC4-MS-175 Method Statement for Remedial Measure of Pile Toe Defect C5P43.pdf |
| 4/1/2019 | 1566 | 1566 SMC4-MS-174 Outline for Loading Test of Pier Head's Supporting System at P36 (1).pdf |
| 4/1/2019 | 1567 | 1567 SMC4-MS-173 Calculation of Tendon Cable Elongation for Pier Head at P33.pdf |
| 4/1/2019 | 1568 | 1568 SMC4-LC-490 Report on Environment Monitoring in Construction Stage (Mar 2019 , Base on EMP).pdf |
| 4/1/2019 | 1569 | 1569 SMC4-LC-491 Report on Environment Monitoring in Construction Stage (3rd Phase in Mar 2019, Parameter TSP).pdf |
| 4/1/2019 | 1570 | 1570 SMC4-WD-228 WD of Diaphragm from Span 38-43.pdf |
| 4/1/2019 | 1571 | 1571 SMC4-WD-229 WD of CIP Concrete Pile for P52 (2nd).pdf |
| 4/1/2019 | 1572 | 1572 SMC4-WD-231 WD of Painting of Exterior Super T Girder from Span 10-16, 20-61.pdf |
| 4/1/2019 | 1573 | 1573 SMC4-WD-230 WD of CIP Concrete Pile for P56 (2nd).pdf |
| 4/1/2019 | 1574 | 1574 SMC4-WD-232 WD of Detail of Segments 6,8,14,16 of Steel Girder.pdf |
| 4/2/2019 | 1575 | 1575 SMC4-WD-233 WD of Substructure - Column & Pier Head P40 (2nd).pdf |
| 4/2/2019 | 1576 | 1576 SMC4-WD-234 WD of CIP Concrete Pile for P49 (2nd).pdf |
| 4/2/2019 | 1577 | 1577 SMC4-WD-235 WD of CIP Concrete Pile for P50 (2nd).pdf |
| 4/2/2019 | 1578 | 1578 SMC4-WD-236 WD of CIP Concrete Pile for P51 (2nd).pdf |
| 4/2/2019 | 1579 | 1579 SMC4-LC-493 Report on Some Defects on Concrete Surface at Pier Head P19 & Countermeasures.pdf |
| 4/2/2019 | 1580 | 1580 SMC4-LC-492 Contractor's Plan for Trial Transportation of Super T Girder Model & Next Related Work Items.pdf |
| 4/2/2019 | 1581 | 1581 315 19-JICA-YL Annual Disbursement Forecast for Japanese Fiscal Year (JFY) 2019.pdf |
| 4/2/2019 | 1582 | 1582 SMC4-LT-22 Capacity Profile of Laboratory ITST for Quality Control of Steel Structures (Additional submission).pdf |
| 4/2/2019 | 1583 | 1583 SMC4-MA-311 Report on Test Result of Jack & Synchronous Experiment of Jack, PC Strand, Anchorage for Post Tensioning Pre Stressed Cantilever Pier Head (4th).pdf |
| 4/4/2019 | 1584 | 1584 SMC4-MA-314 Report on Frequency Test of Cement, Coarse Aggregate, Fine Aggregate & Admixture for Cement Concrete at Transmeco BP (8th to 15th).pdf |
| 4/3/2019 | 1585 | 1585 SMC4-MA-315 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head of P41, P42, P43 (2nd).pdf |
| 4/3/2019 | 1586 | 1586 SMC4-LC-494 Submission of Report on Actual Condition of Cracks on Pier Head P19-P20.pdf |
| 4/3/2019 | 1587 | 1587 784 QD-TCDBVN Permit for Operation of Oversize Vehicle used for Transportation of Oversize cargo on the Road.pdf |
| 4/3/2019 | 1588 | 1588 759 QD-TCDBVN Approval decision on Establishment of Supervision Team for Trial transportion of Super T girder.pdf |
| 4/4/2019 | 1589 | 1589 SMC4-LP-38 Request for Reply the Letter Regarding Exchange Rate VAT Portion.pdf |
| 4/5/2019 | 1590 | 1590 SMC4-RP-47A Report for Loading Test of Pier Head's Supporting System at P20.pdf |
| 4/5/2019 | 1591 | 1591 SMC4-RP-49 Report for Loading Test of Pier Head's Supporting system at P36.pdf |
| 4/5/2019 | 1592 | 1592 SMC4-RP-50 Report for Loading Test of Pier Head's Supporting System at P29.pdf |
| 4/5/2019 | 1593 | 1593 SMC4-MA-314A Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile P57, P58, P59, P60 (1st).pdf |
| 4/5/2019 | 1594 | 1594 SMC4-MA-316 Report on Frequency Test of Epoxy Coated PC Trand (4th) of Zhemao LTD for Pier Head.pdf |
| 4/5/2019 | 1595 | 1595 SMC4-MS-177 Outline for Loading Test ofPier Head's Supporting System from P23-P26.pdf |
| 4/5/2019 | 1596 | 1596 SMC4-MS-178 MS of Pier Column from P38-P40.pdf |
| 4/5/2019 | 1597 | 1597 SMC4-MS-179 MS of Pier Column from P14-P16.pdf |
| 4/5/2019 | 1598 | 1598 SMC4-LC-495 Report on Actual Condition of Cracks on Pier Head P33.pdf |
| 4/5/2019 | 1599 | 1599 SMC4-LC-496 Additional Documents for 2 Cranes Mobilization for Substructure Work at P28-P31 under Scope of Co.414 (2nd).pdf |
| 4/5/2019 | 1600 | 1600 SMC4-LC-497 Mobilization Document for Additional Manpower & Equipment for Substructure & Superstructure Work under Co.407.pdf |
| 4/5/2019 | 1601 | 1601 SMC4-LC-498 Response to Engineer's Letter Regarding WD for General Layout of Drainage System.pdf |
| 4/5/2019 | 1602 | 1602 SMC4-LP-39 Report on Land Obstructions Relating to Eriction of Super T Girders at the P28-P32 Section Right Side.pdf |
| 4/6/2019 | 1603 | 1603 SMC4--LC-499 Engineer's Confirmation for Safety & Environment Satisfaction ( March- 2019).pdf |
| 4/8/2019 | 1604 | 1604 SMC4-LT-22 Capacity Profile of Laboratory ITST for Quanlity Control of Steel Structures ( Additional Submission).pdf |
| 4/8/2019 | 1605 | 1605 SMC4-WD-237 WD of Column & Pier Head of P38.pdf |
| 4/8/2019 | 1606 | 1606 SMC4-WD-238 WD of Column & Pier Head of P39.pdf |
| 4/8/2019 | 1607 | 1607 SMC4-LC-493A Withdrawal of the Letter SMC4-LT-002119 dated 18Mar2019 & SMC4-LT-002219 dated dated 24Mar2019.pdf |
| 4/8/2019 | 1608 | 1608 SMC4-MA-317 Notice of Not Using Minh Tam Batching Plant for Project.pdf |
| 4/8/2019 | 1609 | 1609 SMC4-LC-500 Submission of Weekly Report No.46.pdf |
| 4/8/2019 | 1610 | 1610 SMC4-MA-318 Notice of Using Viet Tiep Batching Plant for Main site.pdf |
| 4/8/2019 | 1611 | 1611 SMC4-LC-501 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P25.pdf |
| 4/9/2019 | 1612 | 1612 SMC4-MS-181-Proposal for MS of pier column P41-P42.pdf |
| 4/9/2019 | 1613 | 1613 SMC4-MS-180 MS of Temporary Facilities Arrangement on Site from P7-P17.pdf |
| 4/9/2019 | 1614 | 1614 SMC4-LC-502 Report on Environment Monitoring in 4th Phase of 2018 & 1st Phase of 2019 of Thanh Long Steel Structure Plant.pdf |
| 4/9/2019 | 1615 | 1615 SMC4-LC-503 Submission of Contractor's Countermeasures to Improve the Construction of Pier head P29.pdf |
| 4/9/2019 | 1616 | 1616 1091-PMUTL-DHDA1 Approval of Variation Order No. VO-HRR3-PK1-003 Environmental Monitoring.pdf |
| 7/3/2019 | 1617 | 1617 1163-PMUTL-DHDA1Result of Vision Inspection by Package 11- Quality Inspection 2019-04-09 14.13.50.pdf |
| 4/9/2019 | 1618 | 1618 SMC4-RP-52 Report on Transportation of the Test Model of Super T Girder.pdf |
| 4/9/2019 | 1619 | 1619 SMC4-MS-182 Calculation of Tendon Cable Elongation For Pier Head from P28-P29.pdf |
| 4/9/2019 | 1620 | 1620 SMC4-MS-183 MS Plan Drawing of CIP Concrete Pile from P46-P56.pdf |
| 4/9/2019 | 1621 | 1621 SMC4-AD-33 Asbuilt Drawing of CIP Concrete Pile of P15.pdf |
| 4/11/2019 | 1622 | 1622 SMC4-WD-239 WD of Detail of Segments from 6-13 of Steel Girder.pdf |
| 4/24/2019 | 1623 | 1623 SMC4-LC-504 Mobilization Document of Additional Equipment & Manpower for Steel Bridge Subscontractor Thanh Long Group JSC (3rd).pdf |
| 4/11/2019 | 1624 | 1624 SMC4-LC-505 Capacity Profile of VSBCO Vietnam for Verification of Super T Girder.pdf |
| 4/11/2019 | 1625 | 1625 SMC4-MS-184 Outline for Checking Quality of Civil Structure.pdf |
| 4/11/2019 | 1626 | 1626 SMC4-AD-34 Asbuilt Drawings of Substructure - Pile Cap, Pier Colum, Pier Head of P21.pdf |
| 4/11/2019 | 1627 | 1627 SMC4-AD-35 As Built Drawings of Substructure - Pile Cap, Pier Column, Pier Head of P22.pdf |
| 4/11/2019 | 1628 | 1628 SMC4-LP-40 Suggestion for the Re-Check Condition of Crack Super T Girder.pdf |
| 4/11/2019 | 1629 | 1629 PMUTL Meeting Invitation-Treatment of the Blocked Drainage Pipe at the Office of the Ministry of Public Security -10Apr2019.pdf |
| 4/12/2019 | 1630 | 1630 SMC4-AD-36 As Built Drawings of Substructure- Pile Cap, Pier Column & Pier Head P30.pdf |
| 4/12/2019 | 1631 | 1631 SMC4-AD-37 As Built Drawings of Substructure-Pile Cap, Pier Column & Pier Head of P31.pdf |
| 4/12/2019 | 1632 | 1632 SMC4-LC-507 Submission of Schedule for Steel Bridge until 30 June 2019.pdf |
| 4/12/2019 | 1633 | 1633 SMC4-LC-508 Submission of Monthly Report No.11.pdf |
| 4/12/2019 | 1634 | 1634 SMC4-RP-53 Report on Loading Test of Pier Head's Supporting System at P28.pdf |
| 4/12/2019 | 1635 | 1635 SMC4-LC-506 Notice of Contractor's Plan for Trial Transportation & Erection of Super T Girder.pdf |
| 4/12/2019 | 1636 | 1636 SMC4-MA-319 Report on Frequency Test of Posco Steel Plate for Steel Bridge (1st).pdf |
| 4/11/2019 | 1637 | 1637 SMC4-MC-11 Application for Interim Payment Certificate No.09 ( Period 01Mar2019 to 31Mar2019).pdf |
| 4/12/2019 | 1638 | 1638 SMC4-AD-32A As Built Drawings of CIP Concrete Pile for P25.pdf |
| 4/12/2019 | 1639 | 1639 SMC4-MA-320 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of P23, P24 (4th) (1).pdf |
| 5/7/2019 | 1640 | 1640 SMC4-MA-321 Characteristic Strength for Concrete Class A of Asean BP - Report 1 & 2.pdf |
| 4/12/2019 | 1641 | 1641 SMC4-LC-509- 2nd Mobilization Document of Additional Manpower of BOT Vinh City Bypass Branch for Substructure Work.pdf |
| 4/25/2019 | 1642 | 1642 SMC4-LC-510 Report on Concrete Surface's Defects of Pier Column P40 & Countermeasures.pdf |
| 4/13/2019 | 1643 | 1643 SMC4-LC-511 Detailed Particular for Claim 1-Request for Extention of Time for Completion Due to Suspension of the Works(DPRK-USD Summit fr 24Feb-1Mar2019).pdf |
| 4/24/2019 | 1644 | 1644 SMC4-MS-185 MS of Defects Treatment & Finishing Concrete Surface of Super T Girder.pdf |
| 4/17/2019 | 1645 | 1645 SMC4-LC-512 Result fo Ultrasonic Test of CIP Concrete Pile at P26.pdf |
| 4/17/2019 | 1646 | 1646 SMC4-LT-23 Update of Capacity Profile of Laboratory ITST.pdf |
| 4/17/2019 | 1647 | 1647 SMC4-LC-514 Submission of Weekly Report No.47.pdf |
| 4/17/2019 | 1648 | 1648 SMC4-MA-322 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of P25, P26, P27 (2nd).pdf |
| 5/7/2019 | 1649 | 1649 SMC4-MA-324 Characteristic Strength for Concrete Class C of Transmeco BP- Report 1, 2.pdf |
| 5/7/2019 | 1650 | 1650 SMC4-MA-325 Characteristic Strength for Concrete Class A of Viet Tiep BP - Report 1.pdf |
| 4/17/2019 | 1651 | 1651 SMC4-MA-326 Report on Frequency Test of Reinforcing Steel VGS for Pier Cap,Pier Column, Pier Head P32-P35 (11th) & P41-P43 (3rd).pdf |
| 4/17/2019 | 1652 | 1652 SMC4-MA-327 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column & Pier Head of P15.pdf |
| 4/17/2019 | 1653 | 1653 SMC4-MA-328 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile at P55, P56.pdf |
| 4/16/2019 | 1654 | 1654 SMC4-LC-513 Claim for an Extension of Time or an Additional Payment for the Suspension of Works.pdf |
| 4/17/2019 | 1655 | 1655 SMC4-WD-240 WD of Super T Girder Span 42 (P41-P42).pdf |
| 4/17/2019 | 1656 | 1656 SMC4-MA-329 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P46, P47.pdf |
| 4/17/2019 | 1657 | 1657 SMC4-MA-330 Report on Frequency Test of Reinforcing Steel VGS for Pier Head P28(3rd) & Diaphragm of Pier P28-P31.pdf |
| 4/17/2019 | 1658 | 1658 SMC4-LC-515 Report on Environment Monitoring in Construction Stage (1st Phase in Apr 2019, Parameter TSP).pdf |
| 5/13/2019 | 1659 | 1659 SMC4-LC-516 Replacement of Foundation-Pilling Engineer- Hồ Đức Phúc.pdf |
| 4/18/2019 | 1660 | 1660 SMC4-LC-517 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P15.pdf |
| 4/19/2019 | 1661 | 1661 SMC4-LC-518 Additional Supervision Cost of Engineer'Staff (Jan, Feb 2019).pdf |
| 4/19/2019 | 1662 | 1662 SMC4-LC-519 Report on Condition of Concrete Surface on Pier Head P29.pdf |
| 4/19/2019 | 1663 | 1663 SMC4-WD-241 WD of Substructure - Pier P59.pdf |
| 4/19/2019 | 1664 | 1664 SMC4-RP-54 Report on Trial Transportation & Erection of Super T Girder.pdf |
| 4/19/2019 | 1665 | 1665 SMC4-MS-186 MS for Lower Part of Pier Head from P14-P16.pdf |
| 5/7/2019 | 1666 | 1666 SMC4-MA-331 Update for TOR for Quality Control of Concrete.pdf |
| 4/20/2019 | 1667 | 1667 SMC4-LC-520 Financial Charges Upon Unpaid Sums.pdf |
| 4/20/2019 | 1668 | 1668 SMC4-MA-332 Test Result of Painting Material & Frequency Test of Primer Coating Paint for Steel Bridge- Hai Phong Paint JSC & Primer Coat Paint at the Factory.pdf |
| 4/20/2019 | 1669 | 1669 SMC4-MS-187 Supplement Method Drawing for Erection of Super T Girder at Span S22( P21-P22) & Permit from Directorate of VN.pdf |
| 4/22/2019 | 1670 | 1670 SMC4-WD-242 WD of Adjustment for Exterior Girder Span 41 (P40-P41).pdf |
| 4/22/2019 | 1671 | 1671 SMC4-WD-243 WD of Super T Girder Span 43( P42-P43).pdf |
| 4/22/2019 | 1672 | 1672 SMC4-MA-333 Report on Frequency Test of Reinforcing Steel-VGS for Pile Cap,Pier Column, Pier Head P32-P35 (12th) & P41-P43 (4th).pdf |
| 4/22/2019 | 1673 | 1673 SMC4-MA-335 Report on Test Result of Stainless Steel - Viet Thang Co.LTD.pdf |
| 4/22/2019 | 1674 | 1674 SMC4-MA-334 Report on Frequency Test of sReinforcing Steel for Pile Cap, Pier Column & Pier Head of P36 (7th).pdf |
| 4/22/2019 | 1675 | 1675 1279 BQLDATL-DA1 Design change of pavement structure for reinstatement of pavement at pier locations.pdf |
| 4/22/2019 | 1676 | 1676 SMC4-RP-42A Report for Loading Test of Pier Head's Supporting System P30.pdf |
| 4/24/2019 | 1677 | 1677 SMC4-RP-55 Report to Monitoring Type 1, 2 Crack of SuperT Girder.pdf |
| 4/25/2019 | 1678 | 1678 SMC4-RP-56 Report on Checking the Periodic Benchmark System (2nd).pdf |
| 4/24/2019 | 1679 | 1679 SMC4-MA-336 Report on Frequency Test of Reinforcing Steel of VGS for Super T Girder (6th) of Team 2 (Co.407).pdf |
| 4/24/2019 | 1680 | 1680 SMC4-WD-244 WD for Basement for Traffic Sign Board at P39.pdf |
| 4/24/2019 | 1681 | 1681 SMC4-WD-245 WD for Basement for Traffic Sign Board at P42.pdf |
| 4/24/2019 | 1682 | 1682 SMC4-WD-246 WD for Basement for Traffic Sign Board at P41.pdf |
| 4/24/2019 | 1683 | 1683 SMC4-WD-247 WD of Substructure - P60.pdf |
| 4/24/2019 | 1684 | 1684 SMC4-MA-338 Capacity Profile of Manufacturer & Supplier of Non Shrinkage Grout Victa VG60- Center of TDBM under IBST.pdf |
| 4/24/2019 | 1685 | 1685 SMC4-MA-337 Update & Supplement of Capacity Profile of ASEAN BP.pdf |
| 4/24/2019 | 1686 | 1686 SMC4-LC-521 Reply to the Engineer's Letter on Notice of Claim due to Delayed Approval Instruction for WD of A1-P10 Section.pdf |
| 4/25/2019 | 1687 | 1687 SMC4-LC-514A Extension of Registration for 2 Trailers & Insurance for crane 160T to Serve Transportation & Eriction Work of Super T Girders.pdf |
| 4/24/2019 | 1688 | 1688 SMC4-LC-522 Submission of Weekly Report No.48.pdf |
| 5/21/2019 | 1689 | 1689 SMC4-LC-523 Additional Mobilization of Tractors, Crane to Serve Transport & Eriction Work of Super T Girder (2nd).pdf |
| 4/24/2019 | 1690 | 1690 SMC4-RP-57 Report on Loading Test of Pier Head's Supporting System at P23.pdf |
| 4/24/2019 | 1691 | 1691 SMC4-MS-188 Supplement the Method Drawing of Pier Head at P23.pdf |
| 4/24/2019 | 1692 | 1692 SMC4-MS-189 Traffic Control Plan for Public Road for Construction of Steel Bridge at P16-P19.pdf |
| 4/24/2019 | 1693 | 1693 SMC4-LT-24 Update & Supplement the Document of Personnel, Equipment of Lab XD 668.pdf |
| 4/24/2019 | 1694 | 1694 SMC4-AD-33A As Built Drawing of Substructure - Backfill P21, P22, P30 & P31.pdf |
| 4/24/2019 | 1695 | 1695 SMC4-AD-38-As Built Drawing of Pre Tensioning Pre Tressed Super T Girder Span 20 (P19-P20).pdf |
| 4/24/2019 | 1696 | 1696 SMC4-AD-39 As Built Drawing of CIP Concrete Pile D1.2m of P26.pdf |
| 4/24/2019 | 1697 | 1697 SMC4-WD-248 WD of Painting of Exterior Super T Girder from Span 10-16 & 20-38 (2nd).pdf |
| 4/24/2019 | 1698 | 1698 SMC4-WD-249-WD General View of Main Bridge & HQV-B Ramp (7th).pdf |
| 4/25/2019 | 1699 | 1699 SMC4-AD-40 As Built Drawings of Substructure- Pile Cap, Pier Column & Pier Head of P19.pdf |
| 4/25/2019 | 1700 | 1700 SMC4-AD-41 As Built Drawings of CIP Concrete Piliing D1.2m of P42L.pdf |
| 4/25/2019 | 1701 | 1701 SMC4-LC-524 Notice on Contractor's Working Schedule during Nation Reunification & International Labor Day on 30 Apr & 1 May 2019.pdf |
| 4/25/2019 | 1702 | 1702 SMC4-WD-250 WD of Substructure- P56.pdf |
| 4/25/2019 | 1703 | 1703 SMC4-WD-251 WD of Substructure- P55.pdf |
| 4/25/2019 | 1704 | 1704 SMC4-WD-252 WD of Substructure- P47.pdf |
| 4/26/2019 | 1705 | 1705 SMC4-LC-525 Method to Improve the Construction of Pier Column.pdf |
| 4/26/2019 | 1706 | 1706 SMC4-LC-526 Notice of Equipment Demobilization - Excavator Hitachi ZX under Scope of 422 Co..pdf |
| 4/27/2019 | 1707 | 1707 SMC4-LC-527 Proposal for top Elevation of Bearing Pad in Accordance with Actual Camber of SPT Girder at Span S29, S30.pdf |
| 4/27/2019 | 1708 | 1708 SMC4-MA-339 Capacity Profile of Manufacturer Waterproofing Material HASEAL 5 - Ha An JSC.pdf |
| 4/27/2019 | 1709 | 1709 SMC4-LC-529 Notice of Environmental Monitoring Schedule in May 2019 at Construction Phase.pdf |
| 4/27/2019 | 1710 | 1710 SMC4-LC-528 Report on Environment Monitoring (2nd Phase in Apr 2019).pdf |
| 4/27/2019 | 1711 | 1711 SMC4-LP-43 Resolving Some Obstacles of Traffic Signal & Camera Systems.pdf |
| 4/27/2019 | 1712 | 1712 SMC4-LC-530 Submission of Weekly Report No.49.pdf |
| 4/27/2019 | 1713 | 1713 SMC4-MA-340 Report on Frequency Test of Reinforcing Steel for SuperT Girder (5th, 6th) of Team 4 (Co.422).pdf |
| 4/27/2019 | 1714 | 1714 SMC4-MS-191 Method Statement of Pier Column From P41-P42 (Rev.02).pdf |
| 4/27/2019 | 1715 | 1715 SMC4-MS-190 Method Statement for Lower Part of Pier Head from P38-P40.pdf |
| 5/27/2019 | 1716 | 1716 SMC4-WD-253 Calculation Sheet & Working Drawing of Deck Slab of Steel Bridge (Including Kawada Certification & S11.02 (1)(a) & S11.08 (1)(c) of JBA (2nd ).pdf |
| 5/3/2019 | 1717 | 1717 SMC4-AD-42 AD of Substructure - Pile Cap, Pier Column & Pier Head of Pier P20.pdf |
| 5/3/2019 | 1718 | 1718 SMC4-LC-531 Substructure Acceptance & Transfer to Superstructure P30.pdf |
| 5/3/2019 | 1719 | 1719 SMC4-LC-533 Pile Foundation Acceptance & Transfer to Substructure P26.pdf |
| 5/3/2019 | 1720 | 1720 SMC4-LC-532 Substructure Acceptance & Transfer to Superstructure P31.pdf |
| 5/3/2019 | 1721 | 1721 SMC4-LC-534 Acceptance of Pile Foundation Stage & Transfer to Substructure P42L.pdf |
| 5/4/2019 | 1722 | 1722 SMC4-LC-535 Report on Status of Connection Drainage System between 2 Project.pdf |
| 5/4/2019 | 1723 | 1723 SMC4-LC-514B Report on Concrete Surface's Defect of Pier Column P16.pdf |
| 5/3/2019 | 1724 | 1724 1432-TB-BQLDA Notice on Conclusion Given in the Meeting on Determination of Exchange Rate & Time for Insuance of VAT Invoice for HCRR3 Construction Project.pdf |
| 5/6/2019 | 1725 | 1725 SMC4-LC-536 Confirmation of Safety & Environment Satisfaction (1-30 Apr 2019).pdf |
| 5/6/2019 | 1726 | 1726 SMC4-MA-341 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of P25, P26 (3rd).pdf |
| 5/6/2019 | 1727 | 1727 SMC4-MA-342 Characteristic Strength of Concrete Class G of Asean BP- Report No.1.pdf |
| 5/6/2019 | 1728 | 1728 SMC4-MS-193 MS for Treatment Form Work at the End of Super T Girder.pdf |
| 5/6/2019 | 1729 | 1729 SMC4-WD- 254 WD for Basement for Traffic Sign Board at P16 (2nd).pdf |
| 5/6/2019 | 1730 | 1730 SMC4-WD-255 WD of Super T Girder Span 39 (P38-P39).pdf |
| 5/6/2019 | 1731 | 1731 SMC4-LC-537 Submission of Weekly Report No.50.pdf |
| 5/6/2019 | 1732 | 1732 SMC4-MS-192 Supplement of Method Drawing for Construction of Pier Head at P27.pdf |
| 5/6/2019 | 1733 | 1733 SMC4-MS-194 Outline for Loading Test of Pier Head Supporting System at P27.pdf |
| 5/7/2019 | 1734 | 1734 SMC4-WD-257 WD of Superstructure - Steel bridge - Detail of Segment 7& 15 - Rigid Pier Head (1st Revision).pdf |
| 5/22/2019 | 1735 | 1735 SMC4-MA-343 Characteristic Strength for Concrete Class Y of ASEAN BP - No.4.pdf |
| 5/7/2019 | 1736 | 1736 SMC4-LC-538 Report on Environment Monitoring in Construction Stage (3rd Phase in Apr 2019, Parameters TSP).pdf |
| 5/7/2019 | 1737 | 1737 SMC4-WD-256 Drawing & Calculation Sheet of Pot Bearing (2nd).pdf |
| 5/7/2019 | 1738 | 1738 SMC4-AD-43 As Built Drawing of CIP Concrete Piling D1.2m of P41L.pdf |
| 5/7/2019 | 1739 | 1739 SMC4-MS-195 Remedial Method for Concrete Surface's Defects for Pier Column P16.pdf |
| 5/7/2019 | 1740 | 1740 SMC4-AD-44 As Built Drawings of Substructure- Pile Cap, Pier Column & Pier Head of P34.pdf |
| 5/7/2019 | 1741 | 1741 SMC4-AD-45 As Built Drawings of Substructure- Pile Cap, Pier Column & Pier Head of P33.pdf |
| 5/7/2019 | 1742 | 1742 SMC4-WD-258 WD of Detail of Segmetns 17-21 of Steel Girder.pdf |
| 5/9/2019 | 1743 | 1743 SMC4-AD-46 As Built Drawings of Pre Tesioning Pre Stressed SuperT Girder Span 21.pdf |
| 5/24/2019 | 1744 | 1744 SMC4-MS-196 MS for Transportation of Steel Girder.pdf |
| 5/9/2019 | 1745 | 1745 SMC4-MA-344 Test Result of Membrane on Pier Head for Friction Cut Material -Lemax 4mm PE-APP.pdf |
| 5/10/2019 | 1746 | 1746 SMC4-LC-539 Reply to the Comment on 2nd Mobilization Document for Additional Manpower of BOT Vinh City bypass Branch for Substructure Works.pdf |
| 5/10/2019 | 1747 | 1747 SMC4-LC-540 Proposal for Transferring the Drilling Crane Kobeco 7055 Working ả P38-P40 (423 Co.) to P52-P56 (422 Co) equipment.pdf |
| 5/10/2019 | 1748 | 1748 SMC4-WD-259 WD of Detail of Segment 6,8,14,16 of Steel Girder (2nd).pdf |
| 5/10/2019 | 1749 | 1749 SMC4-WD-260 WD of Substructure P57.pdf |
| 5/10/2019 | 1750 | 1750 SMC4-WD-261 WD of Substructure P58.pdf |
| 5/10/2019 | 1751 | 1751 SMC4-MS-197 MS of Remove Scaffolding System & Formwork System of Pier Head.pdf |
| 5/10/2019 | 1752 | 1752 SMC4-MS-198 Remedial Method for Concrete Surface's Defects for Pier Column P40.pdf |
| 5/10/2019 | 1753 | 1753 SMC4-MA-340A Report on Frequency Test of Posco Steel Plate for Steel Bridge (2nd).pdf |
| 6/12/2019 | 1754 | 1754 SMC4-MS-199 Countermeasure & Repairing Method for Crack on Pier Head.pdf |
| 5/10/2019 | 1755 | 1755 SMC4-MA-344A TOR for Frequency Test of Materials for Steel Bridge.pdf |
| 5/10/2019 | 1756 | 1756 SMC4-MA-346 Characteristic Strength of Concrete Class Y of Transmeco BP - Report No.1 & 2.pdf |
| 5/10/2019 | 1757 | 1757 SMC4-MA-347 Report on Test Result of Paint Material for Steel Bridge of Hai Phong Paint JSC(2nd).pdf |
| 5/10/2019 | 1758 | 1758 SMC4-LC-541 Submission of Weekly Report No.51.pdf |
| 5/13/2019 | 1759 | 1759 SMC4-WD-262 WD of Detail of Segments 9 to 13 of Steel Girder (2nd).pdf |
| 5/14/2019 | 1760 | 1760 SMC4-LC-542 Report on Environment Monitoring in Construction Stage (1st Phase in May 2019, Parameters TSP).pdf |
| 5/30/2019 | 1761 | 1761 SMC4-MA-347A Capacity Profile of Manufacturer & Suppler for Bolts for Boilts for Steel Bridge-Oriens Metal Co.Ltd & DongAh Co.LTD- Tan Co JSC.pdf |
| 5/14/2019 | 1762 | 1762 SMC4-MA-347B Report on Frequency Test of Reinforcing Steel for Super T Girder (4th) of 414 Team 1.pdf |
| 5/14/2019 | 1763 | 1763 SMC4-MA-347C Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head of P41-P43 (5th).pdf |
| 5/14/2019 | 1764 | 1764 SMC4-MA-348 Characteristic Strength for Concrete Class C of ASEAN BP- Report No.1 from 30Sep-11Dec2018.pdf |
| 5/14/2019 | 1765 | 1765 SMC4-MA-349 Characteristic Strength for Concrete Class A of Viet Tiep BP - Report No.2 form 25Feb -02Apr2019.pdf |
| 5/14/2019 | 1766 | 1766 SMC4-MA-350 Supplier 412 JSC for Steel Plate for Grading & Stainless Steel of Viet Thang Co. LTD.pdf |
| 5/14/2019 | 1767 | 1767 SMC4-MS-200 Supplement Method Drawing for Erection of Super T Girder at S31(P30-P31).pdf |
| 5/14/2019 | 1768 | 1768 SMC4-MS-201 Supplement Drawing for Method Statement of Pier Column from P14-P15.pdf |
| 5/14/2019 | 1769 | 1769 SMC4-MS-202 Supplement Drawing for Method Statement of Pier Column P38-P39.pdf |
| 5/14/2019 | 1770 | 1770 SMC4-MA-348A Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column of P15, P16 (2nd).pdf |
| 5/14/2019 | 1771 | 1771 SMC4-MA-348B Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P57-P60 (2nd).pdf |
| 5/14/2019 | 1772 | 1772 SMC4-LC-543 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work P41L.pdf |
| 5/16/2019 | 1773 | 1773 1560-PMUTL-DA1 Reinstatement of Drainage System for Office of Ministry of Public Security.pdf |
| 5/15/2019 | 1774 | 1774 1491-BQLDATL-DA1 Approval of Nominated Subcontractor for Protection & Relocation of Existing Utilities of PK1.pdf |
| 5/16/2019 | 1775 | 1775 SMC4-LC-544 Monthly Report No.12.pdf |
| 5/15/2019 | 1776 | 1776 SMC4-AD-47 As Built Drawings of Substructure- Pile Cap, Pier Column & Pier Head of P29.pdf |
| 5/16/2019 | 1777 | 1777 SMC4-MC-12 Interim Payment Certificate No. 10 ( Period 1Apr-30Apr2019).pdf |
| 5/17/2019 | 1778 | 1778 SMC4-LC-545 Result of Ultrasonic Test of CIP Concrete Piles at P38.pdf |
| 5/17/2019 | 1779 | 1779 SMC4-LC-541A Updated Quality Control Plan.pdf |
| 5/17/2019 | 1780 | 1780 SMC4-MS-203 MS of Traffic Control for Public Road at Section P38-P43-Volumn VI.4 Arranging TC after Extending Site Fence at P38-P41 Right Side.pdf |
| 5/17/2019 | 1781 | 1781 SMC4-LC-546 Construction Work of the Subcontractor - Co.423.pdf |
| 5/17/2019 | 1782 | 1782 SMC4-LC-547 Report on Defect Treatment (Crack Type 1& 2) & Finishing Surface Concrete of Super TGirder.pdf |
| 5/17/2019 | 1783 | 1783 SMC4-LC-548 Request for Equipment Remobilization- Excavator Hitachi ZX of Co.422 to P52-P56 for Bored Pile Drilling Work & Demobilization of Excavator Kolbeco SK200-8.pdf |
| 5/17/2019 | 1784 | 1784 SMC4-LC-549 Mobilization Documents for Manpower & Machinery for Backlling Work under Scope of 422.pdf |
| 5/17/2019 | 1785 | 1785 SMC4-WD-263 WD of Deck Slab & Link Slab Span S21, 22& 30, 31 (2nd).pdf |
| 5/17/2019 | 1786 | 1786 SMC4-MS-204 Method Drawing for Erection of Super T Girder at Span S20 (P19-P20) & S21( P20-P21).pdf |
| 5/17/2019 | 1787 | 1787 SMC4-AD-48 Asbuilt Drawings of Pre Tensioning Pre Stressed Super T Girder Span 30( P29-P30).pdf |
| 5/18/2019 | 1788 | 1788 1622-BQLDATL-DA1 Approval for Replacement of Key Personnel ( Quality Control Manager).pdf |
| 5/18/2019 | 1789 | 1789 SMC4-MA-351 Report on Fequency Test of Cement, Coarse Aggregate, for Class A, fine Aggregate, Admixture & Water for Cement Concrete at Viet Tiep BP (5th - 6th).pdf |
| 5/18/2019 | 1790 | 1790 SMC4-RP-58 Supplement of Permit from Directorate for Road of VietNam.pdf |
| 5/18/2019 | 1791 | 1791 SMC4-MC-13 Resubmit for Interim Payment Certificate No.10 ( Period 1Apr-30Apr2019).pdf |
| 5/18/2019 | 1792 | 1792 SMC4-LC-550 Report of Surface Repairing Work on Pier Head P20.pdf |
| 5/18/2019 | 1793 | 1793 SMC4-LC-551 Report on Reparation Work for Pier Column P40 Concrete Surface.pdf |
| 5/18/2019 | 1794 | 1794 SMC4-LC-552 Report of Reparation Work for Pier Column P16 Concrete Surface.pdf |
| 5/20/2019 | 1795 | 1795 SMC4-LC-553 Acceptance of Sub Structure Construction Stage & Tranfer to Construction of Superstructure Work for P20.pdf |
| 5/20/2019 | 1796 | 1796 SMC4-MA-352 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of Pile P57-P60 (3rd).pdf |
| 5/20/2019 | 1797 | 1797 SMC4-MA-353 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of P38(4th)-P40 (3rd).pdf |
| 5/20/2019 | 1798 | 1798 SMC4-MS-205 MS of Fence Arrangement on Site from P38-P42.pdf |
| 5/24/2019 | 1799 | 1799 SMC4-MS-206 Traffic Control Plan for Public Road Construction of Steel Bridge at P16-P19 (2nd).pdf |
| 5/22/2019 | 1800 | 1800 1628-PMUTL-DHDA1 Review & Check Quality of Super T Girders at PK1 Fabrication Yard-Remedy of Defects during Construction of Super T Girder.pdf |
| 5/20/2019 | 1801 | 1801 1634 PMUTL-DHDA1 Design Modification of Pavement Structure for Backfill at Locations of Piers-Abutments.pdf |
| 5/31/2019 | 1802 | 1802 SMC4-SC-20 Capacity Profile of Subcontractor PHATECO JSC.pdf |
| 5/21/2019 | 1803 | 1803 SMC4-LC-554 Weekly Report No.52.pdf |
| 5/21/2019 | 1804 | 1804 SMC4-MS-207 MS for Remedy Defects of Super T Girder.pdf |
| 5/21/2019 | 1805 | 1805 SMC4-RP-59 Report on Loading Test of Pier Head's Supporting System at P27.pdf |
| 5/22/2019 | 1806 | 1806 SMC4-MS-208 MS for Confirmation of Concrete Quality for CIP Concrete Piling -Pile C2P38.pdf |
| 5/23/2019 | 1807 | 1807 SMC4-LC-555 Notice of Working Content on Dust Matter at Thanh Long Steel Bridge Fabrication Factory.pdf |
| 5/23/2019 | 1808 | 1808 SMC4-LC-556 Withdrawal of Letter SMC4- LC-505.19 &SMC4- MS-0184.19 dated 10Apr2019.pdf |
| 5/23/2019 | 1809 | 1809 SMC4-MA-354 Capacity Profile of Manufacturer & Supplier for Stud Shear Connector of Steel Bridge- Samjin Co.LTD- Tan Co JSC.pdf |
| 5/23/2019 | 1810 | 1810 SMC4-MS-209 Report on Storage of Steel Plate & Shape Steel at Fabrication Yard.pdf |
| 5/23/2019 | 1811 | 1811 SMC4-WD-264 WD of Super T Girder Span 40 (P39-P40).pdf |
| 5/23/2019 | 1812 | 1812 SMC4-MA-345 Report on Frequency Test of Cement, Coarse Aggregate Fine Aggregate & Water for Cement Concrete at Transmeco BP ( 16th to 20th).pdf |
| 5/23/2019 | 1813 | 1813 SMC4-WD-265 WD of Substructure - Pier P54.pdf |
| 5/23/2019 | 1814 | 1814 SMC4-WD-266 WD of Substructure - Pile Cap P14.pdf |
| 5/23/2019 | 1815 | 1815 SMC4-WD-267 WD of Substructure - Pile Cap P13.pdf |
| 5/23/2019 | 1816 | 1816 SMC4-WD-268 WD of Substructure - Pile Cap P12.pdf |
| 5/23/2019 | 1817 | 1817 SMC4-WD-269 WD of Substructure - Pile Cap P11.pdf |
| 5/23/2019 | 1818 | 1818 SMC4-WD-270 WD of Substructure - Pier P53.pdf |
| 5/30/2019 | 1819 | 1819 SMC4-LC-557 Report on Environment Monitoring in Construction Stage (2nd in May 2019).pdf |
| 5/23/2019 | 1820 | 1820 SMC4-LC-558 Replacement of Some Pre Tensioning Pre Stressed Super T Girders of the Same Type Span S30 by S24 during Erection.pdf |
| 5/23/2019 | 1821 | 1821 SMC4-LC-559 Document of Additional Bored Pile for Pier P43C.pdf |
| 5/24/2019 | 1822 | 1822 SMC4-LC-560 Report on the Problem with the Anchor bar of girder G6-S21.pdf |
| 5/24/2019 | 1823 | 1823 SMC4-WD-271 WD of Super T girder Spans S51-S52 and Spans S54-S61.pdf |
| 5/24/2019 | 1824 | 1824 SMC4-WD-272 WD of Detail of Detail of Segments 1 to 5 of Steel Girder.pdf |
| 5/24/2019 | 1825 | 1825 SMC4-LC-563 Sub of Result of Ultrasonic test of cast-in-place concrete Piles at P39.pdf |
| 5/24/2019 | 1826 | 1826 SMC4-LC-562 Result of Ultrasonic Test of Cast-in-place Piles at P38-Pile 10.pdf |
| 5/24/2019 | 1827 | 1827 SMC4-MA-355 Report on Frequency test of Epoxy Coated PC Strand (5th Time) of Zhemao Science and Technology used Pier Head.pdf |
| 5/24/2019 | 1828 | 1828 SMC4-LC-561 Additional Supervision Cost of Engineer's Staf(March 2019).pdf |
| 6/17/2019 | 1829 | 1829 SMC4-LC-564 Organization Chart and List of Key Personnel.pdf |
| 5/25/2019 | 1830 | 1830 SMC4-MA-356 Approval of capacity Profile of Manufacture and Supplier of dowe D32,D60 Hai Anh.pdf |
| 5/25/2019 | 1831 | 1831 SMC4-MS-210 Document of Protection and Relocation Existing Utilities at section P41-P43 Right side and Pier P53.pdf |
| 5/27/2019 | 1832 | 1832 SMC4-LC-0565 Proposal for Approval of the Contractor's Programme(Rev.2).pdf |
| 5/25/2019 | 1833 | 1833 SMC4-MA-357 Update and Supplement of capacity profile of Batching plant Viet Tiep.pdf |
| 5/27/2019 | 1834 | 1834 SMC4-LC-566 Submission of Information of Subcontrectors Engaged on the Project.pdf |
| 5/28/2019 | 1835 | 1835 SMC4-LC-567 Report on Damaged Underground Electric Cable during the Construction of Pile No. C5P53.pdf |
| 5/27/2019 | 1836 | 1836 1669-BQLDATL-DA1 Invitation- Site Inspection in order to Argree on the Construction site area following the Alterniative of Traffic land Distribution & Traffic Control.pdf |
| 5/28/2019 | 1837 | 1837 BGTVT-CQLXD&CLCTGT Invitation to Site Inspection Date 29.5.2019.pdf |
| 5/28/2019 | 1838 | 1838 SMC4-WD-273 WD of Detail of Segments 17 to 21 of Steel Girder (2nd).pdf |
| 5/28/2019 | 1839 | 1839 SMC4-MA-358 Characteristic Strength for Concrete Class Y of Transmeco BP- Report 1 , 2.pdf |
| 5/28/2019 | 1840 | 1840 SMC4-MS-211 Calculation of Tendon Cable Elongation for Pier Head P27.pdf |
| 5/28/2019 | 1841 | 1841 SMC4-MS-212 Calculation of Tendon Cable Elongation for Pier Head P23.pdf |
| 5/28/2019 | 1842 | 1842 SMC4-LC-568 Weekly Report No.53.pdf |
| 5/28/2019 | 1843 | 1843 SMC4-LC-569 Report of Surface Repairing Work on Pier Head P19.pdf |
| 5/30/2019 | 1844 | 1844 SMC4-LC-570 Notice of Claim on Unforeseeable Physical Conditions Found by the Contractor during Construction of CIP Pile for P53.pdf |
| 5/30/2019 | 1845 | 1845 SMC4-LC-571 Result of Ultrasonic Test of CIP Concrete Piles at P59.pdf |
| 5/30/2019 | 1846 | 1846 SMC4-LC-572 Result of Ultrasonic Test of CIP Concrete Pile at P60.pdf |
| 5/30/2019 | 1847 | 1847 SMC4-LC-573 Withdrawal of the Letter LC-0566 dated 27 may 19.pdf |
| 5/30/2019 | 1848 | 1848 SMC4-WD-274 WD of Substructure P51.pdf |
| 5/30/2019 | 1849 | 1849 SMC4-WD-275 WD of Substructure P52.pdf |
| 5/30/2019 | 1850 | 1850 SMC4-WD-276 WD of Super T Girder Span S53.pdf |
| 5/30/2019 | 1851 | 1851 SMC4-AD-49 As Built Drawings of Pre Tensioning Pre Stressed Super T Girder Span 29 (P28-P29).pdf |
| 5/30/2019 | 1852 | 1852 SMC4-MS-213 Outline for Loading Test of Pier Heads Supporting System at P16.pdf |
| 5/30/2019 | 1853 | 1853 SMC4-MS-214 MS of Structure Excavation from P57-P60.pdf |
| 5/29/2019 | 1854 | 1854 SMC4-MA-359 Trial Mixing Work of Concrete Proportions Class A,B1,B2,C1,C3,C4,D,E,G &Y at Viet Tiep BP after Moving to New Location.pdf |
| 5/29/2019 | 1855 | 1855 SMC4-MA-360 Trial mixing Work of Concrete Proportions Class A, B1,C1,C3,C4, D,E,G & Y at ASEAN BP after Moving to New Location.pdf |
| 5/30/2019 | 1856 | 1856 SMC4-MA-361 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P48, P49.pdf |
| 5/30/2019 | 1857 | 1857 SMC4-MA-362 Report on Frequency Test of Reinforcing Steel for Pile Cap & Pier Column& Pier Head of P24(5th)-P25,P26(4th).pdf |
| 6/17/2019 | 1858 | 1858 SMC4-MS-215 Document of Relocation Existing Utilities at P60.pdf |
| 5/28/2019 | 1859 | 1859 1756-PMUTL-DA1 & TCQM Invitation to Site Inspection.pdf |
| 5/30/2019 | 1860 | 1860 SMC4-LC-574 Acceptance of Sub Structure Construction Stage & Tranfer to Construction of Superstructure Work for P19.pdf |
| 5/30/2019 | 1861 | 1861 SMC4-LC-575 Notice of Environmental Monitoring Schedule in June 2019 at Construction Phase.pdf |
| 5/30/2019 | 1862 | 1862 SMC4-LC-576 Report of Surface Repairing Work on Pier Head P29.pdf |
| 5/30/2019 | 1863 | 1863 SMC4-WD-277 WD of Basement for ITS Sign Board at P25 and P52.pdf |
| 5/30/2019 | 1864 | 1864 SMC4-WD-278 WD of General Arrangement of Foundation of ITS System for Expressway.pdf |
| 5/30/2019 | 1865 | 1865 SMC4-WD-279 WD of Deck Slab Spans 34, 35 & Link Slab at P33,P34,P35.pdf |
| 5/30/2019 | 1866 | 1866 SMC4-MS-216 Reconnect Culvert Pipe D1250 of Ministry of Public Plan (2nd).pdf |
| 5/31/2019 | 1867 | 1867 SMC4-LC-577 Withdrawal of the Letter SMC4-MA-0359 & 0360 dated 28May2019.pdf |
| 5/31/2019 | 1868 | 1868 SMC4-MA-365 Trial Mixing Working of Concrete Proporttions Class A,B1,B2,C1,C3,C4,D,E,G& Y at the VIET TIEP BP after Moving tho New Location.pdf |
| 5/31/2019 | 1869 | 1869 SMC4-MA-366 Trial Mixing Working of Concrete Proportions Class A,B1,C1,C3,C4,D,E,G & Y at the ASEAN BP after Moving to New Location.pdf |
| 5/31/2019 | 1870 | 1870 SMC4-LC-578 Additional Mobilization Document for Cranes & Trailers to Serve Transportation & Erection Work of Super T Girders (3rd).pdf |
| 5/31/2019 | 1871 | 1871 SMC4-LC-579 Report on Status of Connection Drainage Sytem between 2 Project (2nd).pdf |
| 6/19/2019 | 1872 | 1872 SMC4-LC-580 Contractor's Improvement Plan for Super T Girder's Production- Erection Works.pdf |
| 5/31/2019 | 1873 | 1873 SMC4-MA-367 Use Galvanized Dowel D32,D60 Manufactured by Hai Anh Co.Ltd.pdf |
| 5/31/2019 | 1874 | 1874 SMC4-MA-364 Report on Test Result of Welding Material for Steel Bridge.pdf |
| 5/31/2019 | 1875 | 1875 SMC4-MA-363 Test Result of Welding Procedure for Steel Bridge.pdf |
| 5/31/2019 | 1876 | 1876 SMC4-WD-280 WD of Super T Girder Span S46-S47.pdf |
| 5/31/2019 | 1877 | 1877 SMC4-WD-281 WD of Super T Girders Span S48-S49.pdf |
| 6/4/2019 | 1878 | 1878 SMC4-LC- 581 Submission of Video CS No.2 (6months Period from Nov2018 to Apr2019).pdf |
| 6/4/2019 | 1879 | 1879 SMC4-RP-60 Report of Excavation for Survey of Underground Utilities at P47.pdf |
| 6/4/2019 | 1880 | 1880 SMC4-RP-61 Report of Excavation for Survey of Underground Utilities at P48.pdf |
| 6/4/2019 | 1881 | 1881 SMC4-RP-62 Report of Excavation for Survey of Underground Utilities at P49.pdf |
| 6/4/2019 | 1882 | 1882 SMC4-RP-63 Report of Excavation for Survey of Underground Utilities at P52.pdf |
| 6/4/2019 | 1883 | 1883 SMC4-RP-64 Report on Excavation for Survey of Underground Utilities at P54.pdf |
| 6/4/2019 | 1884 | 1884 SMC4-RP-65 Report of Excavation for Survey of Underground Utiliites at P57.pdf |
| 6/4/2019 | 1885 | 1885 SMC4-RP-66 Report of Excavation for Survey of Underground Utilities at P58.pdf |
| 6/4/2019 | 1886 | 1886 SMC4-RP-67 Report of Excavation for Survey of Underground Utilities at P59.pdf |
| 6/18/2019 | 1887 | 1887 SMC4-LC-584 Submission of Schedule for Steel Bridge.pdf |
| 6/4/2019 | 1888 | 1888 SMC4-MS-217 MS of Traffic Control for Public Road at P38-P60 - Vol-VII.3-Arranging TC after Extending Site Fence at P46-P50 Right Side.pdf |
| 6/4/2019 | 1889 | 1889 SMC4-LC-585 Report on Condition of Concrete Surface on Pier Head P23.pdf |
| 6/13/2019 | 1890 | 1890 1834 QD BQLDATL Approval Decision for Cost Estimates of Cast-in-place concrete piles for Piers from P9-P15,P45-P58 to P108.pdf |
| 6/4/2019 | 1891 | 1891 SMC4-MA-368 Proposal to Use Concrete Painting Material for Concrete by Klaas Coating LTD & Supplied Hiep An JSC.pdf |
| 6/13/2019 | 1892 | 1892 SMC4-MA-369 Report on Frequency Test of PC Strand for Super T Girder (21st).pdf |
| 6/4/2019 | 1893 | 1893 SMC4-LC-582 Submission of Weekly Report No.54.pdf |
| 6/4/2019 | 1894 | 1894 SMC4-LC-583 Engineer's Confirmation for Safety & Environment Satisfaction (May 101,2019 to May 31,2019).pdf |
| 6/6/2019 | 1895 | 1895 SMC4-LC-586 Report on Environment Monitoring on Construction Stage (3rd Phase in May 2019, Base on S1.43).pdf |
| 6/4/2019 | 1896 | 1896 SMC4-WD-282 WD of Deck Slab Spans 25, 26, 29 & Link Slab P24-P26, P28, P29.pdf |
| 6/4/2019 | 1897 | 1897 SMC4-WD-283 WD of Super T Girder Span S50 (P49-P50).pdf |
| 6/4/2019 | 1898 | 1898 SMC4-MS-218 Method Drawing for Erection of Super T Girder at Spans from P27-P30.pdf |
| 6/4/2019 | 1899 | 1899 SMC4-LC-587 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P29.pdf |
| 6/5/2019 | 1900 | 1900 SMC4-LC-588 Organization Chart & Job Description of the Management & Key Personnel.pdf |
| 6/13/2019 | 1901 | 1901 SMC4-MA-370 Characteristis Strength for Concrete Class C of Transmeco BP-Report 3 (from 17Feb to 2Apr2019).pdf |
| 6/5/2019 | 1902 | 1902 SMC4-MA-371 Characteristic Strength for Concrete Class Y of Transmeco BP-Report 3( 4Mar to 28Apr2019).pdf |
| 6/5/2019 | 1903 | 1903 SMC4-WD-284 WD of Detail of Connection, Cross Beam, Manhole, Handhole & Water Drain of Steel Girder.pdf |
| 6/5/2019 | 1904 | 1904 SMC4-LC-589 Notice for Leave of Key Personnel (Project Manager).pdf |
| 6/5/2019 | 1905 | 1905 SMC4-MS-219 Resubmission of MS of Pre-Assembly of Steel Bridge at THANH LONG Factory.pdf |
| 6/6/2019 | 1906 | 1906 SMC4-LC-591 Summarize & Update of Countermeasure to Improve the Construction of Pier Head.pdf |
| 6/6/2019 | 1907 | 1907 SMC4-MA-373 Report on Testing Result of Welding Procedure for Steel Bridge.pdf |
| 6/6/2019 | 1908 | 1908 SMC4-MA-375 Report on Test Result of Welding Material for Steel Bridge.pdf |
| 6/7/2019 | 1909 | 1909 SMC4-LC-590 Notification of Delayed Approval-Instruction for WD of A1-P10 & A28L-P31L& P32L, P32R & P43L, P43C, P43R that affected to the Construction Schedule of Project.pdf |
| 6/7/2019 | 1910 | 1910 SMC4-LC-592 Rechecking Result of Girders of S30, S24 & Proposal for Replacement of Pre Tensioning Pre Stressed Super T Girders of S30 by S24 for Erection.pdf |
| 6/7/2019 | 1911 | 1911 SMC4-LC-593 Updated Quality Control Plan (2nd).pdf |
| 6/7/2019 | 1912 | 1912 SMC4-MS-220 Method Drawing for Construction of Pier Head P15-P16.pdf |
| 6/7/2019 | 1913 | 1913 SMC4-RP-68 Report for Excavation for Survey of Underground Utilities at P51.pdf |
| 6/7/2019 | 1914 | 1914 SMC4-MA-372 Report on Frequency Test of Cement, Coarse Aggregate, Fine Aggregate & Admixture for Cement Concrete at Transmeco BP(21th-26th) & Updated testing Results on Cement (19th).pdf |
| 6/7/2019 | 1915 | 1915 SMC4-MA-374 Report on Frequency Test of Reinforcing Steel for CIP Concrete Pier P38-P39,P40 (6th).pdf |
| 6/7/2019 | 1916 | 1916 SMC4-MA-377 Report on Frequency Test of Reinforcing Steel for Super T Girder (7th) of Team 4 Co.422.pdf |
| 6/7/2019 | 1917 | 1917 SMC4-MA-378 Report on Frequency Test of Reinforcing Steel-Vietnam Germany Steel for CIP Pile of P51-P54.pdf |
| 6/8/2019 | 1918 | 1918 SMC4-MS-286 Document for Relocation Electric Cable 22KV at P53.pdf |
| 6/8/2019 | 1919 | 1919 SMC4-WD-285 WD for CIP Concrete Pile for P43R & P43L.pdf |
| 6/8/2019 | 1920 | 1920 SMC4-RP-70 Report of Excavation for Survey of Underground Utilities at P12.pdf |
| 6/8/2019 | 1921 | 1921 SMC4-RP-71 Report of Excavation for Survey of Underground Utilities at P60.pdf |
| 6/8/2019 | 1922 | 1922 SMC4-RP-69 Report of Excavation for Survey of Underground Utilities at P13.pdf |
| 6/8/2019 | 1923 | 1923 SMC4-MA-376 Report on Frequency Test of PC Strand for Super T Girder (22nd).pdf |
| 6/8/2019 | 1924 | 1924 SMC4-MA-379 Use Manterial for Subbase, Base Manufactured & Supplied by VIMECO JSC.pdf |
| 6/8/2019 | 1925 | 1925 SMC4-LC-595 Additional Rebar Arrangement for Pier Head P16.pdf |
| 6/8/2019 | 1926 | 1926 SMC4-MA-380 Report on Results Trial Mix of Concrete Class A ( version 2- Cemment 525kg) used BASF Admixture of VIETTIEP BP ( New Location) & Using Mix Proportion for Construction of Super T Girder.pdf |
| 6/8/2019 | 1927 | 1927 5210 BGTVT-CQLXD Strengthening control of quality progress and labor safety.pdf |
| 6/8/2019 | 1928 | 1928 376 CQLXD-DDB1 Report on Results of Site Inspection.pdf |
| 6/8/2019 | 1929 | 1929 2038 BQLDATL-DA1 HCRR3 Removal of Crossing Drainage Pipe on Pham Van Dong Road.pdf |
| 6/10/2019 | 1930 | 1930 SMC4-MA-381 Report on Test of Jack, Anchorage & Synchoronous Experiment of Jack, PC Strand, Anchorage for Super T Girder (4th).pdf |
| 6/10/2019 | 1931 | 1931 SMC4-MA- 382 Report on Test Result of Galvanized Dowel D32, D60 - Viet Thang Co.LTD.pdf |
| 6/10/2019 | 1932 | 1932 SMC4-LC-594 Additional Information of Subcontractors Engaged in the Project.pdf |
| 6/10/2019 | 1933 | 1933 SMC4-RP-72 Report on Remedy Defect of Super T Girder (6 Fabricated Super T Girders).pdf |
| 6/10/2019 | 1934 | 1934 SMC4-MS-221 Calcuclation of Tendon Cable Elongation for Pier Head from P36.pdf |
| 6/10/2019 | 1935 | 1935 SMC4-MA-383 Use of Viet Tiep BP after Moving to New Location.pdf |
| 6/10/2019 | 1936 | 1936 SMC4-WD-287 WD of Substructure - Pier P48.pdf |
| 6/10/2019 | 1937 | 1937 SMC4-WD-288 WD of Substructure -Pier P49.pdf |
| 6/10/2019 | 1938 | 1938 SMC4-WD-289 WD of Substructure- Pier P50.pdf |
| 6/11/2019 | 1939 | 1939 SMC4-LC-596 Submision of Internal Target Construction Schedule of the Contractor.pdf |
| 6/17/2019 | 1940 | 1940 SMC4-MS-222 MS of Traffic Control for Public Road for Construction Superstructure.pdf |
| 6/11/2019 | 1941 | 1941 SMC4-LC-597 Notice of Equipment Demobilization -Crane Kobelco 7065 at P35 under Scope of 479 Co..pdf |
| 6/11/2019 | 1942 | 1942 SMC4-LC-598 Report of Result for Confirmation Quality of Concrete of CIP Concrete Pilling- Pile No. C2P38.pdf |
| 6/11/2019 | 1943 | 1943 2064-PMUTL-DHDA1 Checking Pier Head of P34.pdf |
| 6/11/2019 | 1944 | 1944 2053-PMUTL-DA1 Appropval of Subcontractor for Execution of Non Destructive Inspection for Welding of Steel Girder & Pier Head.pdf |
| 6/11/2019 | 1945 | 1945 SMC4-LC-599 Report on Environment Monitoring in Construction Stage (1st Phase in June 2019, based on S1.43).pdf |
| 6/11/2019 | 1946 | 1946 SMC4-LC 600 Report of Surface Repairing Work on Pier Head P33.pdf |
| 6/12/2019 | 1947 | 1947 2066 PMUTL-DA1 Approval of Additional Cost Estimate for tests on cast-in-place concrete Piles D1200 in Package 1,2.pdf |
| 6/12/2019 | 1948 | 1948 SMC4-LC-601 Report of Crack Phenomenon on Pier Head P34.pdf |
| 6/12/2019 | 1949 | 1949 SMC4-MS-223 Supplement of the Construction Method Drawing of Diaphragm at Span S22 (P21-P22) Mai Dich Side.pdf |
| 6/12/2019 | 1950 | 1950 SMC4-MS-224 Construction Method Drawing for Lower Part of Pier Head from P41-P42.pdf |
| 6/12/2019 | 1951 | 1951 SMC4-MS-225 Supplement of Calculation of Tendon Cable Elongation for Pier Head at P36.pdf |
| 6/12/2019 | 1952 | 1952 SMC4-LC-602 Result of Tip Contact Checking Test of CIP Concrete Pile C4-P39.pdf |
| 6/12/2019 | 1953 | 1953 SMC4-MA-384 Test Result of Shape Steel Material of Nippon Steel & Sumitomo Metal Cor..pdf |
| 6/12/2019 | 1954 | 1954 SMC4-MA-385 Report on Frequency Test of PC Strand for Super T Girder (23rd).pdf |
| 6/12/2019 | 1955 | 1955 SMC4-MA-386 Report on Frequency Test of Reinforcing Steel for Super T Girder (5th) of Team 01 Co.414.pdf |
| 6/12/2019 | 1956 | 1956 SMC4-RP-73 Report of Excavation for Survey of Underground Utilities at P42C.pdf |
| 6/12/2019 | 1957 | 1957 SMC4-RP-74 Report of Excavation for Survey of Underground Utilities at P50.pdf |
| 6/12/2019 | 1958 | 1958 SMC4-AD-50 AD of CIP Concrete Piling D1.2m of Pier P39.pdf |
| 6/12/2019 | 1959 | 1959 SMC4-AD-51 AD of CIP Concrete Piling D1.2m of Pier P38.pdf |
| 6/12/2019 | 1960 | 1960 SMC4-AD-52 AD of CIP Concrete Piling D1.2m of Pier P14.pdf |
| 6/12/2019 | 1961 | 1961 SMC4-AD-53 AD of CIP Concrete Piling D1.2m of Pier P60.pdf |
| 6/12/2019 | 1962 | 1962 SMC4-AD-54 AD of CIP Concrete Piling D1.2m of Pier P59.pdf |
| 6/12/2019 | 1963 | 1963 SMC4-AD-55 AD of Pre Tensioning Pre Stressed SuperT Girder Span 34 (P33-P34).pdf |
| 6/13/2019 | 1964 | 1964 SMC4-LC-603 Report on Implementation of Temporary Water Drainage for the Ministry of Public Secrurity Office.pdf |
| 6/13/2019 | 1965 | 1965 SMC4-LC-604 Reply to the Engineer's on Delay Reparing Work of Drilling Machine at P54 & P57.pdf |
| 6/13/2019 | 1966 | 1966 SMC4-LP-44 To Support the Contractor in Relocating Camera Control Cabinet at Pier P28.pdf |
| 6/13/2019 | 1967 | 1967 SMC4-LC-605 Changing Design of Drainage Pipe Culvert D500 (2nd).pdf |
| 6/13/2019 | 1968 | 1968 SMC4-LC-606 Result of Tip Contact Checking Test of CIP Concrete Pile C1-P59.pdf |
| 6/13/2019 | 1969 | 1969 SMC4-AD-56 AD of Substructure- Pile Cap, Pier Column & Pier Head of Pier P28.pdf |
| 6/13/2019 | 1970 | 1970 SMC4-AD-57 AD of Backfill for Section P28-P29.pdf |
| 6/14/2019 | 1971 | 1971 SMC4-MA-387 Use Membrane on Pier Head for Friction Cut Material- SBS Modified Bitumen Waterproof Membrane by WEIFANG LUYANG WM Co. & supplied by HIEP AN JSC.pdf |
| 6/14/2019 | 1972 | 1972 SMC4-LC-607 Submission of Weekly Report No.55.pdf |
| 6/14/2019 | 1973 | 1973 SMC4-LC-608 Submission of Weekly Report No.56.pdf |
| 6/14/2019 | 1974 | 1974 SMC4-LC-609 Submission of Monthly Report No.13.pdf |
| 6/14/2019 | 1975 | 1975 SMC4-LC-611 Resubmission of Organization Chart & Key Personnel Job Description of the Management & Key Personnel.pdf |
| 6/14/2019 | 1976 | 1976 SMC4-LC-610 Report of Surface Condition & Repairing Work on Pier Head P28.pdf |
| 6/14/2019 | 1977 | 1977 SMC4-MA-388 Report on Trial Mix of Concrete Class B1,C1,C3,C4,G & Y at Asean BP ( new Location) & Using Mix Proporting for Construction of PK1.pdf |
| 6/14/2019 | 1978 | 1978 SMC4-RP-75 Report on Excavation for Survey of Underground Utilities at P11.pdf |
| 6/14/2019 | 1979 | 1979 SMC4-MS-226 Supplement of the Calculation for Pre Stressing of Super T Girder 38m-Group No.1 Co.422.pdf |
| 6/17/2019 | 1980 | 1980 SMC4-MS-227 MS of Pile Cap from P11-P13.pdf |
| 6/17/2019 | 1981 | 1981 SMC4-RP-76 Report on Excavation for Survey of Underground Utilities at P14.pdf |
| 6/17/2019 | 1982 | 1982 SMC4-RP-77 Report on Loading Test of Pier Head's Supporting System at P16.pdf |
| 6/17/2019 | 1983 | 1983 SMC4-LC-612 Updated Report of Crack Phenomenon on Pier Head P34.pdf |
| 6/17/2019 | 1984 | 1984 SMC4-MS-228 Method Drawing for Construction of Pile Cap from P59-P60.pdf |
| 6/18/2019 | 1985 | 1985 SMC4-WD-290 WD of Detail of Segment 1 to 5 of Steel Girder (2nd).pdf |
| 6/18/2019 | 1986 | 1986 SMC4-MS-229 MS of Traffic Control for Public Road at P38-P60 - Vol VII.3 Arranging Traffic Control after Extending Site Fence at P46-P47 & P55-P56 Right Side.pdf |
| 6/18/2019 | 1987 | 1987 SMC4-MS-230 Supplement of Construction Method Drawing of Diaphragm from P19-P31.pdf |
| 6/26/2019 | 1988 | 1988 SMC4-LC-614 Mobilization Document for Equipment & Labour of Subcontrctor PHATECO JSC for NDT of Steel Bridge (1st).pdf |
| 6/18/2019 | 1989 | 1989 SMC4-MC-14 Application for Interim Payment Certificate No.11 (Period May 1,2019 to May 31,2019).pdf |
| 6/19/2019 | 1990 | 1990 SMC4-LC-615 Report on Status of Connection Drainage System between 2 Project (3rd).pdf |
| 6/19/2019 | 1991 | 1991 SMC4-LC-616 Top Elevation of Bearing Pad in According with Actual Camber of Super T Girder at Span S35-S37.pdf |
| 6/19/2019 | 1992 | 1992 SMC4-MA-389 Report on Frequency Test of PC Strand for Super T Girder (24th).pdf |
| 6/19/2019 | 1993 | 1993 SMC4-MS-231 MS of Gate Arrangement at Pier P25-P26.pdf |
| 6/19/2019 | 1994 | 1994 SMC4-MS-232 Calculation of Tendon Cable Elongation for Pier Head P16.pdf |
| 6/19/2019 | 1995 | 1995 SMC4-LC-617 Reply to the Engineer's Comment Regarding the Improvement Method for Construction of Pier Head.pdf |
| 6/20/2019 | 1996 | 1996 SMC4-RP-78 Transportation Plan of Super T Girder & Permit from Directorate for Road of Viet Nam.pdf |
| 6/20/2019 | 1997 | 1997 SMC4-LC-618 Additional Mobilization Document-Welder Qualification Record for Steel Bridge Work of Subcontractor Thanh Long JSC(4th).pdf |
| 6/20/2019 | 1998 | 1998 SMC4-LC-619 Additional Information of Subcontractors Engaged in Project.pdf |
| 6/20/2019 | 1999 | 1999 SMC4-LC-620 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P28.pdf |
| 6/21/2019 | 2000 | 2000 2178-TB-BQLDATL Notice on Conclusions given by PMUTL in the Meeting to Review the Implementation of PK1 & PK2.pdf |
| 6/21/2019 | 2001 | 2001 SMC4-LC-621 Submission of Weekly Report No.57.pdf |
| 6/21/2019 | 2002 | 2002 SMC4-AD-58 As Built Drawings of CIP Concrete Pile of P13.pdf |
| 7/9/2019 | 2003 | 2003 SMC4-LC-624 Outline for Repairing Cracks on Pier Head P34 & Capacity Profile of Crack Repairing Service- Transport & Communication Consulting & Construction JSC.pdf |
| 6/24/2019 | 2004 | 2004 SMC4-LC-622 Report on Environment Monitoring in Construction Stage (2nd Phase in June 2019 based on S1.43).pdf |
| 6/24/2019 | 2005 | 2005 SMC4-MA-391 Supplier Transport Material Equipment Trading JSC for Reinforcing Steel VN Italy Steel JSC.pdf |
| 6/26/2019 | 2006 | 2006 SMC4-LC- 623 Report of Surface Repairing Work on Pier Head P23.pdf |
| 6/27/2019 | 2007 | 2007 SMC4-MA-390 Accelerated Weather Resistance Resting Result at 500 Hours & 1000 Hours of Fluorex Finish Top Coat of Hai Phong JSC.pdf |
| 6/27/2019 | 2008 | 2008 SMC4-MA-390B Report on Frequency Test of Reinforcing Steel VGS Steel for Pile Cap, Pier Column & Pier Head of P59, P60, P14 (2nd).pdf |
| 6/24/2019 | 2009 | 2009 SMC4-MA-390A Report on Frequency Test of Reinforcing Steel VGS Steel for Pile Cap, Pier Column & Pier Head P59, P60, P14.pdf |
| 6/24/2019 | 2010 | 2010 SMC4-MS-233 MS for Construction of Pile Cap from P59-P60 (Rev.2).pdf |
| 6/24/2019 | 2011 | 2011 SMC4-MA-393 Report on Frequency Test of Reinforcing Steel VN Germany Steel for CIP COncrete Pile of P51-P54 (2nd).pdf |
| 6/24/2019 | 2012 | 2012 SMC4-MA-392 Report on Frequency Test of Reinforcing Steel VN Germany Steel for Pile Cap, Pier Column & Pier Head of P11-P13.pdf |
| 6/25/2019 | 2013 | 2013 SMC4-MS-234 MS for Painting of External Super T Girder.pdf |
| 6/25/2019 | 2014 | 2014 SMC4-MS-235 Method Drawing for Erection of Super T Girder at Spans S23(P22-P23).pdf |
| 6/25/2019 | 2015 | 2015 SMC4-MA-394 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column, Pier Head of Pier P38 (5th), P39, P40 (4th).pdf |
| 6/25/2019 | 2016 | 2016 SMC4-WD-291 WD of Details of Connection, Cross Beam, Man Hole, Hand Hole, Water Drain of Steel Girder (2nd).pdf |
| 6/25/2019 | 2017 | 2017 SMC4-AD-59 As Built Drawings of CIP Concrete Piling D1.2m of P42C.pdf |
| 6/25/2019 | 2018 | 2018 SMC4-AD-60 AD of Pre-tensioning Pre-stressed Super-Tee Girder Span 23(P22-P23).pdf |
| 6/25/2019 | 2019 | 2019 SMC4-LC-626 Supplement Data of Cracks on Thang Long Side of Pier Head P34.pdf |
| 7/9/2019 | 2020 | 2020 SMC4-LC-625 Installation of RC Planks for Super-T Girder and for the Construction of Diaphragm.pdf |
| 6/26/2019 | 2021 | 2021 SMC4-LP-46 Supporting the Contractor in Handing Over Materials & Assets of Traffic Signal System & Concrete Blocks for Managerment Units.pdf |
| 6/26/2019 | 2022 | 2022 SMC4-LP-45 Supporting the Contractor in Extending the Method of Fencing, TC for Construction Eriction Super T Girder & Licensing Regarding Method of TC.pdf |
| 6/26/2019 | 2023 | 2023 SMC4-WD-292 WD of Super T Girder Spans S51-S52 (2nd).pdf |
| 6/26/2019 | 2024 | 2024 SMC4-WD-293 WD of Super T Girder Span S54-S61 (2nd).pdf |
| 6/27/2019 | 2025 | 2025 SMC4-MS-231A MS for Construction of Pier Head from P15-P16 (Rev.2).pdf |
| 6/26/2019 | 2026 | 2026 SMC4-MS-236 MS of Traffic Control for Public Road at Section at A1-P25- Vol VIII.1- Arranging Traffic Control at Section A1- P25.pdf |
| 6/26/2019 | 2027 | 2027 SMC4-MS-237 Supplement of the Construction Method Drawing of Pier Head 2nd Tesioning & Construction Ear Wall, Block Out of Anchorage.pdf |
| 6/26/2019 | 2028 | 2028 SMC4-LC-627 Additional Mobilization Documents Manpower & Equipment for Substructure Work at the Area P8-P13 under Scope of Co.422.pdf |
| 6/26/2019 | 2029 | 2029 SMC4-LC-628 Additional Mobilization Document for 2 Trailers & Renewal of Registration Certificate for 1 Tractor for Transportation & Erection Work of Super T Girder (4th).pdf |
| 6/26/2019 | 2030 | 2030 SMC4-WD-294 WD of Super T Girder Span S44.pdf |
| 6/26/2019 | 2031 | 2031 SMC4-WD-295 WD of Super T Girder Span S45.pdf |
| 6/26/2019 | 2032 | 2032 SMC4-RP-79 Supplement of Permit from Directorate for Road of Viet Nam.pdf |
| 6/27/2019 | 2033 | 2033 MOT-PMUTL Invitation 27Jun2019 Inspectation & Review the Execution of Steel Bridges of HCRR3 Construction Project.pdf |
| 6/29/2019 | 2034 | 2034 SMC4-LC-629 Submission of Sub Contract Agreement Between Main Contractor & Sub Contractor for Non-Destructive Test.pdf |
| 6/27/2019 | 2035 | 2035 SMC4-RP-80 Report on Excavation for Survey of Underground Utilities at P46.pdf |
| 6/27/2019 | 2036 | 2036 SMC4-MA-395 Trial Mix of Concrete C1, C3, C4 and Y at Viet Tiep BP ( New Location) & Using Mix Proportion for Construction of PK1.pdf |
| 7/2/2019 | 2037 | 2037 SMC4-LC-631 Submission of Result of Ultrasonic Test of Cast in Place Concrete Piles at P58.pdf |
| 6/28/2019 | 2038 | 2038 SMC4-WD-296 WD of Substructure Pile Cap of Pier P32C(2th).pdf |
| 6/28/2019 | 2039 | 2039 SMC4-LC-630 Notice of Environmental Monitoring Schedule in July 2019 at Construction Phase.pdf |
| 6/28/2019 | 2040 | 2040 SMC4-LC-633 Revised Programme and Acceleration of Construction Progress.pdf |
| 6/28/2019 | 2041 | 2041 SMC4-MA-396 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head of Piers P38,P41,P42,P43(6th) and Piers P39,P40(5th).pdf |
| 7/5/2019 | 2042 | 2042 SMC4-MA-397 Report on Frequency Test of Reinforcing Steel for Super T Girder(8th) of Team 4(Co.422).pdf |
| 6/28/2019 | 2043 | 2043 SMC4-RP-0081 Report on Excavation for Survay of Underground Utilities at P47(2nd).pdf |
| 7/1/2019 | 2044 | 2044 SMC4-LC-634 Construction Work for the 1st Stage of Pier Column (5-Metter Height) of Piers P11-P14 and P32C.pdf |
| 7/1/2019 | 2045 | 2045 SMC4-MS-238 Method Statement of Pier Column from P59-P60.pdf |
| 7/13/2019 | 2046 | 2046 SMC4-MS-239 MS of TC for Public Road at Section P38-P60. Volume VII.4- Arranging TC after Extending Site Fence at Section P38-P56.pdf |
| 7/1/2019 | 2047 | 2047 SMC4-WD-297 WD of Backfill for Sections P32&P41-P43&P46-P60 (3nd).pdf |
| 7/1/2019 | 2048 | 2048 SMC4-MA-398 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column & Pier Head of Piers P57, P58 (1st).pdf |
| 7/1/2019 | 2049 | 2049 SMC4-LC-632-19 Variation Order No. VO-HRR3-PK1-004 -Design Change of Pile Foundation at P9-P15 and P45-P58 Section.pdf |
| 7/1/2019 | 2050 | 2050 2402 PMUTL-DHDA1 Implementation of Decision No.1219-QD-BGTVT dated June 27,2019 by the Ministry of Transport(MOT).pdf |
| 7/1/2019 | 2051 | 2051 2430-PMUTL- Invitation to attend a Site Inspection & Review the Execution of Steel Bridges of the HCRR3 Construction Project.pdf |
| 7/1/2019 | 2052 | 2052 SMC4-LC-636 Additional Supervision Cost of Engineer's Staff (April 2019).pdf |
| 7/1/2019 | 2053 | 2053 SMC4-LC-628A Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P23.pdf |
| 7/1/2019 | 2054 | 2054 SMC4-LC-628B Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P42C.pdf |
| 7/1/2019 | 2055 | 2055 SMC4-LC-628C Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P60.pdf |
| 7/1/2019 | 2056 | 2056 SMC4-AD-61-As Built Drawings of CIP Concrete Piling D1.2m of Pier P12.pdf |
| 7/1/2019 | 2057 | 2057 SMC4-LC-635 Submission of Weekly Report No.58.pdf |
| 7/2/2019 | 2058 | 2058 SMC4-MS-240 Method Drawing for Erection of Super T Girder at Span S28 ( P27-P28).pdf |
| 7/2/2019 | 2059 | 2059 2453-BQLDATL-GM Attending at Meeting on some Clarifications of Detailed Design of HCRR3 Construction Project.pdf |
| 7/3/2019 | 2060 | 2060 SMC4-LC-638 Report on Environment Monitoring in Construction Stage (3rd Phase in June 2019 based S1.43).pdf |
| 7/3/2019 | 2061 | 2061 SMC4-MA-399 Characteristic Strength for Concrete Class C of Transmeco BP- Report 4 (4Apr to 12May2019).pdf |
| 7/3/2019 | 2062 | 2062 SMC4-RP-82 Report on Loading Test of Supporting System P24.pdf |
| 7/3/2019 | 2063 | 2063 SMC4-LC-639 Additional CIP Concrete Pilling for P43C (2nd).pdf |
| 7/18/2019 | 2064 | 2064 SMC4-MS-241 Adjusted Plan for Reconnect Culvert Pipe of Ministry of Police Public (3rd).pdf |
| 7/3/2019 | 2065 | 2065 SMC4-WD-298 WD of Deck Slab Span 38& 39 & Link Slab at P37-P39.pdf |
| 7/3/2019 | 2066 | 2066 SMC4-AD-62 AD of Pre Tensioning Pre Stressed Super T Girder Span 28 (P27-P28).pdf |
| 7/4/2019 | 2067 | 2067 SMC4-LC-628D Acceptance of C.I.P Pile Foundation Construction Stage and Transfer to Construction of Substructure Work for P13.pdf |
| 7/4/2019 | 2068 | 2068 SMC4-LC-637 Acceptance of Sub Structure Construction Stage and Transfer to Construction of Superstructure Work for P27.pdf |
| 7/5/2019 | 2069 | 2069 SMC4-LC-640 Approved of Top Elevation of Bearing pad in Accordance with Actual Camber of Super T Girder at Spans S24,S25,S28.pdf |
| 7/5/2019 | 2070 | 2070 SMC4-LC-641 Stage Inspection for the Week from July 6th,2019 to July 12th, 2019.pdf |
| 7/5/2019 | 2071 | 2071 SMC4-LC-642 Result of Ultrasonic Test of Cast in place Concrete Piles at P57.pdf |
| 7/5/2019 | 2072 | 2072 SMC4-LC-643 Report on Environmental Monitoring Results at Stage 2 - 2019 at Steel Structure Fabrication Factory of Thanh Long Group JSC.pdf |
| 7/5/2019 | 2073 | 2073 SMC4-AD-63 AD of Pre Tensioning Pre Stressed Super T Girder Span 37 (P36-P37).pdf |
| 7/5/2019 | 2074 | 2074 SMC4-AD-64 AD of Pre Tensioning Pre Stressed Super T Girder Span 36 (P35-P36).pdf |
| 7/5/2019 | 2075 | 2075 SMC4-RP-83 Excavation for Survey of Underground Utilities at P55,P56.pdf |
| 7/5/2019 | 2076 | 2076 SMC4-WD-299 WD of Elastomeric bearing (from P15 to P16).pdf |
| 7/5/2019 | 2077 | 2077 SMC4-MA-400 The Characteristic Strength for Concrete Class Y of Transmeco Batching Plant, Report No 4 (from 4.5.2019 to 27.5.2019).pdf |
| 7/5/2019 | 2078 | 2078 SMC4-MA-401 Report on Frequency Test of Reinforcing Steel for Pier Head of Pier P26 (5th).pdf |
| 7/6/2019 | 2079 | 2079 SMC4-MA-402 Report on Frequency Test of Reinforcing Steel for Pile Cap, Pier Column and Pier Head of P14(3th).pdf |
| 7/5/2019 | 2080 | 2080 SMC4-MA-403 Report on Frequency Test of Reinforcing Steel for Cast in Place Concrete Pile Pier P46,P47 (2nd) and Pile Cap, Pier Column, Pier Head P24(6th), Pile Cap, Pier Column, Pier Head P25&P26 (5th).pdf |
| 7/5/2019 | 2081 | 2081 SMC4-MA-404 Report on Frequency Test of PC Strand for Super T Girder (25th).pdf |
| 7/5/2019 | 2082 | 2082 SMC4-MS-242 MS of Temporary Facilities Arrangement on Site from P38-P56.pdf |
| 7/5/2019 | 2083 | 2083 SMC4-MS-243 MS for Lower Part of Pier Head P59-P60.pdf |
| 7/5/2019 | 2084 | 2084 SMC4-MS-244 MS of Pile Cap from P57-P58.pdf |
| 7/5/2019 | 2085 | 2085 SMC4-AD-65 AD of CIP Concrete Pilling D1.2m of P58.pdf |
| 7/5/2019 | 2086 | 2086 SMC4-AD-66 AD of CIP Concrete Pilling D1.2m of Pier P57.pdf |
| 7/5/2019 | 2087 | 2087 SMC4-MS-245 MS for Erection of Super T Girder at Spans S37 ( P36-P37).pdf |
| 7/6/2019 | 2088 | 2088 SMC4-LC-644 Acceptance of CIP Concrete Pile Foundation Construction Stage & Tranfer to Construction of Substructure Work for P12.pdf |
| 7/8/2019 | 2089 | 2089 SMC4-MA-405 Report on Frequency Test of Cement, Coarse Aggregate, Coarse Aggregate for Class A, Fine Aggregate , Admixture & Water for Cerment Concrete at Viet Tiep BP (7th).pdf |
| 7/8/2019 | 2090 | 2090 SMC4-MA-406 Report on Frequency Test of Cement, Coarse Aggregate, Fine Aggregate & Water for Cement Concrete at TRANSMECO BP (27th to 32nd) & Updated Testing Results (17th,22nd,23rd).pdf |
| 7/8/2019 | 2091 | 2091 SMC4-LC-645 Summary Table of Waste Disposal Implemented by the Subcontractors at Nguyen Khe Disposal Area from Jan to Mar 2019.pdf |
| 7/8/2019 | 2092 | 2092 SMC4-LC-646 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P35.pdf |
| 7/8/2019 | 2093 | 2093 SMC4-LC-647 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P14.pdf |
| 7/9/2019 | 2094 | 2094 SMC4-LC-648 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Subtructure Work for P58.pdf |
| 7/9/2019 | 2095 | 2095 SMC4-MS-245A Method Drawing of Pier Head & Loading Test of Pier Head's Supporting System at P26.pdf |
| 7/9/2019 | 2096 | 2096 SMC4-AD-67 As Built Drawings of Pre Tensioning Pre Stressed Super T Girder Span 35 (P34-P35).pdf |
| 7/8/2019 | 2097 | 2097 SMC4-LC-651 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P36..pdf |
| 7/8/2019 | 2098 | 2098 SMC4-LC-652 Acceptance of Sub Structure Construction Stage & Tranfer to Construction of Superstructure Work for P37.pdf |
| 7/9/2019 | 2099 | 2099 SMC4-MS-246 Calculation of Tendon Cable Elongation for Pier Head P24.pdf |
| 7/9/2019 | 2100 | 2100 SMC4-MS-247 Outline for Loading Test of Pier Head's Supporting System P38-P40.pdf |
| 7/9/2019 | 2101 | 2101 SMC4-RP-84 Notice of DOT Regarding- Traffic Diversion & Organization on PVD Street for Construction of Superstructure Items ( Pier Head Tensioning, Daphragm , Deck Slab, Parapet, etc.).pdf |
| 7/9/2019 | 2102 | 2102 SMC4-RP-85 Notice of DOT Regarding- Traffic Diversion & Organization on PVD Street for Super T Girder Erection.pdf |
| 7/9/2019 | 2103 | 2103 SMC4-WD-300 WD of Substructure - Pile Cap P43.pdf |
| 7/10/2019 | 2104 | 2104 SMC4-LC-657 Withdrawal of the Letter SMC4-MA-0403-19 dated 05Jun2019.pdf |
| 7/10/2019 | 2105 | 2105 SMC4-MA-398A Report on Frequency Test of Reinforcing Steel for CIP Concrete Pile P46,P47 (2nd) & Pile Cap, Pier Column, Pier Head (6th) Pile Cap, Pier Column Pier Head P25 (5th).pdf |
| 7/10/2019 | 2106 | 2106 SMC4-LC-625A Withdrawal of the Letter SMC4-LC-0624-19 dated 22Jun2019.pdf |
| 7/10/2019 | 2107 | 2107 SMC4-LC-627A Outline for Repairing Carks on Pier Head P34 & Capacity Profile of Crack Repairing Service- Transport & Commonication Consulting & Construction JSC.pdf |
| 7/19/2019 | 2108 | 2108 SMC4-MS-248 MS of Pre-Assembly for Steel Bridge at Thanh Long Factory (3rd).pdf |
| 7/10/2019 | 2109 | 2109 SMC4-LT-25 Capacity profile of Stone for Asphalt Concrete Pavement of Ha Tay JSC.pdf |
| 7/10/2019 | 2110 | 2110 SMC4-MA-407 Report on Frequency Test of Reinforcing Steel of VGS for Super T Girder (7th) of Team 2 (407 Co.).pdf |
| 7/10/2019 | 2111 | 2111 SMC4-MA-408 Report on Frequency Test of Steel for Pile Cap, Pier Column & Pier Head P57, P58 (2nd).pdf |
| 7/10/2019 | 2112 | 2112 SMC4-MA-409 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head of P38,P41-P43(7th)& P39,P40(6th).pdf |
| 7/10/2019 | 2113 | 2113 SMC4-LC-654 Manpower Mobilization Document of Subcontractor Hiep An.pdf |
| 7/10/2019 | 2114 | 2114 SMC4-LC-655 Mobilization Document for Manpower & Machine of Subcontractor Thanh Long JSC for Transportaion of Steel Girders.pdf |
| 7/10/2019 | 2115 | 2115 SMC4-LC-656 Additional Mobilization Document for Additonal Welders Basting & Painting Workers for Steel Bridge Work of Thanh Long JSC(5th).pdf |
| 7/22/2019 | 2116 | 2116 SMC4-LC-658 Report on Environment Monitoring in Construction Stage June 2019 (Base on EMP).pdf |
| 7/11/2019 | 2117 | 2117 SMC4-LC-659 Further Instruction on Specifications & BOQ Related to Design Modification of Relocation of Abutment A1.pdf |
| 7/11/2019 | 2118 | 2118 SMC4-LC-660 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P58.pdf |
| 7/12/2019 | 2119 | 2119 SMC4-MS-249 Outline for Loading Test of Pier Head Supporting System at P15.pdf |
| 7/12/2019 | 2120 | 2120 SMC4-MS-250 Method Drawing for Erection of Super T Girder at S34 (P33-P34), S35 (P34-P35).pdf |
| 7/12/2019 | 2121 | 2121 SMC4-MS-251 Method Statement of Pier Head from P38-P40.pdf |
| 7/12/2019 | 2122 | 2122 SMC4-WD-304 WD of Substructure - Pier P14.pdf |
| 7/12/2019 | 2123 | 2123 SMC4-WD-303 WD of Substrcuture - Pier P13.pdf |
| 7/12/2019 | 2124 | 2124 SMC4-WD-302 WD of Substructure - Pier P12.pdf |
| 7/12/2019 | 2125 | 2125 SMC4-WD-301 WD of Substructure - Pier P11.pdf |
| 7/12/2019 | 2126 | 2126 SMC4-RP-86 Report on Loading Test of Pier Head's Supporting System at P25.pdf |
| 7/12/2019 | 2127 | 2127 SMC4-RP-87 Report on Loading Test of Supporting System of Pier Head P26.pdf |
| 7/12/2019 | 2128 | 2128 SMC4-LC-661 Submission of Weekly Report No.59.pdf |
| 7/12/2019 | 2129 | 2129 SMC4-LC-662 Submission of Weekly Report No.60.pdf |
| 7/12/2019 | 2130 | 2130 SMC4-WD-305 WD of Adjustment for Exterior Girder (EXT1-G5,EXT1-G6), Spans S10-S14.pdf |
| 7/12/2019 | 2131 | 2131 SMC4-LC-663 Report on Environment Monitoring in Construction Stage(1st Phase in July 2019 based on S1.43).pdf |
| 7/13/2019 | 2132 | 2132 SMC4-MS-253 MS of Diaphragm Construction from S37-S40.pdf |
| 7/13/2019 | 2133 | 2133 SMC4-MS-254 MS of Pier Column from P11-P13.pdf |
| 7/15/2019 | 2134 | 2134 SMC4-LC-665 Engineer's Confirmation for Safety and Environment Satisfaction (June 01,2019 to June 30,2019).pdf |
| 7/15/2019 | 2135 | 2135 SMC4-WD-306 WD for Basement for Traffic Sign Board at Pier P50.pdf |
| 7/15/2019 | 2136 | 2136 SMC4-307 WD for Basement for Traffic Sign Board at Pier P7.pdf |
| 7/15/2019 | 2137 | 2137 SMC4-MA-410 RP on Frequency Test of Reinforcing Steel Vietnam Germany Steel for Super T Girder (9th) of Team 04(Co.422).pdf |
| 7/15/2019 | 2138 | 2138 SMC4-MA-411 Changing Testing Standard of Waterproofing for Deck Slab Material (Haseal 5) of Technical Specification).pdf |
| 7/15/2019 | 2139 | 2139 SMC4-MA-412 The Characteristic Strength for Concrete class A of Viet Tiep Batching Plant - RP No3 (from 4-4-2019 to 7-6-2019).pdf |
| 7/27/2019 | 2140 | 2140 SMC4-MS-255 Approval of Method Statement of Deck Slab Construction from P19-P31.pdf |
| 7/15/2019 | 2141 | 2141 2578-GM-BQLDATL Invitation Letter - Meeting on Design Modification of On-Off Ramps of HCRR3 Construction Project.pdf |
| 7/15/2019 | 2142 | 2142 SMC4-WD-308 WD of Cast in Place Concrete Pile for Pier P9 (2nd).pdf |
| 7/15/2019 | 2143 | 2143 SMC4-WD-309 WD of Cast in Place Concrete Pile for Pier P10 (2nd).pdf |
| 7/15/2019 | 2144 | 2144 SMC4-AD-68 AD of Cast in Place Concrete Piling D1.2m of Pier P11.pdf |
| 7/15/2019 | 2145 | 2145 SMC4-LC-666 Sub- Structure Construction Stage and Transfer to Construction of Superstructure Work for P33.pdf |
| 7/15/2019 | 2146 | 2146 SMC4-LP-47 Short Name for VND Bank Account to be Disbursed by Counterpart-fund of PK1.pdf |
| 7/15/2019 | 2147 | 2147 TB-BQLDATL Notice on Conclusions Given by PMU Thang Long in the Meeting to Review the Implementation of PK1 & 2 under the HCRR3 Construction Project.pdf |
| 7/16/2019 | 2148 | 2148-SMC4-LC-664 Report on the Result of P34's Pier Head Concrete Quality Checking After Repaired.pdf |
| 7/16/2019 | 2149 | 2149 SMC4-WD-310 WD of Cast in Place Concrete Pile for Pier P7 (2nd).pdf |
| 7/16/2019 | 2150 | 2150 SMC4-WD-311 WD of Cast in Place Concrete Pile for Pier P8 (2nd).pdf |
| 7/16/2019 | 2151 | 2151 SMC4-WD-312 WD of Cast in Place Concrete Pile for Abutment A1 (2nd).pdf |
| 7/16/2019 | 2152 | 2152 SMC4-LC-653A Update Data of Cracks on P34 Pier Head (Thang Long Side) and Report of Cracks on P34C Pier Column.pdf |
| 7/16/2019 | 2153 | 2153 SMC4-LC-667 Variation Order No. VO-HRR3-PK1-001A- Additional Cost Estimate for Test on Cast in Place Concrete Piles D1200 (Design Changed from Rotation Steel Piles to Cast in Place Concrete Piles.pdf |
| 7/16/2019 | 2154 | 2154 Report for Site Instruction No 43 Dated 9 July 2019.pdf |
| 7/16/2019 | 2155 | 2155 SMC4-LC-668 Monthly Report No.14.pdf |
| 7/16/2019 | 2156 | 2156 SMC4-LC-670 Withdrawal of the letter SMC4-LC-659 dated 10 July 2019.pdf |
| 7/17/2019 | 2157 | 2157 SMC4-LC-669 Sub-Structure Construction Stage and Transfer to Construction of Superstructure Work for P34.pdf |
| 7/26/2019 | 2158 | 2158 2553 PMUTL-DHDA1 Approval of Variation Order No.VO-HRR3-PK1-004 for Design change of Pile Foundation at P9-P15 and P45-P58.pdf |
| 7/18/2019 | 2159 | 2159 SMC4-LC-671 Updated Report of Crack Phenomenon on Pier Head P33 (16 Jun 19).pdf |
| 7/26/2019 | 2160 | 2160 SMC4-LC-672 Report of Crack Phenomenon on Pier Head P35.pdf |
| 7/18/2019 | 2161 | 2161 SMC4-MC-15 Application for Interim Payment Certificate No.12 ( Period June1 to Jun30,2019).pdf |
| 7/18/2019 | 2162 | 2162 SMC4-LC-673 Response to the Engineer's Letter ENG-PK1-0907-19 dated 5Jul2919 Regarding Update of Construction Method of Pier Head Type based on Actual Site Condition.pdf |
| 7/18/2019 | 2163 | 2163 SMC4-WD-313 WD of Super T Girder Span S9 (P8-P9).pdf |
| 7/18/2019 | 2164 | 2164 SMC4-RP-88 Report on Excavation for Survey of Underground Utilities at P51 (2nd).pdf |
| 7/18/2019 | 2165 | 2165 SMC4-RP-89 Report on Excavation for Survey of Underground Utilities at P52 (2nd).pdf |
| 7/18/2019 | 2166 | 2166 SMC4-RP-90 Report on Loading Test of Pier Head's Supporting System at P15.pdf |
| 7/19/2019 | 2167 | 2167 SMC4-MA-388A Supplier Vinh Hung Trading Consulting & Construction JSC for 2 Slots of PC Strand 15.2 of GUIZHOU Co..pdf |
| 7/19/2019 | 2168 | 2168 SMC4-MA-406A Report on Frequency Test of PC Strand for Super T Girder ( 25th & 26th).pdf |
| 7/20/2019 | 2169 | 2169 SMC4-AD-69 As-built Drawing of Pre Tensioning Pre Stressed Super T Girder Span 36 (P35-P36)(2nd).pdf |
| 7/20/2019 | 2170 | 2170 SMC4-WD-314 WD of CIP Concrete Pile for P32R and P32L.pdf |
| 7/20/2019 | 2171 | 2171 SMC4-WD-315 WD of Pile Cap of Side & Column of Pier P32.pdf |
| 7/20/2019 | 2172 | 2172 SMC4-MA-413 Report on Frequency Test of Reinforcing Steel VGS for Pier Column of P11-P13.pdf |
| 7/20/2019 | 2173 | 2173 SMC4-MA- 414 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab, Parapet of Span S30.pdf |
| 7/20/2019 | 2174 | 2174 SMC4-MA-415 Report on Frequency Test of Reinforcing Steel VGS for Super T Girder of Team 1( 414 Co).pdf |
| 7/20/2019 | 2175 | 2175 SMC4-MA-416 Report on Frequency Test of Reinforcing Steel-VGS for CIP Concrete Pile of P48-P49(2nd), Diaphargm Span P27-P28(1st).pdf |
| 7/20/2019 | 2176 | 2176 SMC4-RP-91 Report on Loading Test of Pier Head's Supporting System at P40.pdf |
| 7/20/2019 | 2177 | 2177 SMC4-MS-256 MS of Pier Column From P57-P58.pdf |
| 7/20/2019 | 2178 | 2178 SMC4-LC-675 Acceptance of Substructure Construction stage & Transfer to Constructrion of Superstructure Work for P35.pdf |
| 7/20/2019 | 2179 | 2179 SMC4-LC-674 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P11.pdf |
| 7/20/2019 | 2180 | 2180 SMC4-MA-418 Report on Frequency Test of PC Strand for Super T Girder (27th).pdf |
| 7/22/2019 | 2181 | 2181 SMC4-MA-420 Report on Frequency Test of Reinforcing Steel VGS for CIP Pile P51-P54 (3rd).pdf |
| 7/22/2019 | 2182 | 2182 SMC4-RP-92 Report on Excavation for Survey of Underground Utilities at P9, P10.pdf |
| 7/22/2019 | 2183 | 2183 SMC4-MA-417 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab S21, S22.pdf |
| 7/22/2019 | 2184 | 2184 SMC4-MA-419 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column & Head of P15 (4th) & Diaphragm of Span S20,S23.pdf |
| 7/22/2019 | 2185 | 2185 SMC4-AD-70 As-built Drawing of CIP Concrete Piling D1.2m of P57(2nd).pdf |
| 7/22/2019 | 2186 | 2186 SMC4-WD-316 WD for General Arrangment of Traffic Sign for Expressway from Km0+130 - Km0+904.49.pdf |
| 7/22/2019 | 2187 | 2187 SMC4-WD-317 WD for General Layout of Traffic Sign for Urban Road.pdf |
| 7/22/2019 | 2188 | 2188 SMC4-MS-257 Supplement & Updating the MS Plan drawing of CIP Concrete Piling from Abutment A1 to P10.pdf |
| 7/22/2019 | 2189 | 2189 SMC4-MS-258 Calculation of Tendon Cable Elongation for Pier Head P25-P26.pdf |
| 7/22/2019 | 2190 | 2190 SMC4-LC-676 Report on the Result of P34C Pier Column Surface Repairing.pdf |
| 7/23/2019 | 2191 | 2191 SMC4-LC-677 Report on the Result of P33 Pier Head Surface Repairing.pdf |
| 7/22/2019 | 2192 | 2192 SMC4-LC-679 Report on Environment Monitoring in Construction Stage (2nd Phase in July 2019 based on S1.43).pdf |
| 7/22/2019 | 2193 | 2193 SMC4-LC-678 Updated Environmental Control Plan (2nd).pdf |
| 7/22/2019 | 2194 | 2194 SMC4-MS-259 Method Statement of Structure Excavation from P46-P56.pdf |
| 7/22/2019 | 2195 | 2195 SMC4-MS-260 MS of Temporary Facilities Arrangment on Site at P15-P20.pdf |
| 7/24/2019 | 2196 | 2196 SMC4-WD-318 WD for Basement for Traffic Sign Board at P13.pdf |
| 7/24/2019 | 2197 | 2197 SMC4-WD-319 WD of General View & Girder Arrangement of Main Bridge & Ramp HQV-B( stage 8).pdf |
| 7/24/2019 | 2198 | 2198 SMC4-LC-680 Report on the Result of P35 Pier Head Surface Repairing.pdf |
| 7/24/2019 | 2199 | 2199 SMC4-MS-262 MS of Steel Deck Panel Fabrication of Steel Bridge.pdf |
| 7/24/2019 | 2200 | 2200 SMC4-MS-261 Document of Relocation & Cutting Tree at Section A1-P16.pdf |
| 7/24/2019 | 2201 | 2201 SMC4-LC-681 Report on Mobilization of Welding Material.pdf |
| 7/24/2019 | 2202 | 2202 SMC4-MA-423 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P7-P10.pdf |
| 7/24/2019 | 2203 | 2203 SMC4-MA-421 Report on Frequency Test of Shape Steel Material of Nippon Steel & Sumitomo Metal Corp. (1st).pdf |
| 7/24/2019 | 2204 | 2204 SMC4-MA-422 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column & Pier Head of P38(8th)P39,P40(7th), P32(13rd).pdf |
| 7/24/2019 | 2205 | 2205 SMC4-MA-424 Report on Frequency Test of Welding Material-Welding Wire H14 for Steel Bridge (2nd).pdf |
| 7/24/2019 | 2206 | 2206 SMC4-LC-682 Result of Ultrasonic Test of CIP Concrete Piles at P56.pdf |
| 7/24/2019 | 2207 | 2207 SMC4-LC-683 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P35.pdf |
| 7/24/2019 | 2208 | 2208 SMC4-LC-684 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P57.pdf |
| 7/25/2019 | 2209 | 2209 SMC4-LC-685 Additional Supervision Cost of Engineer's Staff (May 2019).pdf |
| 7/25/2019 | 2210 | 2210 SMC4-WD-320 WD of Super T Girder Span S8 (P7-P8).pdf |
| 7/25/2019 | 2211 | 2211 SMC4-WD-321 WD of Structure Excavation for Section A1, P7-P10.pdf |
| 7/25/2019 | 2212 | 2212 SMC4-WD-322 WD of General Layout of Parapet (P19-P61).pdf |
| 7/25/2019 | 2213 | 2213 SMC4-MS-263 MD for Erection of Super T Girder at Spans S36 (P35-P36).pdf |
| 7/25/2019 | 2214 | 2214 SMC4-MS-264 MS of Diaphragm Construction from Span S32 - Span S36.pdf |
| 7/25/2019 | 2215 | 2215 SMC4-LC-687 Result of Ultrasonic Test of CIP Concrete Pile at P55.pdf |
| 7/25/2019 | 2216 | 2216 SMC4-MA-425 Accelerated Weather Resistance Testing Result at 1500Hours of Fluorex Finish Top Coat (Greyt RAL 7035) of Hai Phong Paint JSC.pdf |
| 7/25/2019 | 2217 | 2217 SMC4-LC-686 Notice for Leave for Our Key Personnel (Project Manager).pdf |
| 7/26/2019 | 2218 | 2218 2667-PMUTL-DHDA1 Approval of Variation Order No. VO-HRR3-PK1-001A for Additional Tests on CIP Concrete Piles.pdf |
| 7/26/2019 | 2219 | 2219 SMC4-LC-688 Proposal for Approval of the Contractor's Programme (Rev.2).pdf |
| 7/27/2019 | 2220 | 2220 SMC4-MS-265 MS of Pile Cap from P46-P56.pdf |
| 7/27/2019 | 2221 | 2221 SMC4-MS-266 Method Drawing for Erection of Super T Girder at S24(P23-P24).pdf |
| 7/27/2019 | 2222 | 2222 SMC4-MS-267 Calculation of Tendon Cable Elongation for Pier Head P15.pdf |
| 7/27/2019 | 2223 | 2223 SMC4-MS-268 MS of Temporary Facilities Arrangement on Site from Abutment A1-P7.pdf |
| 7/27/2019 | 2224 | 2224 SMC4-WD-323 WD of Column & Pier Head of Pier P43.pdf |
| 7/27/2019 | 2225 | 2225 SMC4-LC-689 Submission of Weekly Report No.61.pdf |
| 7/27/2019 | 2226 | 2226 SMC4-LC-690 Submission of Weekly Report No.62.pdf |
| 7/27/2019 | 2227 | 2227 SMC4-LC-691 Response to the Engineer's Comment Regarding Updated of Construction Method of Pier Head Type based on Actual Site Condition (2nd).pdf |
| 7/29/2019 | 2228 | 2228 SMC4-AD-71 AD of CIP Concrete Pile D1.2m of P32C.pdf |
| 7/29/2019 | 2229 | 2229 SMC4-LC-692 Capacity Profile of Nhat Son Quang Co.Ltd for Protection & Relocation of Existing Utilities.pdf |
| 7/29/2019 | 2230 | 2230 SMC4-WD-324 WD of the Elevation & Thickness of Deck Slab at Span S30 ( P29-P30).pdf |
| 8/8/2019 | 2231 | 2231 SMC4-LC-693 Re-Checking Result of Girders of S24, S16 & Replacement of Pre Tensioning Pre Stressed Super T Girders of Span S24 by Girders of the Span S16 for Erection.pdf |
| 7/30/2019 | 2232 | 2232 SMC4-LC-694 Notice of Environmental Monitoring Schedule in August 2019 at Construction Phase.pdf |
| 7/31/2019 | 2233 | 2233 SMC4-MS-269 Calculation of Tendon Cable Elongation for Pier Head at P40.pdf |
| 7/31/2019 | 2234 | 2234 SMC4-MS-270 Method Drawing for Erection of Super T Girder at S27(P26-P27) & S26( P25-P26).pdf |
| 7/30/2019 | 2235 | 2235 Minutes of Meeting dated 4 July ,2019.pdf |
| 7/31/2019 | 2236 | 2236 SMC4-MS-271 MS for Lower Part of Pier Head from P11-P13.pdf |
| 7/31/2019 | 2237 | 2237 SMC4-WD-325 WD the Elevation & Thickness of Deck Slab at Span S21(P20-P21).pdf |
| 7/31/2019 | 2238 | 2238 SMC4-MA-426 Report on Frequency Test of Epoxy Coated PC Strand (6th) of Zhemao Science & Technology Co.LTD Used for Pier Head.pdf |
| 7/31/2019 | 2239 | 2239 SMC4-MA-427 Report on Frequency Test of Epoxy Coated PC (7th) & Anchorage (4th) of Zhemao Science & Technology Co.LTD used for Pier Head.pdf |
| 7/31/2019 | 2240 | 2240 SMC4-AD-72 AD of Pre Tensioning Pre Stressed Super T Girder Span 24 ( P23-P24).pdf |
| 7/31/2019 | 2241 | 2241 SMC4-MA-425A Report on Frequency Test of Welding Material Welding Wire SF71 (3rd).pdf |
| 7/31/2019 | 2242 | 2242 SMC4-MA-425B Report on Frequency Test of Welding Material Welding Wire SF71 (2nd).pdf |
| 7/31/2019 | 2243 | 2243 SMC4-MA-428 Trial Mixed Result of Concrete Class B1,C1,C3,C4,D,G &Y at Asean BP( New location).pdf |
| 8/3/2019 | 2244 | 2244 SMC4-MA-429 Characteristic Strength of Concrete Class C of Transmeco BP- Report No.5( fr 14May-18Jun2019).pdf |
| 8/1/2019 | 2245 | 2245 SMC4-LC-695 Cost Estimate for Protection & Relocation of Existing Utilities.pdf |
| 8/1/2019 | 2246 | 2246 SMC4-LC-696 Acceptance Substructure Construction Stage & Transfer to Construction Superstructure Work for P24.pdf |
| 8/1/2019 | 2247 | 2247 SMC4-LC-697 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work at P32C.pdf |
| 8/1/2019 | 2248 | 2248 SMC4-LC-698 Additional Information of Subcontractors Engaged in the Project.pdf |
| 8/7/2019 | 2249 | 2249 SMC4-MA-425C Report on Test Result of Shear Stud for Steel Bridge.pdf |
| 8/1/2019 | 2250 | 2250 SMC4-MS-272 Supplement Method Drawing for Erection of Super T Girder at S36 (P35-P36).pdf |
| 8/3/2019 | 2251 | 2251 SMC4-MA-430 Material Standards for Bolt, Nut & Washer Used for Deck Slab.pdf |
| 8/3/2019 | 2252 | 2252 SMC4-LC-699 Report on Environmennt Monitoring in Construction Stage (3rd Phase in July based on S1.43)).pdf |
| 8/3/2019 | 2253 | 2253 SMC4-MA-431 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap,Pier Column & Pier Head of P32(14th) & Diaphragm of Span S33-S36.pdf |
| 8/3/2019 | 2254 | 2254 SMC4-LC-700 Submission of Construction Schedule of Aug 2019.pdf |
| 8/3/2019 | 2255 | 2255 SMC4-RP-93 Report on Excavation for Survey of Underground Utilities at P50 (2nd).pdf |
| 8/3/2019 | 2256 | 2256 SMC4-MA-429A Report on Frequency Test of Epoxy Coated PC Strand (8th) of Zhemao S&T Co.LTD used for Pier Head.pdf |
| 8/3/2019 | 2257 | 2257 SMC4-MA-429B Report on Frequency Test of PC Strand for Super T Girder (28th).pdf |
| 8/3/2019 | 2258 | 2258 SMC4-MA-432 Report on Frequency Test of Reinforcing Steel VGS for CIP Pile P50 (1st), P23-P28(2nd), Deck Plate P23-P28 (1st).pdf |
| 8/3/2019 | 2259 | 2259 SMC4-MA-433 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column of P46, P47(1st).pdf |
| 8/3/2019 | 2260 | 2260 SMC4-MA-434 Submission of Manufacturer & Supplier of Bridge Expansion Joints.pdf |
| 8/3/2019 | 2261 | 2261 SMC4-WD-326 WD of Super T Girder Span S7 ( A1-P7).pdf |
| 8/5/2019 | 2262 | 2262 SMC4-WD-327 WD of Elastomeric Bearing (A1-P15).pdf |
| 8/5/2019 | 2263 | 2263 SMC4-WD-328 WD of Deck Slab Spans 23, 24, 27, 28.pdf |
| 8/5/2019 | 2264 | 2264 SMC4-MS-273 MS for Lower Part of Pier Head P57-P58.pdf |
| 8/5/2019 | 2265 | 2265 SMC4-MS-274 MS of Pier Column P46-P56.pdf |
| 8/6/2019 | 2266 | 2266 SMC4-MS-275 MS of Traffic Control for Public Road at Section A1-P24- Volumn VII- Ajusted Arrangement Traffic Control at Section A1-P24.pdf |
| 8/5/2019 | 2267 | 2267 SMC4-MA-435 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap,Pier Column & Pier Head of P38(9th),P39-P40 (8th)& Diaphragm of Span P36-P40 (1st).pdf |
| 8/5/2019 | 2268 | 2268 SMC4-LC-702 Weekly Report No.63.pdf |
| 8/5/2019 | 2269 | 2269 SMC4-LC-701 Changing Thickness of Bituminous Membrane on Anchor Block of P16, P19.pdf |
| 8/7/2019 | 2270 | 2270 SMC4-LC-703 Proposal for Approval of Manpower Mobilization Document for Deck Slab Construction Work under Scope of Co. 414.pdf |
| 8/7/2019 | 2271 | 2271 SMC4-LC-704 Proposal for Approval Manpower Mobilization Document for Super T Girder Fabrication under Scope of Co.414.pdf |
| 8/7/2019 | 2272 | 2272 SMC4-LC-705 Proposal for Approval of Asphalt Concrete BP of 656 Co.LTD.pdf |
| 8/7/2019 | 2273 | 2273 SMC4-MS-276 MS of Steel Deck Panel Fabrication of Steel Bridge (2nd).pdf |
| 8/7/2019 | 2274 | 2274 SMC4-MS-277 Adjusted Plan for Reconnect Culvert Pipe D1250 of Ministry of Police Public (4th).pdf |
| 8/7/2019 | 2275 | 2275 SMC4-MA-425D Test Result of Bolt Material for Steel Bridge S10T M22x100 ( including Nut & Washer).pdf |
| 8/8/2019 | 2276 | 2276 SMC4-MA-436 Report on Frequency Test of Material for Cement Concrete of Asean BP (18th and 19th).pdf |
| 8/7/2019 | 2277 | 2277 SMC4-WD-329 WD of Details of Steel Girder Segment 12 (1st).pdf |
| 8/8/2019 | 2278 | 2278 SMC4-LC-706 Top Elevation of Bearing Pad in Accordance with Actual Camber of Super T Girder at Span S16, S26, S27.pdf |
| 8/8/2019 | 2279 | 2279 SMC4-LC-707 Result of Ultrasonic Test of CIP Concrete Pile at P54.pdf |
| 8/8/2019 | 2280 | 2280 SMC4-MA-435A Testing Result of Welding Procedure of Stud Shear Connector.pdf |
| 8/8/2019 | 2281 | 2281 SMC4-MA-437 Accelerated Weather Resistance Testing Result at 2000 Hours of Fluorex Finish Top Coat( Grey RAL 7035) of Hai Phong Paint JSC.pdf |
| 8/8/2019 | 2282 | 2282 SMC4-WD-330 WD of Substruture-Center Column &Lower Part of Pier P32C (2nd).pdf |
| 8/8/2019 | 2283 | 2283 SMC4-MA-439 Characteristic Strength for Concrete Class Y of Transmeco BP -RP No.5(4Jun-21Jun2019).pdf |
| 8/7/2019 | 2284 | 2284 2811 PMUTL-DA1 Inspection and Verification of Management of construction solid waste.pdf |
| 8/8/2019 | 2285 | 2285 SMC4-AD-73 As-Built Drawing of Pre Tensioning Pre Stressed Super T Girder of Span 26 (P25-P26).pdf |
| 8/8/2019 | 2286 | 2286 SMC4-AD-74 As-Built Drawing of Pre Tensioning Pre Stressed Super T Girder Span 25 (P24-P25).pdf |
| 8/8/2019 | 2287 | 2287 SMC4-AD-75 As-Built Drawing of Pre Tensioning Pre Stressed Super T Girder Span 27 (P26-P27).pdf |
| 8/8/2019 | 2288 | 2288 SMC4-LC-708 Weekly Report No.64.pdf |
| 8/8/2019 | 2289 | 2289 SMC4-LC-709 Monthly Report No.15.pdf |
| 8/8/2019 | 2290 | 2290 SMC4-MA-438 Trial Mix Result of Concrete Class A(Ver.2-Cement 525kg), C1, C3, C4& Class Y at Viet Tiep BP (New Location).pdf |
| 8/10/2019 | 2291 | 2291 SMC4-WD-331 WD of CIP Concrete Pile for P44.pdf |
| 8/10/2019 | 2292 | 2292 SMC4-WD-332 WD of CIP Concrete Pile for P45 (2nd).pdf |
| 8/10/2019 | 2293 | 2293 SMC4-LC-711 Report on Steel Bridge Processing Work & Proposal Drilling Hole for Botton Splice Plates before Pre Assembly.pdf |
| 8/10/2019 | 2294 | 2294 SMC4-LC-710 Engineer's Confirmation for Safety & Environment Satisfaction (01Jul to 31Jul2019).pdf |
| 8/10/2019 | 2295 | 2295 SMC4-MA-441 Test Result of Jack, Anchorage & Synchronous Experiment of Jack, PC Strand, Anchoage for Construction Super T Girder(5th).pdf |
| 8/10/2019 | 2296 | 2296 SMC4-MA-442 Report on Frequency Test of Cement, Coarse Aggregate for Class A at Viet Tiep BP Plant ( New Location) (8th) & Updated Testing Result on Cement for Cement Concrete at Viet Tiep BP (6th).pdf |
| 8/10/2019 | 2297 | 2297 SMC4-MA-434A Report on Frequency Test of Reinforcing Steel VGS forCIP Concrete Pile of Section A1-P10 (2nd).pdf |
| 8/13/2019 | 2298 | 2298 SMC4-MA-443 Characteristic Strength for Concrete Class B of Transmeco BP Plant-RP No.1(fr 14Jan to 01Jun2019).pdf |
| 8/10/2019 | 2299 | 2299 SMC4-MA-444 Cement Concrete at Transmeco BP (33rd, 34th) & Update Testing Results on Cement for CC at Transmeco BP( 28th,29th&31th).pdf |
| 8/10/2019 | 2300 | 2300 SMC4-MA-445 Report on Frequency Test of Reinforcing Steel VIS Steel Bar for Super T Girder of Span S11, S12.pdf |
| 8/10/2019 | 2301 | 2301 SMC4-MC-16 Interim Payment Certificate No.13 ( Period 01Jul to 31Jul2019).pdf |
| 8/12/2019 | 2302 | 2302 SMC4-MA-440 Report on Frequency Test of Reinforcing Steel - VGS for Pier Column & Pier Head of Pier P11, P12, P13.pdf |
| 8/12/2019 | 2303 | 2303 SMC4-MA-446 Report on Frequency Test of Reinforcing Steel - VGS for Pile cap, Pier Column & Pier Head of Pier P53, P54, P55, P56 (1st).pdf |
| 8/12/2019 | 2304 | 2304 SMC4-MA-447 Submision of the Characteristic Strength for Concrete Class A of Viet Tiep BP (New Location) - Report No.1 (from 11Jun to 02Jul2019).pdf |
| 8/12/2019 | 2305 | 2305 SMC4-RP-94 Topographic Survey Report at Section from Km2+160 to Km2+220.pdf |
| 8/12/2019 | 2306 | 2306 SMC4-RP-95 Report on Excavation for Survey of Underground Utilities at P48, P49 (2nd).pdf |
| 9/10/2019 | 2307 | 2307 SMC4-RP-96 Report on Excavation for Survey of Underground Utilities at P41R, P42R.pdf |
| 8/12/2019 | 2308 | 2308 SMC4-WD-333 Working Drawing the Elevation & Thickness of Deck Slab at Span S22(P21-P22), S29(P28-P29).pdf |
| 8/12/2019 | 2309 | 2309 SMC4-WD-334 Working Drawings of General Dimension of Steel Girder (1st Revision).pdf |
| 8/12/2019 | 2310 | 2310 SMC4-WD-335 Working Drawings of Painting of Exterior Super T Girder from Spans 10-16 and 20-38 (1st Revision).pdf |
| 8/12/2019 | 2311 | 2311 SMC4-WD-336 Working Drawings of Substructure - Pier P51 (2nd).pdf |
| 8/12/2019 | 2312 | 2312 SMC4-WD-337 Working Drawings of Substructure - Pier P52 (2nd).pdf |
| 8/12/2019 | 2313 | 2313 SMC4-WD-338 Working Drawings of Substructure - Pier P54 (2nd).pdf |
| 8/12/2019 | 2314 | 2314 SMC4-LC-714 The Sequence for the Construction of Superstructure.pdf |
| 8/12/2019 | 2315 | 2315 SMC4-MA-420A Notice of Vietnam Germany Steel Transfer for Bored Piles of Pier P48,P49 will be Used for Bored Piles of Pier 50.pdf |
| 8/13/2019 | 2316 | 2316 SMC4-MA-448 Removal of Welding Wire SF71 Lot Numer MF9747E1 (15255 kg) out of Factory of Thanh Long JSC.pdf |
| 9/7/2019 | 2317 | 2317 SMC4-WD-340 WD for General Layout of Traffic Sign for Urban Road (2nd).pdf |
| 8/23/2019 | 2318 | 2318 SMC4-WD-339 WD for General Arrangement of Traffic Sign for Expressway from Km0+130 - Km0+904.49 (2nd).pdf |
| 8/13/2019 | 2319 | 2319 SMC4-LC-715 Change Position of Steel Bar U160x56x5.2 of Anti Glare Fence on the Concrete Parapet.pdf |
| 8/13/2019 | 2320 | 2320 SMC4-LC-712 Additional Manpower Mobilization Document for Super T Girder Fabrication under Scope of Co.414.pdf |
| 8/13/2019 | 2321 | 2321 SMC4-LC-713 Additional Mobilization for Additional Welders for Steel Bridge of Subcontractor Thanh Long Group JSC (6th).pdf |
| 8/14/2019 | 2322 | 2322 SMC4-LC-716 Result of Ultrasonic Test of CIP Concrete Piles at P46.pdf |
| 8/14/2019 | 2323 | 2323 SMC4-LC-717 Result of Ultrasonic Test of CIP Concrete Piles at P52.pdf |
| 8/14/2019 | 2324 | 2324 SMC4-WD-341 WD of Substructure - Pier Head P46(1st).pdf |
| 8/14/2019 | 2325 | 2325 SMC4-WD-342 WD of Painting of Exterior Super T Girder from Spans S7-S9 & S39-S61(1st).pdf |
| 8/14/2019 | 2326 | 2326 SMC4-WD-343 WD of Substructure - Pier Head P47 (1st).pdf |
| 8/14/2019 | 2327 | 2327 SMC4-WD-344 WD of Substructure - Pier Head P58 (1st).pdf |
| 8/14/2019 | 2328 | 2328 SMC4-WD-345 WD of Substructure - Pier Head P59 (1st).pdf |
| 8/14/2019 | 2329 | 2329 SMC4-WD-346 WD of Substructure -Pier Head P60 (1st).pdf |
| 8/14/2019 | 2330 | 2330 SMC4-AD-76 AD of CIP Concrete Piling D1.2m of P46.pdf |
| 8/14/2019 | 2331 | 2331 SMC4-MS-278 Report for Loading Test of Ground at Pre-Assembly Area of Thanh Long Factory.pdf |
| 8/14/2019 | 2332 | 2332 SMC4-RP-97 Report on Excavation for Survey of Underground Utilities at P7, P8.pdf |
| 8/15/2019 | 2333 | 2333 SMC4-LC-716 Withdrawal of the letter SMC4-MA-0434A dated 3 Aug 2019.pdf |
| 8/15/2019 | 2334 | 2334 SMC4-MA-449 Report on Frequency Test of Reinforcing Steel-VGS for Pile Cap, Pier Column & Pier Head of P46-P49(2nd), CIP Concrete Pile of P44,P45 (1st) & P48,P49(3rd), Link Slab of P23-P28.pdf |
| 8/15/2019 | 2335 | 2335 SMC4-LC-717A Result of Ultrasonic Test of CIP Concrete Piles at P47.pdf |
| 8/15/2019 | 2336 | 2336 SMC4-LC-718 Withdrawal of the letter SMC4-RP-0094 dated 10 Aug 2019.pdf |
| 8/15/2019 | 2337 | 2337 SMC4-MA-450 Notification of Transfer of VGS Used for Construction of CIP Concrete Piles at P50 for the Construction CIP Concrete Piles at P48, P49.pdf |
| 8/15/2019 | 2338 | 2338 SMC4-MA-451 Notification on Transferring of VGS Used for Construction of CIP Concrete Pile at P51-P54 (1st)(3rd) for CIP Concrete Piles P41-P43.pdf |
| 8/15/2019 | 2339 | 2339 SMC4-LC-719 Reply the Engineers Letter Regarding the Contractor's Programme (Rev.2).pdf |
| 8/15/2019 | 2340 | 2340 SMC4-WD-347 WD of Detail of Expansion Joint (for Main Bridge).pdf |
| 8/19/2019 | 2341 | 2341 SMC4-MS-277A MS for Construction of Pier Head & Outling of the Loading Test of Pier Head's Supporting System at P59-P60 & P14.pdf |
| 8/16/2019 | 2342 | 2342 SMC4-LC-720 Report on Installation of Safety Breakers for Protecting Electrical Accident.pdf |
| 8/16/2019 | 2343 | 2343 SMC4-LC-721 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work at P46.pdf |
| 8/15/2019 | 2344 | 2344 SMC4-LC-722 Additional Supervision Cost of Engineer's Staff in June 2019.pdf |
| 8/15/2019 | 2345 | 2345 SMC4-LC-723 Withdrawal of the Letter LC-0719 dated 14Aug2019.pdf |
| 8/15/2019 | 2346 | 2346 SMC4-MS-279 Storing Plan for Super T Girder 34.3m Type at Fabrication Yard of Group 2.pdf |
| 8/16/2019 | 2347 | 2347 SMC4-LC-724 Claim for the Extention of Time for Completion & Proposal for Revised Overall Construction Schedule (Rev.2).pdf |
| 8/15/2019 | 2348 | 2348 SMC4-WD-348 WD of Superstructure - Deck Slab of Span S34, S35 & Link Slab at P33-P35(2nd).pdf |
| 8/15/2019 | 2349 | 2349 SMC4-WD-349 WD of Substructure - Pier Head P55 (1st Rev).pdf |
| 8/15/2019 | 2350 | 2350 SMC4-WD-350 WD of DSubstructure- Pier P10 (1st).pdf |
| 8/15/2019 | 2351 | 2351 SMC4-WD-351 WD of Substructure - Pier Head P57 (1st Rev).pdf |
| 8/15/2019 | 2352 | 2352 SMC4-WD-352 WD of Substructure - Pier Head P56 (1st Rev).pdf |
| 8/16/2019 | 2353 | 2353 SMC4-LC-726 Result of Tip Contact Checking Test of CIP Concrete Pile C6-P54.pdf |
| 8/16/2019 | 2354 | 2354 SMC4-LC-725 Report on Environment Monitoring in Construction Stage (1st Phase in Aug 2019 based on S1.43).pdf |
| 8/16/2019 | 2355 | 2355 SMC4-RP-98 Topographic Survey Report at Section from Km2+150-Km2+225.pdf |
| 8/17/2019 | 2356 | 2356 SMC4-LC-729 Withdrawal of the Letter SMC4-MA-0444-19 dated 9Aug19.pdf |
| 8/19/2019 | 2357 | 2357 SMC4-LC-727 Acceptance of Sub Structure Construction Stage & Transfer to Construction of SuperStructure Work for P26.pdf |
| 8/19/2019 | 2358 | 2358 SMC4-LC-728 Submission of Weekly Report No.65.pdf |
| 8/19/2019 | 2359 | 2359 SMC4-LC-730 Result of Ultrasonic Test of CIP Concrete Piles at P51.pdf |
| 8/19/2019 | 2360 | 2360 SMC4-WD-353 WD of Addition CIP Concrete Pile of Pier P43C (1st).pdf |
| 8/19/2019 | 2361 | 2361 SMC4-MS-280 Supplement the Method Drawing for Erection of Super T Girder at Spans S25(P24-P25) & S26(P25-P26).pdf |
| 8/19/2019 | 2362 | 2362 SMC4-MA-452 Report on Frequency Test of Reinforcing Steel VGS for Link Slab& Pile Cap Pier Column of P53-P56.pdf |
| 8/19/2019 | 2363 | 2363 SMC4-MA-453 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of A1-P10.pdf |
| 8/19/2019 | 2364 | 2364 SMC4-MA-454 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column Pier Head of P50-P52 & Deck Slab S33-S36.pdf |
| 8/19/2019 | 2365 | 2365 SMC4-MA-455 Report on Frequency Test of Reinforcing Steel VGS for Super T Girder of Span S40, S41.pdf |
| 8/19/2019 | 2366 | 2366 SMC4-MA-456 Report on Frequency Test of Reinforcing Steel VGS for Concrete Pile of Section A1-P10,Pile Cap, Pier Column Pier Head P14,Link Slab at P21,P22.pdf |
| 8/19/2019 | 2367 | 2367 SMC4-MA-457 Report of Frequency Test of Reinforcing Steel VGS for Pile Cap,Pier Column of P46, 47.pdf |
| 8/19/2019 | 2368 | 2368 SMC4-AD-77 AD of CIP Concrete Pilling S1.2m off Pier P56.pdf |
| 8/19/2019 | 2369 | 2369 SMC4-MA-399A Report on Frequency Test of Elastomeric Bearing Manufactured by Kawakin and supplied by THQ (2nd).pdf |
| 8/19/2019 | 2370 | 2370 SMC4-MA-425E Report on Frequency Test of Reinforcing Steel VGS for CIP Crete Pile of Section A1-P10 (2nd).pdf |
| 8/19/2019 | 2371 | 2371 SMC4-MA-447A Report on Frequency Test of Elastomeric Bearing Manufactured by Kawakin & Supplied by THQ (3rd).pdf |
| 8/19/2019 | 2372 | 2372 SMC4-MA-458 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile P41-P43.pdf |
| 8/19/2019 | 2373 | 2373 SMC4-MA-459 Mix Proportion for Trial Mix Class C2 at Viet Tiep BP & Transmeco BP.pdf |
| 8/19/2019 | 2374 | 2374 SMC4-WD-354 WD of Superstructure - Deck Slab for Spans S36-S37 (1st).pdf |
| 8/20/2019 | 2375 | 2375 SMC4-LC-732 Acceptance of CIP Concrete Pile Foundation Construction Stage & Tranfer to Construction of Substructure Work for P56.pdf |
| 8/21/2019 | 2376 | 2376 SMC4-RP-99 Report on Loading Test of Pier Head's Supporting System at P59.pdf |
| 8/21/2019 | 2377 | 2377 SMC4-RP-100 Report on Loading Test of Pier Head's Supporting System at P38.pdf |
| 8/21/2019 | 2378 | 2378 SMC4-LC-733 Changing Rebar of Deck Slab in the Area Near the Expansion Joint.pdf |
| 8/21/2019 | 2379 | 2379 SMC4-LC-734 Manpower Mobilization Document for Deck Slab Construction Work Under Scope of Co.423.pdf |
| 8/22/2019 | 2380 | 2380 SMC4-MS-281 Method Statement of Pier Head from P11-P13.pdf |
| 8/21/2019 | 2381 | 2381 SMC4-MS-282 Outline for Loading Test of Pier Head's Supporting System at P12, P13.pdf |
| 8/21/2019 | 2382 | 2382 SMC4-WD-355 WD of Superstructure - Deck Slab for Spans S23, S24, S27, S28 (2nd).pdf |
| 8/21/2019 | 2383 | 2383 SMC4-WD-356 WD of Substructure - Pier P49 (2nd).pdf |
| 8/21/2019 | 2384 | 2384 SMC4-WD-357 WD of Substructure - Pier P48 (2nd).pdf |
| 8/23/2019 | 2385 | 2385 SMC4-MA-460 Report of Frequency Test of Epoxy Coated PC Strand (9th) of Zhemao Co.Ltd used for Pier Head.pdf |
| 8/23/2019 | 2386 | 2386 SMC4-WD-359 WD of Substructure Pier P53 (2nd).pdf |
| 8/23/2019 | 2387 | 2387 SMC4-WD-358 WD of Substructure Pier P50 (2nd).pdf |
| 8/22/2019 | 2388 | 2388 SMC4-MA-461 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P44,P45 & P48,P49 & Deck Slab of P23-P28.pdf |
| 8/22/2019 | 2389 | 2389 SMC4-MA-462 Report of Frequency Test of Reinforcing Steel VGS for Super T Girder of Span S47, S48.pdf |
| 8/22/2019 | 2390 | 2390 SMC4-LC-735 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P25.pdf |
| 8/23/2019 | 2391 | 2391 SMC4-LC-736 Result of Tip Contact Checking Test of CIP Concrete Pile C3-P51.pdf |
| 8/23/2019 | 2392 | 2392 SMC4-MA-464 Report on Frequency Test of Cement, Coarse Aggregate, Fine Aggregate, Admixture & Water of Transmeco BP 33rd-37th, Updated Testing Result 28th,29th,31th....pdf |
| 8/23/2019 | 2393 | 2393 SMC4-MA-463 Material Source & Job-Mix Formula of Dense Asphalt Concrete C19 at 703 Asphalt BP of PK2 used for Asphalt Concrete BP of 656 CoLtd of PK1.pdf |
| 8/23/2019 | 2394 | 2394 SMC4-MA-460A Report on Frequency Test of PC Strand of Super T Girder (29th).pdf |
| 8/23/2019 | 2395 | 2395 SMC4-LC-737 Submission of Weekly Report No.66.pdf |
| 8/23/2019 | 2396 | 2396 SMC4-MA- 465 Result on Test Result of Pot Bearing Manufactured by Kwang Won Co.,Ltd & Supplied by Transport Materials Equipment JSC.pdf |
| 8/26/2019 | 2397 | 2397 SMC4-MA-466 Report on Frequency Test of VGS Pile Cap, Pier Column Pier Head of P50, P52, P32,Pier Head of P32, Deck Slab S33-36.pdf |
| 8/26/2019 | 2398 | 2398 SMC4-AD-78 AD of CIP Concrete Piling D1.2m of P47.pdf |
| 8/26/2019 | 2399 | 2399 SMC4-MA-468 Report on Frequency Test of Cement, Coarse Aggregate for Class A, Coarse cement concrete of Viet Tiep.pdf |
| 8/26/2019 | 2400 | 2400 SMC4-MS-284 MS of Structure Excavation from A1-P10.pdf |
| 8/26/2019 | 2401 | 2401 SMC4-MS-285 Calculation for Pre-Stressing of Super T Girder 34.3m of Group 2 Co.407.pdf |
| 9/10/2019 | 2402 | 2402 SMC4-RP-101 Report on Excavation for Survey of Underground Ultilites at P43R.pdf |
| 8/26/2019 | 2403 | 2403 SMC4-WD-360 WD of the Elevation & Thickness of Deck Slab S23(P22-P23), S28(P27-P28).pdf |
| 8/26/2019 | 2404 | 2404 SMC4-WD-361 WD of Substructure CIP Concrete Pile for P32R, P32L (2nd).pdf |
| 8/26/2019 | 2405 | 2405 SMC4-WD-362 WD of Substructure - Pile Cap of Abutment A1.pdf |
| 8/26/2019 | 2406 | 2406 SMC4-LC-738 Report on Environment Monitoring in Construction Stage (2nd Phase in Aug 2019 based on S1.43).pdf |
| 8/26/2019 | 2407 | 2407 SMC4-MA-467 Report on Frequency Test of PC Strand for Super T Girder (30th).pdf |
| 8/26/2019 | 2408 | 2408 SMC4-MS-283 MS of A1 Abutment's Pile Cap.pdf |
| 8/26/2019 | 2409 | 2409 SMC4-LC-739 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P47.pdf |
| 8/27/2019 | 2410 | 2410 SMC4-AD-79 AD of CIP Concrete Pile D1.2m of P54.pdf |
| 8/27/2019 | 2411 | 2411 SMC4-MA-469 Report on Frequency Test of Reiforcing Steel VGS for Pile Cap, Pier Column of P54.pdf |
| 8/27/2019 | 2412 | 2412 SMC4-MA-470 Report on Frequency Test of Reinforcing Steel VGS for Link Slab P28, P29, Deck Slab of S29.pdf |
| 8/27/2019 | 2413 | 2413 SMC4-MA-471 Notice on Transferring a Part of VGS Used for Bored Pile of P50-P52 to Bored Pile of P47.pdf |
| 8/29/2019 | 2414 | 2414 SMC4-RP-102 Report of Excavation for Survey of Underground Utilities at P43L.pdf |
| 8/29/2019 | 2415 | 2415 SMC4-WD-363 WD of Relocation of Project Information Sign to P17-P18.pdf |
| 8/29/2019 | 2416 | 2416 SMC4-WD-364 WD of Pile Cap of P43 (2nd).pdf |
| 8/29/2019 | 2417 | 2417 SMC4-WD-366 WD of Superstructure- Deck Slab for Span S20 & Link Slab at Pier P20 (1st).pdf |
| 8/29/2019 | 2418 | 2418 SMC4-WD-365 WD of Pot Bearing at Piers P16 & P19 (1st).pdf |
| 8/28/2019 | 2419 | 2419 SMC4-LC-740 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P54.pdf |
| 8/29/2019 | 2420 | 2420 SMC4-LC-741 Notification on Persons in Charge of Traffic Control P15, P16, P24.pdf |
| 8/30/2019 | 2421 | 2421 SMC4-LC-742 Reply to the Engineer's Letter No.HCRR RE1-1510-1.29 Regarding Construction Progress for Main Structure Items-August 2019.pdf |
| 8/30/2019 | 2422 | 2422 SMC4-LC-743 Result of Ultrasonic Test of Cast in Place Concrete Piles at P9.pdf |
| 8/30/2019 | 2423 | 2423 SMC4-LC-744 Result of Ultrasonic Test of Cast in Place Concrete Piles at P10.pdf |
| 8/30/2019 | 2424 | 2424 SMC4-LC-745 Notice of Environmental Monitoring Schedule in Sep2019 at Construction Phase.pdf |
| 8/30/2019 | 2425 | 2425 SMC4-LC-746 Manpower Mobilization Document for Deck Slab Construction Work from P31 to P36 under Scope of 422 Co..pdf |
| 8/30/2019 | 2426 | 2426 SMC4-LC-747 Manpower Mobilization Document of Subcontractor Vietbuilt Construction & Trading JSC for Safety Work.pdf |
| 8/30/2019 | 2427 | 2427 SMC4-MS-103 Report on Excavation for Survey of Underground Ultilities at P44,P45.pdf |
| 8/30/2019 | 2428 | 2428 SMC4-MS-286 Calculation of Tendon Cable Elongation for Pier Head at P38.pdf |
| 8/30/2019 | 2429 | 2429 SMC4-MA-472 Capacity Profile of Manufacturer and Supplier for Bolts, Nut and Stud Bolt for Steel Bridge.pdf |
| 8/30/2019 | 2430 | 2430 SMC4-LT-26 Capacity Profile of Laboratory LAS-XD 1133 of Institute for Building Material.pdf |
| 8/30/2019 | 2431 | 2431 SMC4-AD-80 AD of Cast in Place Concrete Piling D1.2m of Pier P52.pdf |
| 8/31/2019 | 2432 | 2432 SMC4-MA-474 Frequency Test of Reinforcing Steel VGS for Bore Pile A1, P7-P10, Pile Cap, Pier Column, Pier Head of P9-P13.pdf |
| 8/31/2019 | 2433 | 2433 SMC4-LC-739A Report on Casting Concrete Phenomenon of CIP Concrete Pilling at No.9 P49.pdf |
| 8/31/2019 | 2434 | 2434 SMC4-MA-473 Report on Frequency Test of Epoxy Coated PC Strand (10th) of Zhemao S & T Co.Ltd used for Pier Head.pdf |
| 8/31/2019 | 2435 | 2435 SMC4-LC-748 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P52.pdf |
| 8/31/2019 | 2436 | 2436 SMC4-LC-749 Submission of Weekly Report No.67.pdf |
| 8/31/2019 | 2437 | 2437 SMC4-LC-750 Result of Tip Contact Checking Test of CIP Concrete Pile C4-P10.pdf |
| 8/31/2019 | 2438 | 2438 SMC4-MA-475 Report on Frequency Test of Welding Material -Welding Wire SF71 (4th).pdf |
| 8/31/2019 | 2439 | 2439 SMC4-MA-476 Report on Frequency Test of Posco Steel Plate Material (Filter Plate) for Steel Bridge.pdf |
| 8/31/2019 | 2440 | 2440 SMC4-MA-477 Capacity Profile of Manufacturer & Supplier of Drainage Pipe Material (2nd).pdf |
| 8/31/2019 | 2441 | 2441 SMC4-WD-367 WD of Superstructure- Deck Slab for Spans S38, 39 & Link Slab at P37-P39 (2nd).pdf |
| 8/31/2019 | 2442 | 2442 SMC4-WD-368 WD of Substructure Pier P9 (1st).pdf |
| 9/3/2019 | 2443 | 2443 SMC4-WD-369 WD of Backfill for Section A1-P10 (1st).pdf |
| 9/3/2019 | 2444 | 2444 SMC4-MA-478 Proposal for Approval of 703 Asphalt Batching Plant of PK2 used for PK1.pdf |
| 9/3/2019 | 2445 | 2445 SMC4-MA-479 Report on Frequency Test of Reinforcing Steel - VGS for Pile Cap, Pier Column of P46 & P47 , CIP Concrete Pile of P44, P45; Diaphgragm Span S25,S26,S27, Deck Slab S27.pdf |
| 9/4/2019 | 2446 | 2446 SMC4-MS-287 Calculation of Tendon Cable Elongation for Pier Head P59-P60.pdf |
| 9/3/2019 | 2447 | 2447 SMC4-MS-288 MS for Lower Part of Pier Head from P46-P56.pdf |
| 9/3/2019 | 2448 | 2448 SMC4-MS-289 MS for Construction of Pier Head & Outline of the Loading Test of Pier Head's Supporting System from P57 to P58.pdf |
| 9/3/2019 | 2449 | 2449 SMC4-MA-480 Using Cao Duong Quarry, Cao Duong Commune, Luong Son District, Hoa Binh Province Exploited by Hien Luong Mineral Exploitation & Processing Co., Ltd & Supplied by 28-10 Thang Long.pdf |
| 9/3/2019 | 2450 | 2450 SMC4-MA-481 Report on Frequency Test of Reinforcing Steel - VGS for Deck Slab & Link Slab S20-S23.pdf |
| 9/3/2019 | 2451 | 2451 SMC4-MS-290 Method Statement of Pile Cap from P7-P10.pdf |
| 9/4/2019 | 2452 | 2452 SMC4-WD-370 WD of General Layout of Parapet & Median Barrier for Main Bridge (2nd).pdf |
| 9/4/2019 | 2453 | 2453 SMC4-MA-482 Report on Frequency Test of Painting Material for Steel Bridge (1st) of Hai Phong Paint JSC for Steel Bridge.pdf |
| 9/4/2019 | 2454 | 2454 SMC4-AD-81 As Built Drawings of CIP Concrete Piling D1.2m of P55.pdf |
| 9/4/2019 | 2455 | 2455 SMC4-LC-751 Report on Environment Monitoring in Construction Stage (3rd Phase in Aug 2019 Based on S1.43).pdf |
| 9/6/2019 | 2456 | 2456 SMC4-LP-49 Report on Mobilization of Pile Machine T-Works to the Site & Placed at the U-Turn Point P15-P16 by the Contractor of Widening Project.pdf |
| 9/6/2019 | 2457 | 2457 SMC4-MA-483 Additional Capacity Profile of Asphalt Concrete BP of Co.656.pdf |
| 9/6/2019 | 2458 | 2458 SMC4-MA-484 Characteristic Strength for Concrete Class Y of Transmeco - RP No.6 (from 28Jun to 31Jul2019).pdf |
| 9/6/2019 | 2459 | 2459 SMC4-MA-485 Characteristic Strength for Concrete Class A of Viet Tiep BP - RP.2 (from 2Jul to 31Jul2019).pdf |
| 9/6/2019 | 2460 | 2460 SMC4-MA-486 Characteristic Strength for Concrete Class C of Transmeco BP- RP No.6 (from 22Jun to 31Jul2019).pdf |
| 9/6/2019 | 2461 | 2461 SMC4-LC-754 Break Down of Cost for Structure Excavation Item.pdf |
| 9/6/2019 | 2462 | 2462 SMC4-LC-753 Submission of Weekly Report No.68.pdf |
| 9/10/2019 | 2463 | 2463 SMC4-MS-291 Plan of Cutting & Pruning Tree from Abutment A1-P16.pdf |
| 9/6/2019 | 2464 | 2464 SMC4-LC-752 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P55.pdf |
| 9/6/2019 | 2465 | 2465 3123 PMUTL-DHDA1 Implementation of Conclusions by Minister Nguyen Van The.pdf |
| 9/7/2019 | 2466 | 2466 SMC4-WD-369A WD of Elevation& Thickness of Deck Slab at Span S35(P34-P35).pdf |
| 9/7/2019 | 2467 | 2467 SMC4-MA- 487 Report on Frequency Test of Reinforcing Steel VIS Bar for Super T Girder S47, S48.pdf |
| 9/9/2019 | 2468 | 2468 SMC4-MA-488 Frequency Test of Materials for Cement Concrete at Viet Tiep BP (11th& 12th) & Updated (8th).pdf |
| 9/9/2019 | 2469 | 2469 SMC4-MA-489 Report on Frequency Test of Manterial for Cement Concrete at Transmeco BP(38th & 39th).pdf |
| 9/10/2019 | 2470 | 2470 SMC4-MA-490 Report on Frequency Test of Materials for Cement Concrete at Asean BP(20th) & Updated (17th to 19th).pdf |
| 9/7/2019 | 2471 | 2471 SMC4-MA-491 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column,Pier Head of P39, Deck Slab S37-S41.pdf |
| 9/7/2019 | 2472 | 2472 SMC4-MA-492 Report on Frequency Test of Reinforcing Steel VGS for Pier Head of P57, P58.pdf |
| 9/7/2019 | 2473 | 2473 SMC4-MA-493 Report on Frequency Test of Reinforcing Steel VGS for Precast Panel of Super T Girder.pdf |
| 9/7/2019 | 2474 | 2474 SMC4-MS-290A MS of Deck Slab Construction from P32-P40.pdf |
| 9/7/2019 | 2475 | 2475 SMC4-MS-290B Method Drawing of Pier Column Construction at P55-P56.pdf |
| 9/7/2019 | 2476 | 2476 SMC4-LC-755 Cost Estimate for Protection & Relocation of Existing Utilities (2nd).pdf |
| 9/7/2019 | 2477 | 2477 SMC4-LC-756 Updated Quality Control Plan (3rd).pdf |
| 9/7/2019 | 2478 | 2478 SMC4-LC-757 Additional Supervision Cost of Engineers Staff (July 19).pdf |
| 9/7/2019 | 2479 | 2479 SMC4-MS-290C Method Drawing of Pier Head & Loading Test of Pier Head's Supporting System at P39.pdf |
| 9/9/2019 | 2480 | 2480 SMC4-LP-50 VAT Invoices for Interim Payment Certificate No.09 of PK1.pdf |
| 9/9/2019 | 2481 | 2481 SMC4-LP-51 VAT Invoices for Interim Payment Certificate No.10 of PK1.pdf |
| 9/9/2019 | 2482 | 2482 SMC4-LP-52 VAT Invoices for Interim Payment Certificate No.11 of PK1.pdf |
| 9/9/2019 | 2483 | 2483 SMC4-LP-53 VAT Invoices for Interim Payment Certificate No.12 PK1.pdf |
| 9/9/2019 | 2484 | 2484 SMC4-LC-758 Reply to the Engineer's Letter No ENG-PK1-0974-1.27 dated 31Aug2019 Regarding Reminder on Submission of Outstanding Document.pdf |
| 9/9/2019 | 2485 | 2485 SMC4-MS-292 Permission for Circulation of Vehicles to Transport Overlength Cargo on Road ( Transportation of Steel Girder & Steel Pier Head).pdf |
| 9/9/2019 | 2486 | 2486 SMC4-WD-371 WD of Superstructure-Deck Slab for Spans 40 & 41.pdf |
| 9/10/2019 | 2487 | 2487 SMC4-LC-759 Changing Method Statement of Drilling Hole Splice Plates before Pre Assembly.pdf |
| 9/11/2019 | 2488 | 2488 SMC4-RP-104 Report on Excavation for Survey Underground Utilities at P53.pdf |
| 9/10/2019 | 2489 | 2489 SMC4-AD-82 AD of CIP Concrete Pile D1.2m of P10.pdf |
| 9/10/2019 | 2490 | 2490 SMC4-LC-760 Construction Schedule of Sep. 2019.pdf |
| 9/10/2019 | 2491 | 2491 SMC4-LC-761 Result of Ultrasonic Test of CIP Concrete Pile at P42R.pdf |
| 9/10/2019 | 2492 | 2492 SMC4-LC-762 Result of Ultrasonic Test of CIP Concrete Pile at P41R.pdf |
| 9/14/2019 | 2493 | 2493 SMC4-MA-494 Report on Frequency Test of PC Trand for Super T Girder (31st).pdf |
| 9/14/2019 | 2494 | 2494 SMC4-MA-495 Report on Frequency Test of PC Strand for Super T Girder (32rd).pdf |
| 9/23/2019 | 2495 | 2495 SMC4-MA-496 Frequency Test of Posco Steel Plate for Steel Bridge (3rd).pdf |
| 9/23/2019 | 2496 | 2496 SMC4-MA-497 Frequency Test of Posco Steel Plate for Steel Bridge (4th).pdf |
| 9/10/2019 | 2497 | 2497 350 GM-SGTVT Invitation date 11.9.19.pdf |
| 9/12/2019 | 2498 | 2498 SMC4-MA-498 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap P48, P49 ( M& T 3Sep19).pdf |
| 9/12/2019 | 2499 | 2499 SMC4-MA-499 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head P50-P52,Pile Cap, Pier Column Pier Head P32, P9, P10(M&t 04Sep19).pdf |
| 9/12/2019 | 2500 | 2500 SMC4-MA-500 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column,Pier Head P14-Pile Cap, Pier Column, PierHead P44, P45 (M&T 07Sep19).pdf |
| 9/12/2019 | 2501 | 2501 SMC4-LT-27 Inspection Minutes of Lab LAS-XD 1133 of Institute for Building Material.pdf |
| 9/12/2019 | 2502 | 2502 SMC4-MS-293 MS of Erection for Pier Head P17, P18.pdf |
| 9/12/2019 | 2503 | 2503 SMC4-LC-766 Submission of Monthly Report No.16.pdf |
| 9/12/2019 | 2504 | 2504 SMC4-LC-765 Engineer's Confirmation for Safety & Environment Satisfaction (1-31Aug 2019).pdf |
| 9/12/2019 | 2505 | 2505 SMC4-LC-764 Change the Type of Rebar for Lifting Hook of Rebar Cage of Bored Pile.pdf |
| 9/12/2019 | 2506 | 2506 SMC4-LC-763 Acceptance of CIP Concrete Pile Foundation Construction & Transfer to Substructure for P10.pdf |
| 9/11/2019 | 2507 | 2507 3175 TB-BQLDATL Notice on Conclusions given by PMU in the Meeting to review the Implementation.pdf |
| 9/12/2019 | 2508 | 2508 SMC4-RP-105 RP on Excavation for Survey of Underground Utilities at Abutment A1.pdf |
| 9/13/2019 | 2509 | 2509 SMC4-MA-501Report on Frequency Test of Reinforcing Steel VIS for Super T Girder of S9, S10.pdf |
| 9/13/2019 | 2510 | 2510 SMC4-MA-502 Report on Frequency Test of Reinforcing Steel VIS for CIP Concrete Pile at A1.pdf |
| 9/13/2019 | 2511 | 2511 SMC4-MA-503 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap,Pier Column of P48, P49.pdf |
| 9/12/2019 | 2512 | 2512 SMC4-LC-768 Installation of Crack Induction Joint to Abutment A1.pdf |
| 9/12/2019 | 2513 | 2513 SMC4-AD-83 AD of Pre-tensioning Pre-stressed Super T Girder os Span 16 (P15-P16).pdf |
| 9/12/2019 | 2514 | 2514 SMC4-AD-84 AD of Cast in Place Concrete Piling D1.2m of Pier P51.pdf |
| 9/13/2019 | 2515 | 2515 SMC4-LC-767 Claim for Extention of Time for Completion of Works & Revised Overal Construction Schedule of the Project (Revision Version).pdf |
| 9/13/2019 | 2516 | 2516 SMC4-LC-769 Subcontracts Agreement for Protection & Relocation of Existing Utilities Item.pdf |
| 9/13/2019 | 2517 | 2517 SMC4-LC-770 Contractor for Design Modification of Relocation of Abutment A1.pdf |
| 9/14/2019 | 2518 | 2518 SMC4-LC-771 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Substructure Work for P51.pdf |
| 9/14/2019 | 2519 | 2519 SMC4-LC-772 Summary Table of Waste Disposal Implement by the Subcontractors at Nguyen Khe Disposal Area from Apr to Jun 19.pdf |
| 9/14/2019 | 2520 | 2520 SMC4-LC-773 Report on Environmental Monitoring in Construction Stage (1st Phase in Sep 19 based on S1.43).pdf |
| 9/20/2019 | 2521 | 2521 SMC4-MS-294 Calculation of Tendon Cable Elongation for Pier Heads P11-P13.pdf |
| 9/16/2019 | 2522 | 2522 SMC4-MS-295 Method Drawing for Erection of Super T Girder at Span S16 (P15-P16).pdf |
| 9/14/2019 | 2523 | 2523 SMC4-AD-85 AD of CIP Concrete Piling D1.2m of Pier P41R.pdf |
| 9/16/2019 | 2524 | 2524 SMC4-LC-775 Manpower Mobilization Document for Deck Slab Construction Work Under Scope Co.414.pdf |
| 9/16/2019 | 2525 | 2525 SMC4-LC-776 Submission of Weekly Report No.69.pdf |
| 9/14/2019 | 2526 | 2526 SMC4-LC-774 Notice of Claim on Unforeseeable Physical Conditions Found by Constructor during Construction of A1.pdf |
| 9/16/2019 | 2527 | 2527 SMC4-WD-372 WD of Elevation & Thickness of Deck Slab at Span S27 (P26-P27).pdf |
| 9/16/2019 | 2528 | 2528 SMC4-RP-106 Report on Loading Test of Pier Head's Supporting System P39.pdf |
| 9/16/2019 | 2529 | 2529 SMC4-RP-102A Report on Loading Test of Pier Head's Supporting System P13.pdf |
| 9/16/2019 | 2530 | 2530 SMC4-LC-779 Proceeding Bored Piles Works of abutment A1.pdf |
| 9/16/2019 | 2531 | 2531 SMC4-WD-373 WD of Structure Excavation for Section P44-P45.pdf |
| 9/16/2019 | 2532 | 2532 SMC4-WD-374 WD of Retaining Wall MSE Wall from Sta 0+494.22-Sta 0+566.125.pdf |
| 9/17/2019 | 2533 | 2533 SMC4-MA-504 RP on Frequency Test of Reinforcing Steel VGS for Bore Piles of Pier P53; Pile Cap, Pier Column, Pier Head of P50-P52; P9-P10; P39 and Deck Slab of Span S36.pdf |
| 9/16/2019 | 2534 | 2534 SMC4-LC-777 Acceptance of Sub Structure Construction Stage & Transfer to Constrution of Superstructure Work for P15.pdf |
| 9/16/2019 | 2535 | 2535 SMC4-LC-778 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work for P16.pdf |
| 9/17/2019 | 2536 | 2536 SMC4-MA-506 RP on Frequency Test of Galbon SP Primer Paint of Hai Phong Paint JSC for SCC Slab of Steel Bridge (sampling date 01.09.2019).pdf |
| 9/17/2019 | 2537 | 2537 SMC4-LC-780 Result of Ultrasonic Test of Cast in Place Concrete Piles at P43L.pdf |
| 9/17/2019 | 2538 | 2538 SMC4-LC-781 Result of Ultrasonic Test of Cast in Place Concrete Piles at P43R.pdf |
| 9/17/2019 | 2539 | 2539 SMC4-WD-375 WD of Superstructure Deck Slab for Spans 10,13,14,15 and Link Slab at Piers P10, P12, P13, P14 & P15.pdf |
| 9/17/2019 | 2540 | 2540 SMC4-WD-376 WD of Substructure - Pier P7.pdf |
| 9/17/2019 | 2541 | 2541 SMC4-WD-377 WD of Substructure Pier P8.pdf |
| 9/17/2019 | 2542 | 2542 SMC4-MA-505 RP on Frequency Test of Reinforcing Steel- VIS for Super T Girder Span 60 (Minutes of Checking and Taking Sample Dated 13 September 2019).pdf |
| 9/17/2019 | 2543 | 2543 SMC4-MA-507 RP on Frequency Test of Reinforcing Steel-VGS for Deck Slab and Link Slab S20-S23 (The Minutes of Checing and Taking Sample Dated 13 Sep 2019).pdf |
| 9/17/2019 | 2544 | 2544 SMC4-LP-54 Clarify the Scope of Work of Noise Barrier Items.pdf |
| 9/17/2019 | 2545 | 2545 SMC4-MC-17 Application for Interim Payment Certificate No.14 (Period 01st August,2019 to 31st August, 2019).pdf |
| 9/17/2019 | 2546 | 2546 SMC4-LC-782 Swapping Position of Pre Tensioning Pre Stressed Super T Girders of Span S16.pdf |
| 9/17/2019 | 2547 | 2547 SMC4-LC-783 Acceptance of CIP Concrete Pile Foundation Construction Stage & Tranfer to Construction of Substructure Work for P41R.pdf |
| 9/18/2019 | 2548 | 2548 SMC4-AD-86 AD of CIP Concrete Piling D1.2m D1.2m of Pier P9.pdf |
| 9/24/2019 | 2549 | 2549 SMC4-MS-296 MS of Cutting & Pruning Tree for Section A1-P16.pdf |
| 9/18/2019 | 2550 | 2550 SMC4-WD-378 WD of Parapet & Median Barrier of Spans P19-P32.pdf |
| 9/18/2019 | 2551 | 2551 SMC4-WD-379 WD of Substructure Pier P53 (3rd).pdf |
| 9/18/2019 | 2552 | 2552 SMC4-LC-784 Acceptance of CIP COncrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work at P9.pdf |
| 9/18/2019 | 2553 | 2553 SMC4-LC-762A Reply to the Consultant's Letter No, HCRR-RE1-16031.72 Warning about Working Safety on the High Position.pdf |
| 9/17/2019 | 2554 | 2554 211-Agreement Minutes on Alternatives of Traffic Control for Construction of Asphalt Pavement.pdf |
| 9/18/2019 | 2555 | 2555 3276-PMUTL-DHDA1 Implementation of Instructiion by MOT Vide Letter No.8736-BGTVT-CQLXD 16Sep19 Regarding Design of Additional Pile at P43C in PK1.pdf |
| 9/20/2019 | 2556 | 2556 SMC4-WD-380 WD of Road Work - Epressway at Sta.0+447.90-Sta.0+568.40.pdf |
| 9/20/2019 | 2557 | 2557 SMC4-AD-87 AD of Pre Tensioning Pre Stressed Super T Girder of Span 38 (P37-P38).pdf |
| 9/20/2019 | 2558 | 2558 SMC4-LC-785 Result of Ultrasonic Test of CIP Concrete Piles at P49.pdf |
| 9/20/2019 | 2559 | 2559 SMC4-LC-786-Result of Ultrasonic Test of CIP Concrete Pile at P50.pdf |
| 9/20/2019 | 2560 | 2560 SMC4-LC-787 Submission of Weekly Report No.70.pdf |
| 9/20/2019 | 2561 | 2561 SMC4-MC-18 Interim Payment Certificate No.14 ( Period 1-31AUG19).pdf |
| 9/21/2019 | 2562 | 2562 SMC4-MA-508 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of P44,P45, Pier Column, Pier Head of P46,P47.pdf |
| 9/21/2019 | 2563 | 2563 SMC4-WD-381 Calculation Sheet & WD of Adjust of CIP Concrete Pile, Pile Cap of P43C ( 1st Revision).pdf |
| 9/21/2019 | 2564 | 2564 SMC4-RP-107 Report on Loading Test of Pier Head Supporting System at P60.pdf |
| 9/21/2019 | 2565 | 2565 SMC4-RP-108 Report on Loading Test of Pier Head Supporting System at P58.pdf |
| 9/21/2019 | 2566 | 2566 SMC4-WD-382 WD of Superstructure - Deck Slab for Span 16.pdf |
| 9/21/2019 | 2567 | 2567 SMC4-WD-383 WD of Substructure Pier P45.pdf |
| 9/21/2019 | 2568 | 2568 SMC4-WD-384 WD of Substructure -Deck Slab for Span 42 & Link Slabs at P41, P42.pdf |
| 9/21/2019 | 2569 | 2569 SMC4-WD-385 WD of CIP concrete Pile for Abutment A28L.pdf |
| 9/21/2019 | 2570 | 2570 SMC4-MS-297 MS for Construction of Parapet & Median Barrier.pdf |
| 9/21/2019 | 2571 | 2571 SMC4-MS-298 Method Drawing for Erection of Super T Girder at Span S38(P37-P38) & S40(P39-P40).pdf |
| 10/2/2019 | 2572 | 2572 SMC4-MA-509 Report on Frequency Test of Welding Material Welding Wire Supercore 81 Lot Number 20003938AB9GE2, 10Sep19.pdf |
| 9/21/2019 | 2573 | 2573 SMC4-LC-788 Additional Manpower Mobilization Document for Substructure & Deck Slab Construction Work of Co.422.pdf |
| 9/21/2019 | 2574 | 2574 SMC4-LC-789 Manpower Mobilization Document of Thanh Long for Erection of Steel Girder & Steel Concrete Composite Deck Slab.pdf |
| 9/21/2019 | 2575 | 2575 SMC4-LC-790 Manpower Mobilization Document for Deck Slab Construction Work under Scope of Co.412.pdf |
| 9/21/2019 | 2576 | 2576 SMC4-MA-510 Qualification Document of Acrowel Materials for Steel Structure.pdf |
| 9/23/2019 | 2577 | 2577 SMC4-LC-793 Detailed Information of Subcontract Agreements.pdf |
| 9/23/2019 | 2578 | 2578 SMC4-MA-511 Additional Manufacturer of Bridge Expansion Joints.pdf |
| 9/23/2019 | 2579 | 2579 SMC4-MA-512 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab S36 (MoC&TS dated 17Sep19).pdf |
| 9/23/2019 | 2580 | 2580 SMC4-LC-791 Report on Environment Monitoring in Construction Stage (2nd Phase on Sep 2019 based on S1.43).pdf |
| 9/23/2019 | 2581 | 2581 SMC4-LC-792 Result of Ultra Sonic Test of CIP Pile at P48 (From Pile No.1 to Pile No.8).pdf |
| 9/23/2019 | 2582 | 2582 SMC4-LC-794 Official Instruction on Design Modification for Off Ramp HQV-B.pdf |
| 9/24/2019 | 2583 | 2583 SMC4-WD-386 Calculation Sheet & WD of CIP Pile, Pile Cap P48 (1st).pdf |
| 9/24/2019 | 2584 | 2584 SMC4-MS-299 MS of Pier Column from P8-P10.pdf |
| 9/24/2019 | 2585 | 2585 SMC4-LC-795 Joint Between Retaining Wall Segments.pdf |
| 9/24/2019 | 2586 | 2586 SMC4-MA-513 Report on Frequency Test of Coated PC Strand (11th) & Anchorage (5th).pdf |
| 9/25/2019 | 2587 | 2587 SMC4-MA-514 Report on Frequency Test of VIS l for Girder Cover Plate ( MoC&TS 17Sep2019).pdf |
| 9/25/2019 | 2588 | 2588 SMC4-MS-300 Calculation of Tendon Cable Elongation for Pier Head at P39.pdf |
| 9/25/2019 | 2589 | 2589 SMC4-WD-385A WD of Elevation & Thickness of Deck Slab at Span S37 (P36-P37).pdf |
| 9/25/2019 | 2590 | 2590 SMC4-LC-796 Acceptance of Sub Structure Construction Stage & Transfer ot Construction of Superstructure Work for P38.pdf |
| 9/26/2019 | 2591 | 2591 SMC4-MA-515 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column,Pier Head P59, P60, Deck Slab & Link Slab S20-S30 (MoC& TS 21Sep19).pdf |
| 9/26/2019 | 2592 | 2592 SMC4-MA-516 Report on Frequency Test of VGS for CIP Concrete Pile P44, P45, Deck Slab S25, S26 (MoC&TS 21Sep19).pdf |
| 9/26/2019 | 2593 | 2593 SMC4-MA-517 Report on Frequency Test of Reinforcing Steel VGS steel for Pile Cap, Pier Column & Pier Head of P53,P54-P55,P56 ( MoC& TS 17Sep19).pdf |
| 9/26/2019 | 2594 | 2594 SMC4-MA-518 Report on Frequency Test of VGS for Link Slab P30, P31 & Deck Slab Span S31 (MoC& TS 17Sep19).pdf |
| 9/26/2019 | 2595 | 2595 SMC4-LC-797 Result of Ultrasonic Test of CIP Concrete Piles at P7.pdf |
| 9/26/2019 | 2596 | 2596 SMC4-LC-798 Result of Ultrasonic Test of CIP Concrete Piles at P8.pdf |
| 9/27/2019 | 2597 | 2597-SMC4-LT-0028 Inspection Minutes of LAS-XD 1256 of Techno Science of Transport Centre- UOT&C.pdf |
| 9/23/2019 | 2598 | 2598 3307-PMUTL-DA1 Notice on Inspection Plan by Stage Acceptance Commitee.pdf |
| 9/27/2019 | 2599 | 2599 SMC4-AD-88 AD of CIP Concrete Pilling D1.2m of Pier P49.pdf |
| 9/27/2019 | 2600 | 2600 SMC4-WD-387 WD of Substructure Pile Cap & Column Side Pier P32 (1st).pdf |
| 9/30/2019 | 2601 | 2601 SMC4-LC-799 Sulutions for Water Supply Pipe D800 at Abutment A1.pdf |
| 9/27/2019 | 2602 | 2602 SMC4-RP-109 Report on Loading Test of Pier Head's Supporting System at P12.pdf |
| 10/1/2019 | 2603 | 2603 SMC4-MA-519 Report on Frequency Test of Welding Material Welding Wire Supercore 81 Lot No. 20003938AB9GE2 Testing 13Sep19 & 20Sep19.pdf |
| 9/27/2019 | 2604 | 2604 SMC4-WD-388 WD of Elevation& Thickness of Deck Slab at Spans S24 (P23-P24),S24 (P24-P25),S26 (P25-P26).pdf |
| 9/27/2019 | 2605 | 2605 SMC4-MS-301 Calculation of Tendon Cable Elongation for Pier Head P57-P58.pdf |
| 9/27/2019 | 2606 | 2606 SMC4-LC-801 Environmental Monitoring Schedule in Oct 2019 at Construction Phase.pdf |
| 9/27/2019 | 2607 | 2607 SMC4-LC-800 Acceptance of CIP Concrete Pile Foudation Construction Stage & Tranfer to Construction of Substructure Work for P49.pdf |
| 9/30/2019 | 2608 | 2608 SMC4-MA-520 Report on Frequency Test of Bolt Material for Steel Bridge S10T (including Nut & Washer) TS dated 05Aug19 & Testing dated 13Aug19.pdf |
| 9/30/2019 | 2609 | 2609 SMC4-MA-521 Report on Frequency Test of Bolt Material for Steel Bridge S10T (including Nut & Washer) TS dated 31Aug19 & Testing dated 09Sep19.pdf |
| 9/30/2019 | 2610 | 2610 SMC4-LC-803 Submission of Weekly Report No.71.pdf |
| 9/30/2019 | 2611 | 2611 SMC4-LC-804 Changing Position of Steel Bar U160x56x5.2 of the Anti-Glare Fence on the Concrete Parapet (2nd).pdf |
| 9/30/2019 | 2612 | 2612 SMC4-LC-802 Resubmit Subcontract Agreements with PHATECO and Nhat Son Quang.pdf |
| 9/30/2019 | 2613 | 2613 SMC4-MA-522 Report on Frequency Test of Reinforcing Steel - VGS for Pile, Pier Column P49 (MoC&TS 20Sep 2019).pdf |
| 9/30/2019 | 2614 | 2614 SMC4-MA-523 Report on Frequency Test of Reinforcing Steel - VIS Bar for Super T Girder Span S60 (MoC&TS 24 September 2019).pdf |
| 9/30/2019 | 2615 | 2615 SMC4-MA-524 Report on Frequency Test of Reinforcing Steel - VIS Bar (VIS) for Super T Girder Span S42, S53 (MoC&TS 24Sep19.pdf |
| 9/30/2019 | 2616 | 2616 1117 VPCP-TH Invitation Letter.pdf |
| 9/30/2019 | 2617 | 2617 SMC4-LC-805 Report on Environment Monitoring Results at Stage 3 2019 at Steel Structure Fabrication Factory of Thanh Long JSC.pdf |
| 9/30/2019 | 2618 | 2618 SMC4-MA-518A Report on Frequency Test of PC Strand for Super T Girder (33rd).pdf |
| 9/30/2019 | 2619 | 2619 SMC4-MA-519A Report on Frequency Test of PC Strand for Super T Girder (34th).pdf |
| 9/30/2019 | 2620 | 2620 SMC4-WD-389 WD of Elevation & Thickness of Deck Slab at Span S36 (P35-P36).pdf |
| 10/4/2019 | 2621 | 2621 SMC4-MS-302 MS for Construction of Pier Head & Outline of the Loading Test of Pier Head's Supporting System from P46-P56.pdf |
| 9/30/2019 | 2622 | 2622 SMC4-AD-89 AD of CIP Concrete Pilling D1.2m of Pier P50.pdf |
| 9/30/2019 | 2623 | 2623 SMC4-WD-390 WD of Miscellaneous -General View of Noise Barrier (1st).pdf |
| 9/30/2019 | 2624 | 2624 SMC4-LC-806 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P50.pdf |
| 10/1/2019 | 2625 | 2625 SMC4-WD-391 WD of Substructure - Pile Cap of Side Pier P43 (2nd).pdf |
| 10/1/2019 | 2626 | 2626 SMC4-WD-392 WD of Substructure - Column & Pier Head P48 (1st).pdf |
| 10/1/2019 | 2627 | 2627 SMC4-WD-393 WD of Substructure - Pier P44 (1st).pdf |
| 10/1/2019 | 2628 | 2628 SMC4-WD-394 WD of Superstructure Diaphargm from Span 7-9 & 44-61 (1st).pdf |
| 10/1/2019 | 2629 | 2629 SMC4-LP-55 Supporting the Contractor to Get Permit for Cutting & Prunning Trees at the Section from Mai Dich Bridge to P16.pdf |
| 10/1/2019 | 2630 | 2630 SMC4-LC-807 Result of Tip Contact Checking Test of CIP at C5-P7.pdf |
| 10/1/2019 | 2631 | 2631 SMC4-MA-525 Capacity Profile of Supplier, Manufaturer Bitumen, Bitumen Emulsion Used for Asphalt concrete.pdf |
| 10/1/2019 | 2632 | 2632 SMC4-LT-29 Updated Capacity Profile of Crushed Stone Quarry for Asphalt Concrete of Ha Tay JSC.pdf |
| 10/3/2019 | 2633 | 2633 SMC4-MA-526 Notice on Transferring a Part of VGS Used for Deck Slab of S20 to S24.pdf |
| 10/3/2019 | 2634 | 2634 SMC4-MS-303 Supplement for Calculation of Tendon Cable Elongation of Pier Head P11-P12.pdf |
| 10/7/2019 | 2635 | 2635 SMC4-MS-304 MS of Gate Arrangement Between Pier P50-P51 & P53-P54.pdf |
| 10/3/2019 | 2636 | 2636 SMC4-LC-808 Report on Environment Monitoring in Construction Stage (3rd Phase in Sep 2019 Based on S1.43).pdf |
| 10/3/2019 | 2637 | 2637 SMC4-LC-809 Report on Environment Monitoring in Construction Stage Sep 2019 (Base on EMP).pdf |
| 10/4/2019 | 2638 | 2638 SMC4-MS-305 General Plan for Relocation or Protection Water Supply Pipe D800 at Abutment A1(2nd).pdf |
| 10/7/2019 | 2639 | 2639 SMC4-MS-306 MS of Erection for Pier Head P17, P18 (2nd).pdf |
| 10/4/2019 | 2640 | 2640 SMC4-LC-812 Resubmission of Schedule for Steel Bridge (2nd).pdf |
| 10/4/2019 | 2641 | 2641 SMC4-WD-395 WD of Pot Bearing at Piers P16 & P19 (2nd).pdf |
| 10/4/2019 | 2642 | 2642 SMC4-WD-396 WD for teel Concrete Composite Deck Slab (SCC Slab) of Steel Bridge (1st revision).pdf |
| 10/4/2019 | 2643 | 2643 SMC4-LC-810 Withdrawal of the Letter SMC4-LT-0756-19 dated 6Sep2019.pdf |
| 10/5/2019 | 2644 | 2644 SMC4-LC-811 Updated Quality Control Plan (3rd).pdf |
| 10/5/2019 | 2645 | 2645 SMC4-LC-813 Minutes of Meeting Regarding Plan for Erection of Span S61.pdf |
| 10/5/2019 | 2646 | 2646 SMC4-MA-527 Characteristic Strength for Concete Class A of Viep Tiep BP ( New Location)- RP No.3 (fr 1Aug to 31Aug2019).pdf |
| 10/5/2019 | 2647 | 2647 SMC4-MA-528 Characteristic Strength for Concrete Class C of Transmeco - RP No.7 (fr 1Aug to 30Aug2019).pdf |
| 10/5/2019 | 2648 | 2648 SMC4-MA-529 Characteristic Strength for Concrete Class Y of Transmeco - RP No.7 (fr 1Aug to 29Aug2019).pdf |
| 10/7/2019 | 2649 | 2649 SMC4-MS-305A MS for Lower Part of Pier Head P9-P10.pdf |
| 10/16/2019 | 2650 | 2650 SMC4-MS-307 Supplement Method Drawing of Link Slab Construction.pdf |
| 10/7/2019 | 2651 | 2651 SMC4-MS-308 MS for Erection of Super T Girder at Span S58 (P57-P58) to S61 (P60-P61).pdf |
| 10/7/2019 | 2652 | 2652 SMC4-LC-814 Engineer's Confirmation for Safety & Environment Satisfaction (1Sep2019 to 30Sep2019).pdf |
| 10/7/2019 | 2653 | 2653 SMC4-LT-535 Updated Quality Control Plan & Quality Assurance Plan & Welding Plan for Steel Bridge Fabrication at Thang Long Group JSC.pdf |
| 10/7/2019 | 2654 | 2654 SMC4-LP-56 Clarify the Scope of Work of Contractor in the Items Related for Urban Road under Viaduct.pdf |
| 10/7/2019 | 2655 | 2655 SMC4-MA-530 Report on Frequency Test of Shear Stud Connector for Steel Bridge (TS dated 12Sep2019 & Testing dated 18Sep2019).pdf |
| 10/7/2019 | 2656 | 2656 SMC4-MA-531 Report on Frequency Test of PC Strand for Super T Girder (35th).pdf |
| 10/7/2019 | 2657 | 2657 SMC4-MA-532 Material Source & C19 Tight Aggregate Asphalt Concrete at 703 Asphalt BP of PK2 used for PK1.pdf |
| 10/7/2019 | 2658 | 2658 SMC4-MA-533 Notification on Transferring VGS Used for Deck Slab S36 Righ Side.pdf |
| 10/7/2019 | 2659 | 2659 SMC4-MA-534 Notification on Transferring of VGS Steel Used for Diaphragm S38 Righ Side.pdf |
| 10/7/2019 | 2660 | 2660 SMC4-LC-815 Machine & Manpower Mobilization Document of Thanh Long JSC for Erection of Steel Girder.pdf |
| 10/8/2019 | 2661 | 2661 SMC4-LC-809A Withdrawal of the Letter SMC4-LC-799 dated 26Sep2019.pdf |
| 10/8/2019 | 2662 | 2662 SMC4-LC-816 Withdrawal of the Letter SMC4-WD-0381 dated 19Sep2019.pdf |
| 10/8/2019 | 2663 | 2663 SMC4-817 Withdrawal of the Letter SMC4-WD-0386 dated 23Sep2019.pdf |
| 10/8/2019 | 2664 | 2664 SMC4-LC-817A Design of Addtional CIP Concrete Pile at Pier P43C (1st).pdf |
| 10/8/2019 | 2665 | 2665 SMC4-LC-817B Design of Additional CIP Concrete Pile at Pile at Pier P48 (1st).pdf |
| 10/21/2019 | 2666 | 2666 SMC4-LC-818 Submission of Construction Schedule of Oct 2019.pdf |
| 10/8/2019 | 2667 | 2667 SMC4-LC-819 Protection Solutions the Reinforcement Bar of Deck Slab at Span S31 (P30-P31) Left Side.pdf |
| 10/8/2019 | 2668 | 2668 SMC4-WD-397 WD of Backfill at Piers P44-P45.pdf |
| 10/8/2019 | 2669 | 2669 SMC4-WD-398 WD of Superstructure - Deck Slab for Spans 51, 52, 55, 56, 59, 60 & Link Slab at P50-P52, P54-P56, P58-P60.pdf |
| 10/8/2019 | 2670 | 2670 SMC4-MA-536 Capacity Profile of Manufacturer & Supplier of Joint Sealing Grout - VITEC JSC.pdf |
| 10/8/2019 | 2671 | 2671 SMC4-MA-537 Report on Frequency Test of Material for Cement Concrete at Viet Tiep BP (13th-15th) & Updated Frequency Test of Cement R28 (9th-11th).pdf |
| 10/8/2019 | 2672 | 2672 SMC4-MS-309 Outline for Loading Test of Pier Head's Supporting System P9-P11.pdf |
| 10/8/2019 | 2673 | 2673 SMC4-MS-310 Resubmission of the Supplement of the Storing Plan for Super T Girder 34.3m Type at Fabrication Yard of Group No.2 ( Rev 2).pdf |
| 10/9/2019 | 2674 | 2674 SMC4-RP-110 Report on Loading Test of Pier Head's Supporting System at P14.pdf |
| 10/9/2019 | 2675 | 2675 SMC4-RP-111 Report on Loading Test of Pier Head's Supporting System at P46.pdf |
| 10/9/2019 | 2676 | 2676 SMC4-MA-538 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column & Pier Head P41-P43 (MoC& TS dated 21 Oct2019).pdf |
| 10/9/2019 | 2677 | 2677 SMC4-MA-539 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column & Pier Head P53-P56 ( MoC& TS dated 2 Oct2019).pdf |
| 10/9/2019 | 2678 | 2678 SMC4-MA-540 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column Pier Head P41-P43, P50-P52( MoC&TS dated 2 Oct2019.pdf |
| 10/9/2019 | 2679 | 2679 SMC4-MA-541 Report on Frequency Test of Reinforcing Steel VGSl for Link Slab P24-P26 ( MoC&TS dated 1 Oct2019).pdf |
| 10/10/2019 | 2680 | 2680 SMC4-WD-399 WD of Substructure - Pier P8 (2nd).pdf |
| 10/9/2019 | 2681 | 2681 203-TTHDNTNN-GD3 Results of Site Inspection to the HCRR3 Construction Project MD-STL Section.pdf |
| 10/9/2019 | 2682 | 2682 1147 GM-BGTVT Notice on Changing Inspection Time.pdf |
| 10/10/2019 | 2683 | 2683 SMC4-MA-543 Report on Frequency Test of Reinforcing Steel VIS for Super T Girder of Span S41, S50 ( MoC&TS dated 5 Oct 2019).pdf |
| 10/10/2019 | 2684 | 2684 SMC4-MA-542 Report on Frequency Test of Materials for Cement Concrete at ASEAN BP (21st & 22nd) & Updated Frequency Test of Cement R28 (20th).pdf |
| 10/10/2019 | 2685 | 2685 SMC4-MA-544 Report on Frequency Test of Materials for Cement Concrete at Transmeco BP (40th to 44th) & Updated Result of Cement R28 (36th & 38th).pdf |
| 10/10/2019 | 2686 | 2686 SMC4-LT-30 Inspection Minutes of LAS-XD 1256 of TechnoScience of Transport Centra- UOT&C.pdf |
| 10/10/2019 | 2687 | 2687 SMC4-RP-109A Report on Excavation for Survey of Underground Utilities at P32 ( L+R).pdf |
| 10/10/2019 | 2688 | 2688 SMC4-LC-820 Submission of Weekly Report No.72.pdf |
| 10/10/2019 | 2689 | 2689 SMC4-LC-821 Submission of Weekly Report No.73.pdf |
| 10/10/2019 | 2690 | 2690 SMC4-LC-822 Result of Ultrasonic Test of CIP Concrete Pile at P53.pdf |
| 10/10/2019 | 2691 | 2691 SMC4-LC-823 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P39.pdf |
| 10/10/2019 | 2692 | 2692 SMC4-LC-824 Capacity Profile of Subcontractor Hai Anh Co.Ltd.pdf |
| 10/10/2019 | 2693 | 2693 SMC4-RP-112 Report on Checking the Periodic Benchmarks System (3rd).pdf |
| 10/10/2019 | 2694 | 2694 SMC4-AD-90 As Built Drawing of Pre Tensioning Pre Stressed Super T Girder Span 39 (P38-P39).pdf |
| 10/10/2019 | 2695 | 2695 SMC4-WD-400 WD of Superstructure - Deck Slab Span 61.pdf |
| 10/10/2019 | 2696 | 2696 SMC4-WD-401 WD of General Layout of Drainage System from Km0+400.00-Km0+740.00.pdf |
| 10/10/2019 | 2697 | 2697 SMC4-WD-402 WD of Substructure Pier P7 (2nd).pdf |
| 10/10/2019 | 2698 | 2698 SMC4-MS-312 Resubmission of Permission for Circulation of Vehicles to Transport Overlength Cargo on Road (Transportation of Steel Girder& Steel Pier Head).pdf |
| 10/19/2019 | 2699 | 2699 SMC4-MS-311 MS for Construction of Pier Head from P41-P43.pdf |
| 10/14/2019 | 2700 | 2700 SMC4-MA-545 Material of Stabilized Earth (MSE) Retaining Wall System.pdf |
| 10/14/2019 | 2701 | 2701 SMC4-MA-546 Report on Frequency Test of Galbon SP Primer Paint of Hai Phong JSC for SCC Slab of Steel Bridge ( Samle date 30Sep2019).pdf |
| 10/14/2019 | 2702 | 2702 SMC4-WD-403 WD of Superstructure Deck Slab for Spans 54, 57, 58.pdf |
| 10/14/2019 | 2703 | 2703 SMC4-WD-404 WD of Superstructure -Deck Slab for Spans 40 and 41 (2nd).pdf |
| 10/14/2019 | 2704 | 2704 SMC4-LC-825 Submission of Monthly Report No.17.pdf |
| 10/14/2019 | 2705 | 2705 SMC4-LC-826 Report on Environment Monitoring in Construction Stage, 1st Phase in Oct 2019, based on S1.43).pdf |
| 10/14/2019 | 2706 | 2706 SMC4-LC-827 Withdrawal of Letter MA-0411 dated 13July19.pdf |
| 10/14/2019 | 2707 | 2707 SMC4-LC-830 Additional Supervision Cost of Engineer's Staff (Aug 2019).pdf |
| 10/14/2019 | 2708 | 2708 SMC4-RP-113 Report on Loading Test of Pier Head's Supporting System at P57.pdf |
| 10/14/2019 | 2709 | 2709 SMC4-MS-314 Method Statement of Structure Excavation P44-P45.pdf |
| 10/14/2019 | 2710 | 2710 SMC4-MS-313 Method Statement of Pile Cap P44-P45.pdf |
| 10/15/2019 | 2711 | 2711 SMC4-MA-547 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pier of P32 ( MoC& TS dated 11 Oct 2019).pdf |
| 10/15/2019 | 2712 | 2712 SMC4-MA-548 Testing Result of HDPE Conduit Santo JSC.pdf |
| 10/15/2019 | 2713 | 2713 SMC4-AD-91 As Built Drawing of CIP Concrete Piling D1.2m of P8.pdf |
| 10/15/2019 | 2714 | 2714 SMC4-WD-405 WD of Detail of Expansion Joint (for Main Bridge -2nd).pdf |
| 10/15/2019 | 2715 | 2715 SMC4-LC-831 Manpower Mobilization Document for Supporting Work.pdf |
| 10/15/2019 | 2716 | 2716 SMC4-LC-832 Notice of Department of Transport Regarding- Traffic Diviersion & Organization on PVD Str for Super T Girder Erection( 10 Oct 2019 to 11 Jan 2020).pdf |
| 10/15/2019 | 2717 | 2717 SMC4-LC-828 Protection Plan for Water Supply Pipe D800 at the Location of Abutment A1- Raising the Elevation of Abutment's Pile Cap.pdf |
| 10/15/2019 | 2718 | 2718 SMC4-LC-829 WD of CIP Concrete Piles, Pile Cap & Abutment A1.pdf |
| 10/15/2019 | 2719 | 2719 SMC4-MS-315 Report on Loading Test for Pier Head's Supporting System at P18.pdf |
| 10/15/2019 | 2720 | 2720 SMC4-MS-316 Method Statement of Mock Up for SCC Deck Slab.pdf |
| 10/16/2019 | 2721 | 2721 SMC4-LC-833 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P8.pdf |
| 10/16/2019 | 2722 | 2722 SMC4-LP-57 Support the Contractor to Extending the Method of Fencing Traffic Control at Project.pdf |
| 10/16/2019 | 2723 | 2723 SMC4-LC-834 Appendix to the Contract with Subcontractor Thanh Long Group JSC.pdf |
| 10/16/2019 | 2724 | 2724 SMC4-WD-407 WD of Substructure- Column & Pier Head of P43 (2nd).pdf |
| 10/16/2019 | 2725 | 2725 SMC4-WD-406 WD of Additional CIP Concrete Pile at P43C (1st).pdf |
| 10/16/2019 | 2726 | 2726 SMC4-WD-408 WD of Supstructure -Adjustment Pile Cap of Pier Cap of P43C (1st).pdf |
| 10/16/2019 | 2727 | 2727 SMC4-MA-549 Report on Frequency Test of Reinforcing Steek VGS for Pile Cap, Pier Column P7-P8 (MoC&TS dated 12 Oct 2019).pdf |
| 10/16/2019 | 2728 | 2728 3557-PMUTL-DHDA1 Triển khai thi công nhánh HQV-B.pdf |
| 10/16/2019 | 2729 | 2729 3604-PMUTL-DHDA1 Overall Construction Schedule & Quality Control.pdf |
| 10/17/2019 | 2730 | 2730 SMC4-WD-402A WD of Painting of Segment 7&15 - Rigid Pier Head of Steel Bridge (1st).pdf |
| 10/17/2019 | 2731 | 2731 SMC4-WD-409 WD of Substructure - Upper Part of Pier Head P32.pdf |
| 10/17/2019 | 2732 | 2732 SMC4-AD-92 AD of CIP Concrete Piling D1.2m of Pier P42R.pdf |
| 10/17/2019 | 2733 | 2733 SMC4-LC-835 Acceptance Substructure Construction Stage & Transfer to Construction Superstructure Work for P60.pdf |
| 10/17/2019 | 2734 | 2734 SMC4-LC-836 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure for P59.pdf |
| 11/4/2019 | 2735 | 2735 3618-QD-BQLDATL Decision for Design Change of Pile Foundation Structure of Pier P43C in PK1.pdf |
| 10/18/2019 | 2736 | 2736 SMC4-LC-837 Countermeasure to Improve Concrete Surface of Multi-pier Pier Head.pdf |
| 10/18/2019 | 2737 | 2737 SMC4-LC-836A Proposal for Using Super T Girder at Span S59(P58-P590 for Span S61(P60-P61) & Vice Versa.pdf |
| 10/18/2019 | 2738 | 2738 SMC4-LC-838 Additional Machine & Manpower Mobilization Document of Subcontractor Thanh Long Group JSC for Erection of Steel Girder( Crane & Operator-1st).pdf |
| 10/18/2019 | 2739 | 2739 SMC4-LC-839 Clarification of Arrangement of HDPE Corrugate Conduit for ITS System in the Median Barirer on the Bridge.pdf |
| 10/18/2019 | 2740 | 2740 SMC4-LC-840 Cost Estimate for Changing Design of Drainage Pipe Cultvert D500.pdf |
| 10/18/2019 | 2741 | 2741 SMC4-LC-841 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P42R.pdf |
| 10/18/2019 | 2742 | 2742 SMC4-LC-842 Survey Data of Span S61 Before the Erection of Super T Girders.pdf |
| 10/18/2019 | 2743 | 2743 SMC4-MS-317 Method Statement for Fabrication Panel MSE.pdf |
| 10/18/2019 | 2744 | 2744 SMC4-WD-410 WD of Elevation & Thickness of Deck Slab at Span S38 (P37-P38).pdf |
| 10/18/2019 | 2745 | 2745 SMC4-WD-411 WD of Detail of Drainage System under Viaduct Section P18-P25.pdf |
| 10/18/2019 | 2746 | 2746 SMC4-WD-412 WD of Retaining Wall - Parapet from Km0+447.90-Km0+494.22.pdf |
| 10/18/2019 | 2747 | 2747 SMC4-AD-93 As-built Drawing of Pre Tensioning Pre Stressed Super T Girder Span 60 (P59-P60).pdf |
| 10/18/2019 | 2748 | 2748 SMC4-AD-94 As-built Drawing of Pre Tensioning Pre Stressed Super T Girder Span 61 (P60-P61).pdf |
| 10/19/2019 | 2749 | 2749 SMC4-MC-19 Interim Payment Certificate No.15 ( Period 01st Sep to 30th 2019).pdf |
| 10/19/2019 | 2750 | 2750 SMC4-MA-550 Supplement the Testing Properties of Waterproofing Material HASEAL 5.pdf |
| 10/19/2019 | 2751 | 2751 SMC4-MA-551 Notification on Transferring VGS Steel for the Use of Pile Cap & Column of P7, P8.pdf |
| 10/19/2019 | 2752 | 2752 SMC4-MA-552 Notification on Transferring VGS Steel for the Use of Deck Slab S38 Right Side.pdf |
| 10/19/2019 | 2753 | 2753 SMC4-MA-553 Notification on Transferring VGS Steel for the Use of Pile Cap & Column of P7, P8.pdf |
| 10/19/2019 | 2754 | 2754 SMC4-MA-554 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column, Pier Head P41-P43 ( MoC&TS dated 11 Oct 2019).pdf |
| 10/19/2019 | 2755 | 2755 SMC4-RP-114 Report on Excavation for Survey of Underground Utilities at P43C- Around the Additional Pile.pdf |
| 10/19/2019 | 2756 | 2756 SMC4-LC-843 Submission of Weekly Report No.74.pdf |
| 10/19/2019 | 2757 | 2757 SMC4-MS-318 Site Organization Chart of SMCC-CIENCO4 JV for Construction SCC Deck Slab.pdf |
| 10/19/2019 | 2758 | 2758 SMC4-RP-115 Report on Loading Test of Pier Head's Supporting System at P11.pdf |
| 10/19/2019 | 2759 | 2759 SMC4-MA-555 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab S25 ( MoC& TS dated 12 Oct 2019).pdf |
| 10/19/2019 | 2760 | 2760 SMC4-MA-556 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab S37-P40 (MoC&TS dated 11 Oct 2019).pdf |
| 10/21/2019 | 2761 | 2761 SMC4-MC-20 Resubmission of Interim Payment Certificate No.15 (Period 01-30 Sep 2019).pdf |
| 10/22/2019 | 2762 | 2762 SMC4-LC-844 Reply for Engineer's Request to Submit Details Document Supporting the Protection of Water Pipe D800 at A1 & Resubmitsion of WD of Adjusted Pile at A1 Abutment(2nd).pdf |
| 10/21/2019 | 2763 | 2763 SMC4-MS-319 Method Drawing for Construction of Pile Cap P43 (L,R).pdf |
| 10/22/2019 | 2764 | 2764 SMC4-WD-413 WD of Additional CIP Concrete Pile at P43C (2nd).pdf |
| 10/22/2019 | 2765 | 2765 SMC4-MS-317A Calculation of Tendon Cable Elongation for Pier Head P14.pdf |
| 10/22/2019 | 2766 | 2766 SMC4-MS-319A Calculation of Tendon Cable Elongation for Pier Head P44-P57.pdf |
| 10/22/2019 | 2767 | 2767 SMC4-MS-320 Method Statement of Steel Girder Erection.pdf |
| 10/22/2019 | 2768 | 2768 SMC4-AD-95 AD of CIP Concrete Piling of D1.2m of P43L.pdf |
| 10/22/2019 | 2769 | 2769 SMC4-WD-415 WD of Superstructure - Deck Slab for S49, S50, S53.pdf |
| 10/22/2019 | 2770 | 2770 SMC4-WD-414 WD of Superstructure- Deck Slab for Span 46-48 & Link Slab P45-P48.pdf |
| 10/23/2019 | 2771 | 2771 SMC4-RP-116 Loading Test of Pier Head Supporting System at P52, P56.pdf |
| 10/23/2019 | 2772 | 2772 SMC4-WD-416 WD of Diaphragm from Span 44-61.pdf |
| 10/23/2019 | 2773 | 2773 SMC4-WD-417 WD of Diaphragm from Span 7-9.pdf |
| 10/23/2019 | 2774 | 2774 SMC4-WD-418 WD of Parapet& Median Barrier of Spans P19-P32 (2nd).pdf |
| 10/23/2019 | 2775 | 2775 SMC4-LC-848 Internal Target Schedule for Main Bridge.pdf |
| 10/28/2019 | 2776 | 2776 SMC4-LC-847 Design Change Document for Modification of Abutment A1 Structure.pdf |
| 10/23/2019 | 2777 | 2777 SMC4-LC-845 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P43L.pdf |
| 10/23/2019 | 2778 | 2778 SMC4-LC-846 Acceptance of Sub Structructure Construction Stage & Transfer to Construction of Superstructure Work of P40.pdf |
| 10/23/2019 | 2779 | 2779 SMC4-MS-319B MS of CIP Concrete Pilling Diameter D1.2m - Additional Pile at P43C.pdf |
| 10/24/2019 | 2780 | 2780 3677-PMUTL-DA1 Opinion on Design of WD of Traffic Safety on the Widened Road under the RRNo.3 Widening Project, MDSTL Section.pdf |
| 10/24/2019 | 2781 | 2781 10052-BGTVT-CQLXD Design of Additional CIP Concrete Pile at P48 in PK1.pdf |
| 10/26/2019 | 2782 | 2782 SMC4-AD-96 AD of Pre Tensioning Pre Stressed SuperT Girder Span 40(P39-P40).pdf |
| 10/26/2019 | 2783 | 2783 SMC4-MA-557 Testing Result of Selection of Backfill Material- Cao Duong Quarry, Commune Exploited by Hien Luong Mineral Exploitation & ProcessingCo.Ltd & Spuulied by 28-10 Thang Long JSC.pdf |
| 10/26/2019 | 2784 | 2784 SMC4-MA-558 Notification on Transferring VGS Steel for the Use of Pile Cap & Column of P53.pdf |
| 10/26/2019 | 2785 | 2785 SMC4-LC-849 Manpower Mobilization Document of Subcontractor Thanh Long JSC for Construction Work of Steel Girder at Site - 1st.pdf |
| 10/26/2019 | 2786 | 2786 SMC4-LC-850 Acceptance of CIP Concrete Pile Foundation Construction Stage& Transfer to Construction of Substructure Work for P53.pdf |
| 10/26/2019 | 2787 | 2787 SMC4-AD-97 AD of CIP Concrete Piling of Pier P53.pdf |
| 10/26/2019 | 2788 | 2788 SMC4-MA-562 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column of P7 P8, Pier Head Pier Column of P9, P10, substructure P41-P43, P50-P52 ( MoC&TS 19Oct2019).pdf |
| 10/26/2019 | 2789 | 2789 SMC4-MA-561 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column of P44-P45, Pier Head of P47, CIP Concrete Pile P48, Deck Slab Span S25(MoC&TS 20 Oct 2019).pdf |
| 10/26/2019 | 2790 | 2790 SMC4-MA-563 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column & Pier Head of P53-P56 ( MoC&TS dated 19 Oct 2019).pdf |
| 10/29/2019 | 2791 | 2791 SMC4-LC-851 Proceeding Bored Piles Work at Abutment A1 following Modified Design.pdf |
| 10/28/2019 | 2792 | 2792 SMC4-WD-419 WD of Additional CIP Concrete Pile at pier P48.pdf |
| 10/28/2019 | 2793 | 2793 SMC4-MA-559 Report on Frequency Test of Reinforcing Steel VGS for CIP Concrete Pile of Pier P43C ( the MoC & TS dated 22 Oct 2019).pdf |
| 10/28/2019 | 2794 | 2794 SMC4-MA-560 Report on Frequency Test of Reinforcing Steel of VGS for Super T Girder of S54-S58 ( The MoC&TS dated 22 Oct 2019).pdf |
| 10/28/2019 | 2795 | 2795 SMC4-LC-852 Report on Environment Monitoring In Consruction Stage, 2nd Phase in Oct 2019 based on S1.43.pdf |
| 10/28/2019 | 2796 | 2796 SMC4-LC-853 Notice of Environment Monitoring Schedule in Nov 2019 at Construction Phase.pdf |
| 10/28/2019 | 2797 | 2797 SMC4-WD-420 WD of Elevation & Thickness of Deck Slab at S39 (P38-P39).pdf |
| 10/28/2019 | 2798 | 2798 SMC4-AD-98 AD of CIP Concrete Piling D1.2m of Pier P7.pdf |
| 11/6/2019 | 2799 | 2799 SMC4-MS-321 Method Statement of Pier Head from P9-P10.pdf |
| 10/28/2019 | 2800 | 2800 SMC4-MA-564 Notification on Transfering VGS Steel for the use of Diaphragm Span S54-S61.pdf |
| 10/28/2019 | 2801 | 2801 SMC4-MS-322 MS of CIP Concrete Pilling Diameter D=1.2m Abutment A1.pdf |
| 10/28/2019 | 2802 | 2802 SMC4-WD-421 WD of Substructure - Adjustment Pile Cap of P43C (1st).pdf |
| 11/14/2019 | 2803 | 2803 SMC4-WD-422 WD of Painting of Segments 1-6, 8-14, 16-21 of Steel Girder (1st).pdf |
| 10/28/2019 | 2804 | 2804 3732-QD-BQLDATL Approval Decision for Design Change of Pile Foundation Structure of P48 in PK1.pdf |
| 10/29/2019 | 2805 | 2805 SMC4-RP-117 Report on Excavation for Survey of Underround Utilities at C9A-P48.pdf |
| 10/29/2019 | 2806 | 2806 SMC4-LC-854 Weekly Report No.75.pdf |
| 12/13/2019 | 2807 | 2807 SMC4-LC-855 Changing Design of Drainage Pipe Culvert D500.pdf |
| 10/29/2019 | 2808 | 2808 SMC4-WD-423 WD of Deck Slab Spans 11 & 12.pdf |
| 10/29/2019 | 2809 | 2809 SMC4-MS-323 MS of CIP Concrete Piling Diameter D1,2m - Additional Pile at P48.pdf |
| 10/29/2019 | 2810 | 2810 SMC4-LC-856 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work at P7.pdf |
| 10/30/2019 | 2811 | 2811 SMC4-LC-857 Result of Ultrasonic Test of CIP Concrete Pile at P44.pdf |
| 10/30/2019 | 2812 | 2812 SMC4-LC-858 Result of Ultrasonic Test of CIP Concrete Pile at P45.pdf |
| 10/30/2019 | 2813 | 2813 SMC4-MA-565 Frequency Test of VGS for Deck Slab S39R,Parapet S39R, Diaphragm S39, Link Slab P28 P29 ( MoC&TS 21 Oct 2019).pdf |
| 10/30/2019 | 2814 | 2814 SMC4-MA-566 Frequency Test of Reinforcing Steel VGS for Deck Slab of S37-S40 ( MoC&TS 22 Oct 2019).pdf |
| 10/31/2019 | 2815 | 2815 SMC4-MA-567 Addition Capacity Profile of Asphalt Concrete Batching of Plant 656 Co.LTD.pdf |
| 10/31/2019 | 2816 | 2816 SMC4-MA-568 Updated Profile of Material & Mix Design for Drainage Pipes Manufacturer, Material Sourse & Mix Desgn used for Drainage Pipe.pdf |
| 10/31/2019 | 2817 | 2817 SMC4-MA-569 Capacity Profile of Manufacturer for Mineral used for Asphalt Concrete-Bao Minh Mineral Co.LTD.pdf |
| 11/15/2019 | 2818 | 2818 SMC4-MS-320A MS for Diaphragms Construction from P44-P61.pdf |
| 10/31/2019 | 2819 | 2819 SMC4-MS-324 MS of Demolition of Existing Pavement, Site Clearing & Common Excavation.pdf |
| 10/31/2019 | 2820 | 2820 SMC4-MS-325 Report on Loading Test of Pier Head's Supporting System at P10.pdf |
| 10/31/2019 | 2821 | 2821 SMC4-MS-326 Report on Pre-Assembly of Segment 16 to 21 (G1+G2).pdf |
| 10/31/2019 | 2822 | 2822 SMC4-MS-327 Report on Pre-Assembly of Segment 14,15,16.pdf |
| 10/30/2019 | 2823 | 2823 SMC4-LC-860 Target Schedule for Main Bridge.pdf |
| 10/31/2019 | 2824 | 2824 SMC4-LC-859 Acceptance of Sub Structure Construction Stage & Tranfer to Construction of Superstructure Work for P58.pdf |
| 11/2/2019 | 2825 | 2825 SMC4-LC-861 Notice for the Leave of Key Personnel (Foundation. Piling Engineer).pdf |
| 10/31/2019 | 2826 | 2826 3780-PMUTL-DA1 Implementation of Conclusion by MOT's Inspection Team on Environment Protection.pdf |
| 10/31/2019 | 2827 | 2827 490-GM-BQLCTGT Invitation Nov 11,2019 Holding a Coordination Meeting for Construction between HCRR3 & Investment Project for Widening RR3.pdf |
| 11/2/2019 | 2828 | 2828 SMC4-MA-570 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab & Diaphragm S54-S61 ( MoC&TS dated 28 Oct 2019).pdf |
| 11/2/2019 | 2829 | 2829 SMC4-MA-571 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap P7 (MoC&TS dated 29 Oct2019).pdf |
| 11/2/2019 | 2830 | 2830 SMC4-LC-862 Manpower of WD Design (Electrical Engineer).pdf |
| 11/2/2019 | 2831 | 2831 SMC4-MA-572 Capacity of Profile of Supplier & Manufacturer of Angle Steel for Positioning Transverse Rib of ACC Deck Slab-Thai Nguyen JSC.pdf |
| 11/2/2019 | 2832 | 2832 SMC4-MA-573 Additional Profile of Manufacturer & Suppluer Viet Thang LTD for Anchor Bolt D25(M24) for Noise Barrier.pdf |
| 11/2/2019 | 2833 | 2833 SMC4-WD-424 WD of Substructure - Adjustment Pile Cap of P48 (1st).pdf |
| 11/2/2019 | 2834 | 2834 SMC4-WD-425 WD of Steel Concrete Composite Deck Slab of Steel Bridge (1st Revision-2nd).pdf |
| 11/2/2019 | 2835 | 2835 SMC4-AD-99 AD of Super T Girder Span 59 ( P58-P59).pdf |
| 11/2/2019 | 2836 | 2836 SMC4-LC-863 Submission of Weekly Report No.76.pdf |
| 11/2/2019 | 2837 | 2837 SMC4-MS-328 MS of Structure Excavation Abutment A1.pdf |
| 11/4/2019 | 2838 | 2838 SMC4-LC-865 Overall Construction Schedule & Quality Control.pdf |
| 11/2/2019 | 2839 | 2839 SMC4-LC-867 Arrangement of HDPE Corrugate Conduit of ITS System in Median Barrier on the Bridge.pdf |
| 11/6/2019 | 2840 | 2840 SMC4-MS-329 Loading Test Outline of Support System TP12, 13, 14 for Steel Girder Erection of Span P18-P19.pdf |
| 11/2/2019 | 2841 | 2841 SMC4-MS-330 WD of Elevation & Thickness of Deck Slab S60 (P59-P60).pdf |
| 11/2/2019 | 2842 | 2842 SMC4-LC-864 Report on Environment Monitoring in Construction Stage ( 3rd Phase Oct 19 based on S1.43).pdf |
| 11/2/2019 | 2843 | 2843 1193-2919-JICA-YL Disbursement Schedule for the End of Calendar Year 2019.pdf |
| 11/5/2019 | 2844 | 2844 SMC4-LC-866 Withdrawal of Letter SMC4-LC-0844-19 dated 21 October 2019.pdf |
| 11/5/2019 | 2845 | 2845 SMC4-LC-868 Submission of Construction Schedule of November - 2019.pdf |
| 11/5/2019 | 2846 | 2846 SMC4-LC-869 Notification on the Replacement of the Contractor's Chief Engineer at the Fabrication Yard.pdf |
| 11/6/2019 | 2847 | 2847 SMC4-MA-574 Report on Frequency Test of Reinforcing Steel - VGS for Deck Slab Span S37-S40,S60, Link Slab S37-S40, Diaphragm S38-S40 (MoC&TS dated 27 Oct 2019).pdf |
| 11/6/2019 | 2848 | 2848 SMC4-MA-575 Submission of Qualification Documents of Organic Zinc Rich Paint for High Tensile Bolt of Steel Bridge (Epicon Zinc HB2 of Hai Phong JSC).pdf |
| 11/6/2019 | 2849 | 2849 SMC4-MA-576 Report on Frequency Test of Reinforcing Steel VGS for Parapet P19-P30 (MoC&TS dated 28 Oct 2019).pdf |
| 11/6/2019 | 2850 | 2850 SMC4-MS-331 MS of Deck Slab Construction from P44-P61.pdf |
| 11/6/2019 | 2851 | 2851 SMC4-MA-577 Report on Frequency Test of Reingforcing Steel VIS for Super T Girder Span S42, S53 (MoC&TS 28 Oct 2019).pdf |
| 11/6/2019 | 2852 | 2852 SMC4-MA-578 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap, Pier Column & Pier Head of P53-P56( MoC& TS dated 26 Oct 2019).pdf |
| 11/6/2019 | 2853 | 2853 SMC4-LC-870 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P14.pdf |
| 11/6/2019 | 2854 | 2854 SMC4-MA-582 Characteristic Strength of Concrete Class C of Asean - Report 1(26 Jun-12 Sep 2019) & RPNo.2 (14-28 Sep 2019).pdf |
| 11/6/2019 | 2855 | 2855 SMC4-MA-583 Characteristic Strength for Concrete Class C of Transmeco BP- Report No. 8 (2-29 Sep 2019).pdf |
| 11/6/2019 | 2856 | 2856 SMC4-MA-586 Report on Frequency Test of Reinforcing Steel VGS for Pier Head of P49 (MoC&TS 22 Oct 2019).pdf |
| 11/6/2019 | 2857 | 2857 SMC4-MA-587 Characteristic Strength of Concrete Class A of Viet Tiep BP( New Location) - Report No. 4( 1-29 Sep 2019).pdf |
| 11/6/2019 | 2858 | 2858 SMC4-MA-588 Characteristic Strength of Concrete Class Y of Viet Tiep BP - Report 1(10 Jul-17 Sep2019) RP 2( 19-30 Sep 2019).pdf |
| 11/6/2019 | 2859 | 2859 SMC4-WD-426 WD of Road Work- Express Way from Station Km0+568.40 (2nd).pdf |
| 11/6/2019 | 2860 | 2860 SMC4-WD-427 WD of Deck Slab Span 16 (2nd).pdf |
| 11/6/2019 | 2861 | 2861 SMC4-MA-579 Characteristic Strength for Concrete B of Transmeco BP- Report No. 2 (8 Jun -29 Sep 2019).pdf |
| 11/6/2019 | 2862 | 2862 SMC4-MA-580 Characteristic Strength for Concrete Class Y of Transmeco BP- Report No. 8( 3-20 Sep 2019).pdf |
| 11/6/2019 | 2863 | 2863 SMC4-MA-581 Charateristic Strength for Concrete Class Y of Viet Tiep BP(New Location) - Report 1, 2.pdf |
| 11/13/2019 | 2864 | 2864 SMC4-MS-332 MS for Construction of Concrete Wall.pdf |
| 11/7/2019 | 2865 | 2865 SMC4-MS-334 Supplement the Method Drawing for Pier Head at P47.pdf |
| 11/7/2019 | 2866 | 2866 SMC4-525A Notification on Transfering VGS for the Use of Diaphragm Span S54-S61.pdf |
| 11/7/2019 | 2867 | 2867 SMC4-LC-871 Result of Ultrasonic Test of CIP Concrete Pile at P43C.pdf |
| 11/7/2019 | 2868 | 2868 SMC4-LC-872 Result of Ultrasonic Test of CIP Concrete Pile at P32R.pdf |
| 11/7/2019 | 2869 | 2869 SMC4-LC-873 Result of Ultrasonic Test of CIP Concrete Pile at P32L.pdf |
| 11/7/2019 | 2870 | 2870 SMC4-WD-428 WD of Parapet (Left Side) of Span P27-P32.pdf |
| 11/7/2019 | 2871 | 2871 SMC4-MS-333 MS of Pile Cap Abutment A1.pdf |
| 11/7/2019 | 2872 | 2872 SMC4-AD-100 As Built Drawing of Pre Tensioning Pre Stressed Super T Girder of Span 14 (P13-P14).pdf |
| 11/7/2019 | 2873 | 2873 SMC4-AD-101 As Built Drawings of Pre Tensioning Pre Stressed Super T Girder of Span 15 (P14-P15).pdf |
| 11/7/2019 | 2874 | 2874 SMC4-MA-589 Report on Frequency Test of Materials for Cement Concrete at Asean BP(23rd to 25th).pdf |
| 11/7/2019 | 2875 | 2875 SMC4-MA-590 Report on Frequency Test of Material for Cement Concrete at Transmeco BP(45-48th) & Updated Result of Cement R28 (44th).pdf |
| 11/7/2019 | 2876 | 2876 SMC4-MA-591 Report on Frequency Test of Materials for Cement Concrete at Viet Tiep BP(16-19th)& Updated FT of Cement R28 (13-15th).pdf |
| 11/8/2019 | 2877 | 2877 SMC4-LC-874 Request for the Engineer's Instruction on Transtation & Installation of Steel Pier Head of Pier P18.pdf |
| 11/8/2019 | 2878 | 2878 SMC4-LP-58 Clarification of Arrangement of HDPE Corrugate Conduit for ITS System in the Median Barrier on the Bridge.pdf |
| 11/8/2019 | 2879 | 2879 SMC4-MS-335 Permission for Circulation of Vehicles to Transport Overlength Cargo on Road ( Transportation of Steel Pier Head).pdf |
| 11/9/2019 | 2880 | 2880 SMC4-MA-584 Report on Frequency Test of Reinforcing Steel VIS for CIP Concrete Pile at Abutment A1( MoC&TS dated 3 Nov 2019).pdf |
| 11/9/2019 | 2881 | 2881 SMC4-MA-585 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab & Diaphragm S54-S61, Link Slab P53-P61 ( MoC&TS dated 1 Nov 2019).pdf |
| 11/8/2019 | 2882 | 2882 SMC4-LC-876 Engineer's Confirmation for Safety & Environment Satisfaction ( Oct 2019).pdf |
| 11/8/2019 | 2883 | 2883 SMC4-LC-875 Reply to the Engineer's Request for Implementation of Conclussion by MOT's Inspection Team on Environment Protection.pdf |
| 11/8/2019 | 2884 | 2884 SMC4-MS-336 Supplement Method Drawing for Pier Head Construction at P55.pdf |
| 11/8/2019 | 2885 | 2885 SMC4-MS-337 Method Drawing for Erection of Super T Girder at Spans S15 (P14-P15) & S14 9P13-P14).pdf |
| 11/8/2019 | 2886 | 2886 SMC4-MS-338 Method Statement of Structure Excavation Pier P43C.pdf |
| 11/9/2019 | 2887 | 2887 SMC4-LC-877 Submission of Weekly Report No.77.pdf |
| 11/9/2019 | 2888 | 2888 SMC4-LC-878 Withdrawal of the letter LC-0874 dated 7 Nov 2019.pdf |
| 11/9/2019 | 2889 | 2889 SMC4-MA-592 Notification on Transferring VGS for Pier Head of P10.pdf |
| 11/9/2019 | 2890 | 2890 SMC4-MA-593 Report on Frequency Test of Reinforcing Steel VIS for Supet T Girder S41, S50 ( MoC& TS dated 30 Oct 2019).pdf |
| 11/9/2019 | 2891 | 2891 SMC4-MA-594 Report on Friction Test of Galbon S-HB PZ L1 Paint of Hai Phong JSC for Steel Bridge.pdf |
| 11/9/2019 | 2892 | 2892 SMC4-LC-879 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work for P13.pdf |
| 11/9/2019 | 2893 | 2893 SMC4-WD-429 WD of Structure Excavation for Abutment A1 (1st Revision).pdf |
| 11/11/2019 | 2894 | 2894 SMC4-MS-316A MS of Structure Excavation Pier P43 (L-R).pdf |
| 11/11/2019 | 2895 | 2895 SMC4-MS-339 Painting Method at Contact Surface of Bolted Connection with Filler Plate.pdf |
| 11/11/2019 | 2896 | 2896 SMC4-MS-340 MS of Pier Column from P43-P45.pdf |
| 11/11/2019 | 2897 | 2897 SMC4-WD-430 WD of Electric & Lighting -Gerneral View of Electric & Lighting for Expressway (1st).pdf |
| 11/11/2019 | 2898 | 2898 SMC4-WD-431 WD of Structure Excavation for Pierr P43C (1st).pdf |
| 11/11/2019 | 2899 | 2899 SMC4-WD-432 WD of Superstructure-Deck Slab for Span of S9 (1st).pdf |
| 11/11/2019 | 2900 | 2900 SMC4-WD-433 WD of Detail of Pipe Culvert D500& & Catch Basin Type A (CB-A) under Viaduct Section A1-P61.pdf |
| 11/11/2019 | 2901 | 2901 SMC4-AD-102 AD of CIP Concrete Pile D1.2m of Pier P43R.pdf |
| 11/11/2019 | 2902 | 2902 SMC4-LC-880 Report on the Phenomenon & Treatment Solution for CIP Concrete Pile D1.2m-Pile No.8-P45.pdf |
| 11/9/2019 | 2903 | 2903 3828-3745 PMUTL-DHDA1 Installation of Noise Barrier on PK1 & PK2.pdf |
| 11/11/2019 | 2904 | 2904 SMC4-LC-881 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P43R.pdf |
| 11/12/2019 | 2905 | 2905 SMC4-MA-595 Updated Profile Minute of Inspection of Ha Thanh Factory & The Testing Result of Drainage Pipe D500 Material of Ha Thanh Concrete JSC.pdf |
| 11/12/2019 | 2906 | 2906 SMC4-LP-59 Notice of Actual Site Visit of Students & Lecturers of Transport & Communication University.pdf |
| 11/12/2019 | 2907 | 2907 SMC4-LC-882 Notice of Claim for Extension of Time for Completion of Project & Addtional Cost Due to Design Modification for Off Ramp HQV-B.pdf |
| 11/12/2019 | 2908 | 2908 SMC4-LC-883 Updated Organization Chart & Job Description of the Key Management & Key Personnel.pdf |
| 11/12/2019 | 2909 | 2909 SMC4-LT-31 Updated Equipment of Site Laboratary LAS XD 668 Quality Verification for Asphalt Concrete Works.pdf |
| 11/12/2019 | 2910 | 2910 SMC4-RP-118 Report on Excavation for Survey of Underground Utilities at MSE Wall & Concrete Wall Behind Abutment A1.pdf |
| 11/12/2019 | 2911 | 2911 SMC4-MS-341 Report on Loading Test of Pier Head Supporting System at P47.pdf |
| 11/12/2019 | 2912 | 2912 SMC4-AD-103 AD of Superstructure-Steel Bridge - Detail of Segment 15 - Rigid Pier Head P18.pdf |
| 11/12/2019 | 2913 | 2913 SMC4-MS-340A-MS for Lower Part of Pier Head from P7-P8.pdf |
| 11/13/2019 | 2914 | 2914 SMC4-MA-596 Report on Frequency Test of Reinforcing Steel VGS for Pier Column & Pier Head P53-P55( MoC&TS dated 02 Nov 2019).pdf |
| 11/13/2019 | 2915 | 2915 SMC4-MA-597 Report on Frequency Test of Reinforcing Steel VGS Deck Slab S40, Parapet S40R, Diaphragm S40,Link Slab P35 P37R P38R & Conter Median S29,S30 ( MoC&TS dated 02 Nov 2019).pdf |
| 11/20/2019 | 2916 | 2916 SMC4-MA-598 Report on Frequency Test of Welding Material- Welding Wire SF71( MoC&TS dated 14 Oct 2019) for Steel Bridge.pdf |
| 11/13/2019 | 2917 | 2917 SMC4-LC-884 Capacity Profile of Subcontractor Hanoi Infrastructure & Culture Works Construction JSC.pdf |
| 11/18/2019 | 2918 | 2918 SMC4-LC-885 Report on Environment Monitoring in Construction Stage, 1st Phase in Nov 2019 based on S1.43).pdf |
| 11/12/2019 | 2919 | 2919 1351-GM-BGTVT Meeting on Treatment of Drainage Pipe D1250 of the Ministry of Public Security.pdf |
| 11/14/2019 | 2920 | 2920 SMC4-MC-21 Interim Payment Certificate No.16 ( Peried 01 Oct 2019 to 31 Oct 2019).pdf |
| 11/14/2019 | 2921 | 2921 SMC4-MA-600 Report on Frequency Test of Elastomeric Bearing by Kawakin Core Tech VN & Supplied THQ Global JSC.pdf |
| 11/14/2019 | 2922 | 2922 SMC4-MA-601 Report on Frequency Test of Hai Phong Paint Material of Hai phng for Steel Bridge.pdf |
| 11/14/2019 | 2923 | 2923 SMC4-MA-599 Proposal for Noise Barrier Manufacturered by Nippon & Suminkin-Supplied by Nam Anh.pdf |
| 11/14/2019 | 2924 | 2924 SMC4-LC-886 Additional Machine Mobilization Document of Thanh Long JSC for Transportation of Steel Girder - 2nd.pdf |
| 11/14/2019 | 2925 | 2925 SMC4-LC-887 Estimate Overall Schedule (without Off Ramp HQV-B).pdf |
| 11/14/2019 | 2926 | 2926 SMC4-WD-434 WD of Parapet (Right Side) of Spans P27-P32.pdf |
| 11/27/2019 | 2927 | 2927 SMC4-WD-435 WD of Detail of Catch Basin & U-ditch of Drainage System under Viaduct Section at P18-P25 (2nd).pdf |
| 11/21/2019 | 2928 | 2928 SMC4-LC-891 Report of Phenomenon on the Surface of Pier Column P18 after Erection of Steel Pier Head.pdf |
| 11/15/2019 | 2929 | 2929 SMC4-LC-888 Withdrawal of the Letter Regarding Profile of Subcontractor Hai Anh Company.pdf |
| 11/15/2019 | 2930 | 2930 SMC4-LC-892 Unit Price Comparison Table for Design Change of Drainage Pipe Culvert D500.pdf |
| 11/15/2019 | 2931 | 2931 SMC4-LC-890 Submission of Monthly Report No.18.pdf |
| 11/15/2019 | 2932 | 2932 SMC4-MS-342 Report on Pre-Assembly of Segment 16 to 21 (G3+G4).pdf |
| 11/15/2019 | 2933 | 2933 SMC4-LC-889 Submission of Weekly Report No.78.pdf |
| 11/15/2019 | 2934 | 2934 SMC4-MS-343 Calculation of Tendon Cable Elonggation for Pier Head P10.pdf |
| 11/15/2019 | 2935 | 2935 SMC4-MS-344 Method Drawing for Erection of Super T Girder at Span S41 (P40-P41).pdf |
| 11/15/2019 | 2936 | 2936 SMC4-MS-345 MS for Lower Part of Pier Head P43-P45.pdf |
| 11/15/2019 | 2937 | 2937 SMC4-MA-602 Characteristic Strength for Concrete Class G of Transmeco BP- Report 1 ( from 28 Nov 2018 to 21 Sep 2019).pdf |
| 12/9/2019 | 2938 | 2938 SMC4-MS-301A Painting Method at Joint & High Strength Bolt.pdf |
| 11/21/2019 | 2939 | 2939 SMC4-MS-320B MS for Diaphragms Construction from Abutment A1-P16.pdf |
| 11/15/2019 | 2940 | 2940 SMC4-LC-893 Report on the Phenomenon & Treatment Solution for CIP Concrete Pile D1.2m-Pile No.8 of P45.pdf |
| 11/15/2019 | 2941 | 2941 SMC4-LC-894 Reply to Engineer's Letter about the Contractor's Proposal for Installation of Crack Insdustion Joint on the A1 Abutment Wall.pdf |
| 11/15/2019 | 2942 | 2942 SMC4-MS-346 Report on Loading Test of Pier Head's Supporting System at P55.pdf |
| 11/15/2019 | 2943 | 2943 SMC4-WD-436 WD of Superstructure-Deck Slab for Span S8 & Link Slab P7 (1st).pdf |
| 11/15/2019 | 2944 | 2944 10826-BGTVT-CQLXD Design Change to Raise Up Elevation of Pile Cap at Abutment A1.pdf |
| 11/16/2019 | 2945 | 2945 SMC4-WD-437 WD of Structure Excavation for Pier P48.pdf |
| 11/16/2019 | 2946 | 2946 SMC4-MS-347 MS of Structure Excavation Pier P48.pdf |
| 11/16/2019 | 2947 | 2947 3980-PMUTL-DA1 Arrangement of HDPE Conduits in Central Median on Viaduct.pdf |
| 11/19/2019 | 2948 | 2948 SMC4-LC-897 Report on Discovered Underground Drainage Pipe D1250 Near P43C.pdf |
| 11/28/2019 | 2949 | 2949 SMC4-WD-438 WD of Median Barrier of Span P29-P30.pdf |
| 11/19/2019 | 2950 | 2950 SMC4-MS-348 Report on Loading Test of Temporary Support TP12,TP13,TP14 (G3+G4) for steel girder erection.pdf |
| 11/18/2019 | 2951 | 2951 3914 TB-BQLDATL Notice on Conclusions given by PMU Thang Long In the meeting to review the Implementation.pdf |
| 11/19/2019 | 2952 | 2952 SMC4-WD-439 WD of the Elevation & Thickness of Deck Slab at Span S40 (P39-P40).pdf |
| 11/19/2019 | 2953 | 2953 SMC4-WD-440 WD of Gegeral Layout of Noise Barrier (2nd ).pdf |
| 11/30/2019 | 2954 | 2954 SMC4-MS-349 Method Drawing for Erection of Super T Girder at Span S13 (P12-P13).pdf |
| 12/3/2019 | 2955 | 2955 SMC4-MS-350 MS of Structure Excavation for Abutment A1 ( Rev 03).pdf |
| 11/19/2019 | 2956 | 2956 SMC4-LC-898 Plan for Connection of Drainage System at Started Point of Viaduct.pdf |
| 11/25/2019 | 2957 | 2957 SMC4-LC-899 Capacity Profile of the Subcontractor Vonta Vietnam LTD.pdf |
| 11/19/2019 | 2958 | 2958 SMC4-LC-896 Acceptance of Substructure Construction Stage & Transfer to Superstructure Work for P41.pdf |
| 11/19/2019 | 2959 | 2959 SMC4-LC-895 Acceptance of Substructure Construction Stage & Transfer to Superstructure Work for P57.pdf |
| 11/21/2019 | 2960 | 2960 SMC4-MA-603 Notification on Transfering VGS Steel for Use of Pile Cap, Column of Pier P44-P45.pdf |
| 11/21/2019 | 2961 | 2961 SMC4-MA-604 Electrical Material of Vonta Limitted Company Lighting Pole 11m, 7m & Bolt.pdf |
| 11/21/2019 | 2962 | 2962 SMC4-LC-898 Steel Bridge Schedule in November and December.pdf |
| 11/21/2019 | 2963 | 2963 SMC4-AD-104 As-built Drawings of Pre-tensioning Pre-stressed Super-T Girder Span 58(P57-P58).pdf |
| 11/21/2019 | 2964 | 2964 SMC4-AD-105 As-built Drawings of Pre-tensioning Pre-stressed Super-T Girder Span 41(P40-P41).pdf |
| 11/22/2019 | 2965 | 2965 SMC4-WD-441 WD the Top Elevation of Parapet & Median Barrier at Spans S27(P26-P27) toS30 (P29-P30).pdf |
| 11/22/2019 | 2966 | 2966 SMC4-MS-351 Supplement Method Drawing for Pier Head Construction at P49.pdf |
| 11/22/2019 | 2967 | 2967 4035 PMUTL-DA1 Implementation of Working Minutes dated November 1,2019 between Widening Project and Viaduct Project.pdf |
| 11/22/2019 | 2968 | 2968 SMC4-LC-901 Submission of Weekly Report No.79.pdf |
| 11/22/2019 | 2969 | 2969 SMC4-LC-902 Result of Ultrasonic Test of CIP Concrete Pile at Abutment A1.pdf |
| 11/22/2019 | 2970 | 2970 SMC4-LC-903 Result of Ultrasonic Test of Additional CIP Concrete Pile at P48.pdf |
| 11/22/2019 | 2971 | 2971 SMC4-LC-904 Submission of Video CD No.3 (6 Months Period from May to Oct 2019).pdf |
| 11/22/2019 | 2972 | 2972 SMC4-LC-442 WD of Deck Slab Spans 54, 57, 58 (2nd).pdf |
| 11/22/2019 | 2973 | 2973 SMC4-WD-443 WD of Deck Slab Span 49, 50, 53 (2nd).pdf |
| 11/28/2019 | 2974 | 2974 SMC4-WD-444 WD of Parapet Right Side Span P27-P32 (2nd).pdf |
| 11/28/2019 | 2975 | 2975 SMC4-WD-445 WD of Parapet (Left Side) of Spans P27-P32 (2nd).pdf |
| 11/22/2019 | 2976 | 2976 SMC4-LC-905 Report on Ultrasonic Test of Concrete Surface of Pier Column P18.pdf |
| 11/23/2019 | 2977 | 2977 SMC4-MA-605 Test Result of Material for MSE Retaining Wall System Include Start Bar, Lifting, Insert, Bearing Pads.pdf |
| 11/23/2019 | 2978 | 2978 SMC4-AD-106 AD of CIP Concrete Pilling D1.2m of Pier P44.pdf |
| 11/25/2019 | 2979 | 2979 SMC4-MA-606 Report on Frequency Test of Reinforcing Steel VIS Bar for Super T Girder of Span S8 ( MoC& TS dated 22 Nov 2019).pdf |
| 11/25/2019 | 2980 | 2980 4004-QD-BQLDATL Decision on the Appproval of Adjustment Design to Increase Elecation of A1 Abutment under PK1.pdf |
| 11/26/2019 | 2981 | 2981 SMC4-AD-107 As-Built Drawings of Pre-Tensioning Pre-Stressed Super T Girder of Span 12 (P11-P12).pdf |
| 11/26/2019 | 2982 | 2982 SMC4-AD-108 As-Built Drawings of Pre-Tensioning Pre-Stressed Super T Girder of Span 13 (P12-P13).pdf |
| 12/9/2019 | 2983 | 2983 SMC4-WD-447 Working Drawing of Parapet of Spans P23-P27.pdf |
| 11/26/2019 | 2984 | 2984 SMC4-WD-446 WD of Detail for Catch Basin & U-Ditch of Drainage System under Viaduct Section P26-P34.pdf |
| 11/26/2019 | 2985 | 2985 SMC4-MS-352 MS of Deck Slab Construction from A1-P16.pdf |
| 11/26/2019 | 2986 | 2986 SMC4-MS-353 Report on Loading Test of Pier Head's Supporting System at P51.pdf |
| 11/26/2019 | 2987 | 2987 SMC4-LC-908 Notice of Equipment Demobilization- Crane Kolbeco 7055 & Excavator Komasu PC-200 at P7 Area under Scope of Co.407.pdf |
| 12/10/2019 | 2988 | 2988 SMC4-LC-909 Report on Environment Monitoring in Construction Stage 2nd Phase in Nov 2019 based on S1.43.pdf |
| 11/26/2019 | 2989 | 2989 SMC4-LC-910 Supplement of 5 Permits from DRVN from 9 Nov to 2 Dec, from 20 Nov to 20 Dec, from 28 Nov to 11 Dec, from 23 Nov to 23 Dec 2019.pdf |
| 11/26/2019 | 2990 | 2990 SMC4-LC-906 Acceptance of C.I.P Concrete Pile Foundation Construction Stage & Transfer to Construciton of Substructure Work for P44.pdf |
| 11/26/2019 | 2991 | 2991 SMC4-LC-907 Acceptance of Sub-Structure Construction Stage & Transfer to Construction of Superstructure Work for P12.pdf |
| 11/26/2019 | 2992 | 2992 18-CDECE-KHHIV-MDNTL Plan on the Implementation of HIV-AIDS Prevention Program on Dec 2019.pdf |
| 11/26/2019 | 2993 | 2993 MOT Invitation.pdf |
| 11/26/2019 | 2994 | 2994 Addendum No.03.pdf |
| 11/27/2019 | 2995 | 2995 SMC4-LC-911 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for P45.pdf |
| 11/27/2019 | 2996 | 2996 SMC4-AD-109 AD of CIP Concrete Piling D1.2m of P45.pdf |
| 11/27/2019 | 2997 | 2997 SMC4-MS-354 MS for Painting of Concrete Surface for Abutment & Pier.pdf |
| 11/27/2019 | 2998 | 2998 SMC4-MS-355 MS of Structure Excavation Pier P43C (2nd).pdf |
| 11/27/2019 | 2999 | 2999 SMC4-MS-356 MS of Pile Cap P43C.pdf |
| 11/27/2019 | 3000 | 3000 SMC4-LC-912 Report on Discovering a Tomb at P44.pdf |
| 11/28/2019 | 3001 | 3001 SMC4-WD-448 WD of Elevation & Thickness of Deck Slab at Spans S4 (P13-P14), S15 (P14-P15), S59 (P58-P59).pdf |
| 11/28/2019 | 3002 | 3002 SMC4-WD-449 WD of Deck Slab for Span S7 (1st).pdf |
| 11/28/2019 | 3003 | 3003 SMC4-LC-898A Result of Tip Contact Checking Test of CIP Pile C5-P48.pdf |
| 11/28/2019 | 3004 | 3004 SMC4-LC-899A Result of Tip Contact of Concrete Pile C5-P44.pdf |
| 12/10/2019 | 3005 | 3005 SMC4-WD-450 WD of General Layout of Drainage System Km0+400-Km2+812.50(1st Rev).pdf |
| 11/29/2019 | 3006 | 3006 SMC4-MA-608 Notification on Trasnfering VGS steel for Link Slab P35.pdf |
| 11/29/2019 | 3007 | 3007 SMC4-MA-609 Notification on Transferring VGS steel for Deck Slab, Diaphragm S12-S15.pdf |
| 11/29/2019 | 3008 | 3008 SMC4-MA-610 Notification on Transferring VGS for the Use of Pier Head of P9.pdf |
| 11/29/2019 | 3009 | 3009 SMC4-MA-611 Notification on Transferring VGS for Pile Cap,. Pier Column, Pier Head of P42, P43.pdf |
| 11/29/2019 | 3010 | 3010 SMC4-MA-612 Submission of Updated Profile of Paraweb Strip Material.pdf |
| 11/29/2019 | 3011 | 3011 SMC4-RP-119 Report on Loading Test of Pier Head Supporting System at P49.pdf |
| 11/29/2019 | 3012 | 3012 SMC4-MS-353A MS for Diaphargm Construction from Pier P40-P44.pdf |
| 11/29/2019 | 3013 | 3013 SMC4-WD-451 WD of Substructure - Design Changed Abutment A1.pdf |
| 11/29/2019 | 3014 | 3014 SMC4-WD-452 WD of Design Change of CIP Concrete Pile for Abutment A1 (1st).pdf |
| 11/29/2019 | 3015 | 3015 SMC4-WD-453 WD of Structure Excavation for Abutment A1 (1st Rev-2nd).pdf |
| 11/29/2019 | 3016 | 3016 SMC4-WD-454 WD of Detail of Noise Barrier.pdf |
| 11/29/2019 | 3017 | 3017 SMC4-WD-455 WD of Substructure - Design Changed Pile Cap of Abutment A1.pdf |
| 11/29/2019 | 3018 | 3018 SMC4-WD-456 WD of Median Barrier of Spans P27-P29.pdf |
| 11/30/2019 | 3019 | 3019 SMC4-MA-607 Report on Frequency Test of Reinforcing Steel VIS for Super T Girder Span S46 (MoC&TS dated 22 Nov 2019).pdf |
| 11/30/2019 | 3020 | 3020 SMC4-LC-913 Report on Results of Pile Head Treatment Work for Pile No.8 P45.pdf |
| 12/2/2019 | 3021 | 3021 SMC4-MS-353B Report on Loading Test of Pier Head's Supporting System at P9.pdf |
| 11/30/2019 | 3022 | 3022 SMC4-LC-914 Notice of Environmental Monitoring in Dec 2019 at Construction Phase.pdf |
| 11/30/2019 | 3023 | 3023 SMC4-MS-357 Method Statement of Abutment A1 Column.pdf |
| 11/30/2019 | 3024 | 3024 SMC4-MS-358 Method Statement of Pile Cap Pier P48.pdf |
| 11/30/2019 | 3025 | 3025 SMC4-LC-915 Engineer's for Safety & Environment Satisfaction (1st -30th Nov , 2019.pdf |
| 12/2/2019 | 3026 | 3026 SMC4-MC-22 Interimpayment Certificate No.17 ( Period 1st Nov 2019 to 30th Nov 2019).pdf |
| 12/2/2019 | 3027 | 3027 SMC4-RP-120 Report on the Result of MSE Panel Trial Fabrication.pdf |
| 12/2/2019 | 3028 | 3028 SMC4-AD-110 AD of CIP Concrete Pile P48.pdf |
| 12/2/2019 | 3029 | 3029 SMC4-LC-918 Additional Supervision Cost of Engineer'Staff (Sep 2019).pdf |
| 12/2/2019 | 3030 | 3030 SMC4-MS-359 Supplement for Calculation of Tendon Cable Elongation of Pier Head P44-P57.pdf |
| 12/2/2019 | 3031 | 3031 SMC4-LC-917 Submission of Weekly Report No.80.pdf |
| 12/2/2019 | 3032 | 3032 SMC4-LC-916 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction Work for P48.pdf |
| 12/4/2019 | 3033 | 3033 SMC4-WD-457 WD of Detail of Catch Basin & U Ditch of Drainage System under Viaduct P11-P17.pdf |
| 12/4/2019 | 3034 | 3034 SMC4-WD-458 WD of Substructure - Approach Slab of Abutment A1.pdf |
| 12/4/2019 | 3035 | 3035 SMC4-MS-360 Calculation of Tendon Cable Elongation for Pier Head P9.pdf |
| 12/5/2019 | 3036 | 3036 SMC4-MA-613 Report on Frequency Test of Reinforcing Steel VGS for Pile Cap Pier Column Pier Head of P32, P43, P50 ( MoC& TS da |
| 12/5/2019 | 3037 | 3037 SMC4-MA-614 Report on Frequency Test of Reinforcing Steel VGS for Deck, Link Slab Span P41, Pile Cap Pier Column & Pier Head P |
| 12/5/2019 | 3038 | 3038 SMC4-WD-459 WD of Superstructure-Deck Slab for Span S44 (1st).pdf |
| 12/6/2019 | 3039 | 3039 SMC4-LC-920 Acceptance of Substruction Construction Stage & Transfer to Construction of Next Stage Steel Structure Work for P |
| 12/7/2019 | 3040 | 3040 SMC4-LC-919A Submission of Weekly Report No.81.pdf |
| 12/9/2019 | 3041 | 3041 SMC4-LC-868A Acceptance of Substructure Stage & Transfer to Construction of Next Stage Steel Structure Work for P18.pdf |
| 12/17/2019 | 3042 | 3042 SMC4-MA-615 Using Non-Woven Geotextile Vietnam Geotextile JSC for Mechanical Stabilized Earth (MSE) Retaining Wall.pdf |
| 12/6/2019 | 3043 | 3043 SMC4-MA-616 Report on Supplementary & Completion of Remainings of the Asphalt Concrete BP.pdf |
| 12/6/2019 | 3044 | 3044 SMC4-LC-922 Report on Environment Monitoring in Construction Stage 3rd in Nov 2019 ( Base on S1.43).pdf |
| 12/6/2019 | 3045 | 3045 SMC4-LC-923 Submission of Construction Schedule of Dec 2019.pdf |
| 12/6/2019 | 3046 | 3046 SMC4-AD-111 AD of CIP Concrfete Piling D1.2m of P43C.pdf |
| 12/6/2019 | 3047 | 3047 SMC4-MS-362 MS of Deck Slab Construction from P40-P44.pdf |
| 12/6/2019 | 3048 | 3048 SMC4-MS-361 MS for Pier Head Construction of Pier Head & Outline of the Loading Test of Pier Head's Supporting System from P44 |
| 12/7/2019 | 3049 | 3049 SMC4-LC-924 Acceptance of Substructure Constructure Stage & Transfer to Construction of Superstructure Work for P56.pdf |
| 12/7/2019 | 3050 | 3050 SMC4-LC-925 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for |
| 12/7/2019 | 3051 | 3051 SMC4-MA-619 Report on Frequency Test of Materials for Cement Concrete at Viet Tiep BP (2-thto21th) & Updated Frequency Test of |
| 12/7/2019 | 3052 | 3052 SMC4-MA-620 Report on Frequency Test of Material for Cement Concrete at ASEAN BP (26th to 27th) & Updated Result of Cement R28 |
| 12/7/2019 | 3053 | 3053 SMC4-MA-621 Report on Frequency Test of Manterial for Cement Concrete at Transmeco BP(49th to 50th) & Updated Result of Cement |
| 12/7/2019 | 3054 | 3054 SMC4-WD-460 WD of General Layout of Parapet& Barrier (for Main Bridge) (1st Rev).pdf |
| 12/7/2019 | 3055 | 3055 SMC4-WD-461 WD of Parapet of Spans P19-P23.pdf |
| 12/7/2019 | 3056 | 3056 SMC4-WD-462-WD of Detail of Expansion Joint (for Main Bridge) (3rd).pdf |
| 12/7/2019 | 3057 | 3057 SMC4-MS-363 Method Drawing for Erection of Super T Girder at S47 (P46-P47), S54 (P53-P54), S57 (P56-P57).pdf |
| 12/7/2019 | 3058 | 3058 SMC4-LC-927 Resubmission of Schedule for Steel Bridge (3rd).pdf |
| 12/7/2019 | 3059 | 3059 SMC4-MA-617 Report on Frequency Test of Reinforcing Steel VGS for Pier Head P7, P8, P45, A1- Deck Slab Diaphragm S12-S15, MSE |
| 12/7/2019 | 3060 | 3060 SMC4-MA-618 Report on Frequency Test of Reinforcing Steel VGS for Pier Column Pier Head of P44, P45-Diaphargm S47- Parapet of |
| 12/7/2019 | 3061 | 3061 SMC4-MA-622 Report on Frequency Test of Reinforcing Steel VGS for Diaphragm S54-S61, Parapet S19R-S30R (MoC&TS dated 02 Dec 20 |
| 12/7/2019 | 3062 | 3062 SMC4-MA-623 Report on Frequency Test of Reinforcing Steel VGS for Super T Girder of Span S54-S58 (MoC&TS dated 3 Dec 2019).pdf |
| 12/7/2019 | 3063 | 3063 SMC4-MA-624 Report on Frequency Test of Organic Zinc Rich Paint (Epicon Zinc HB2) of High Tensile Bolt for Steel Bridge ( Date |
| 12/7/2019 | 3064 | 3064 SMC4-MA-625 Characteristic Strength for Concrete Class C of ASEAN BP (new Location) - Report 3(3-31 Oct 2019).pdf |
| 12/7/2019 | 3065 | 3065 SMC4-MA-626 Characteristic Strength for Concrete Class C of Transmeco BP- Report 9 (1-31 Oct 2019).pdf |
| 12/7/2019 | 3066 | 3066 SMC4-MA-627 Characteristic Strength for Concrete Class Y of Viet Tiep BP (New Location) - Report 3 (2-25 Oct 2019).pdf |
| 12/7/2019 | 3067 | 3067 SMC4-MA-628 Characteristic Strength for Concrete Class B of Transmeco BP- Report 3 (1-30 Oct 2019).pdf |
| 12/7/2019 | 3068 | 3068 SMC4-MA-629 Characteristic Strength for Concrete Class A of Viet Tiep BP (New Location) - Report 5 (1-31 Oct 2019).pdf |
| 12/7/2019 | 3069 | 3069 SMC4-MA-630 Characteristic Strength for Concrete Class C of Viet Tiep BP- Report 3 (4-31 Oct 2019).pdf |
| 12/7/2019 | 3070 | 3070 SMC4-LC-928 Equipment Mobilization Document for the Work Scope of 422 Co..pdf |
| 12/9/2019 | 3071 | 3071 SMC4-MA-631 Report on Frequency Test of Shear Stud Connector for Steel Bridge Taking Sample dated 26 Oct 2019 & Testing Dated |
| 12/9/2019 | 3072 | 3072 SMC4-MA-632 Material-Reinforced Concrete Pipes D400, Precast Bearing D400, D500, Dicth U, Catch Basin Used for Drainage System |
| 12/9/2019 | 3073 | 3073 SMC4-LC-926 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work for P46.pdf |
| 12/9/2019 | 3074 | 3074 SMC4-LC-929 Acceptance of substructure Constructure Stage & Transfer to Construction of Superstructure Work for P47.pdf |
| 12/9/2019 | 3075 | 3075 SMC4-AD-112 AD of CIP Concrete Piling D1.2m of P32L.pdf |
| 12/9/2019 | 3076 | 3076 SMC4-AD-113 AD of Super T Girder Span 47 (P46-P47).pdf |
| 12/9/2019 | 3077 | 3077 SMC4-WD-463 WD of Superstructure - Deck Slab for Span S45 (1st ).pdf |
| 12/9/2019 | 3078 | 3078 SMC4-MS-364 Girder Transportation to Site.pdf |
| 12/10/2019 | 3079 | 3079 SMC4 -MA-633 Frequency Test of Reinforcing Steel VIS for Super T Girder of Span S7 (MoC&TS dated 30 Nov 2019).pdf |
| 12/10/2019 | 3080 | 3080 SMC4-MC-23 Application for Retention Money Payment ceritificate(Period 11.5.18-20.11.19).pdf |
| 12/10/2019 | 3081 | 3081 SMC4-LC-932 Proposal for Approval of Capacity Profile of Subcontractor Nam Anh Technology construction Equipment Co.,ltd.pdf |
| 12/10/2019 | 3082 | 3082 SMC4-MS-360A Report on Loading Test of Pier Head's Supporting System at Pier P54.pdf |
| 12/10/2019 | 3083 | 3083 SMC4-MS-364A MS for Construction of Pier Head & Outline for Loading Test of Pier Head's Supporting System from P7-P8.pdf |
| 12/23/2019 | 3084 | 3084 SMC4-MS-365 Resubmission of MS of Mock Up for SCC Deck Slab.pdf |
| 12/10/2019 | 3085 | 3085 SMC4-MS-366 Resubmission of MS of Pile Cap Abutment A1 (2nd Rev).pdf |
| 12/10/2019 | 3086 | 3086 SMC4-WD-464 WD of Backfill for Abutment A1 and Piers P43C, P48 (1st Rev).pdf |
| 12/10/2019 | 3087 | 3087 SMC4-MA-634 Use Aggregate Subbase Course Type II Dmax-37.5mm for Subgrade Material.pdf |
| 12/10/2019 | 3088 | 3088 SMC4-LC-930 Report on Grouting Work at the Pile No.5 P43C.pdf |
| 12/11/2019 | 3089 | 3089 SMC4-LC-933 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for |
| 12/11/2019 | 3090 | 3090 SMC4-MA-635 Report on Frequency Test of PC Strand of Epoxy Coated PC Strand (12th) Zhemao LTD Used for Pier Head.pdf |
| 12/11/2019 | 3091 | 3091 SMC4-LC-931 Summary Table of Waste Disposal Implemented by the Subcontractors at Nguyen Khe from July.pdf |
| 12/11/2019 | 3092 | 3092 SMC4-LC-919 Submission of Monthly Report No.19.pdf |
| 12/11/2019 | 3093 | 3093 SMC4-AD-115 AD of CIP Concrete Pilling D1.2m of Abutment A1.pdf |
| 12/11/2019 | 3094 | 3094 SMC4-AD-114 AD of Pre Tesioning Pre Stressed Super T Girder Span 57 (P56-P57).pdf |
| 12/11/2019 | 3095 | 3095 SMC4-LC-934 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for |
| 12/12/2019 | 3096 | 3096 SMC4-MA-636 Electrical Material of Vonta LTD - HDPE Conduit Pipe.pdf |
| 12/12/2019 | 3097 | 3097 SMC4-MA-637 Manufacturer & Supplier of Deck Drain Box Trash Rack, Supporting & Steel Gutter.pdf |
| 12/12/2019 | 3098 | 3098 SMC4-MA-638 Capacity Profile of Supplier & Manufacturer of Angle Steel for Positioning Transverse Rib of SCC Deck Slab Steel B |
| 12/12/2019 | 3099 | 3099 SMC4-MS-367 Method Drawing for Erection of Super T Girder at Span S42 ( P41-P42).pdf |
| 12/12/2019 | 3100 | 3100 SMC4-WD-465 WD the Top Elevation of Parapet & Median Barrier at Spans S21(P20-P21) to S26 (P25-P26).pdf |
| 12/12/2019 | 3101 | 3101 818-CQLXD-DB1 Report on Results of Site Inspection at the HRR3 Construction Project MDSTL Section.pdf |
| 12/13/2019 | 3102 | 3102 SMC4-LC-935 Notice for Leave for Key Personnel (Project Manager).pdf |
| 12/13/2019 | 3103 | 3103 SMC4-LC-936 Report on Environment Monitoring In Construction Stage 1st Time in Dec 2019 Based on S1.43.pdf |
| 12/13/2019 | 3104 | 3104 SMC4-WD-470 WD of Detail of Catch Basin & U Ditch of Drainage System Under Viaduct Section P35-P41.pdf |
| 12/13/2019 | 3105 | 3105 SMC4-WD-469 WD of Miscellaneous Parapet of MSE Wall (1st).pdf |
| 12/13/2019 | 3106 | 3106 SMC4-WD-468 WD of Median Barrier of Span P19-P23.pdf |
| 12/13/2019 | 3107 | 3107 SMC4-WD-467 WD of Elevation & Thickness of Deck Slab at Span S41 (P40-P41), S58 (P57-P58).pdf |
| 12/13/2019 | 3108 | 3108 SMC4-WD-466 WD of Median Barrier of Spans P23-P27.pdf |
| 12/13/2019 | 3109 | 3109 SMC4-LC-747A Report of Crack Phenomenon on Pier Column of the Pier P25.pdf |
| 12/16/2019 | 3110 | 3110 SMC4-LC-939 Cost Estimate of Structure Excavation Item.pdf |
| 12/16/2019 | 3111 | 3111 SMC4-MS-368 Resubmission of MS of Steel Girder Erection 92nd).pdf |
| 12/16/2019 | 3112 | 3112 SMC4-AD-116 AD of Pre Tensioning Pre Stressed Super T Girder of Span 42 (P41-P42).pdf |
| 12/16/2019 | 3113 | 3113 SMC4-MA-642 Report on Frequency Test of PC Strand for Super T Girder (36th).pdf |
| 12/20/2019 | 3114 | 3114 SMC4-MA-640 Report on Frequency Test of Galbon S-HB PZ L1 of Hai Phong Paint JSC ( Sampling 22 Nov 2019).pdf |
| 12/16/2019 | 3115 | 3115 SMC4-MA-639 Material-Reinforced Concrete Pipe D400, Precast Bearing D400, D500 Used for Drainage System of Ha Thanh Concrete J |
| 12/16/2019 | 3116 | 3116 SMC4-MA-641 Additional Submission of Manufacturer of Bridge Expansion Joints.pdf |
| 12/16/2019 | 3117 | 3117 SMC4-LC-938 Withdrawal of letter SMC4-MA-0632 dated 7Dec2019.pdf |
| 12/16/2019 | 3118 | 3118 SMC4-LC-937 Notice on New Year Holiday Schedule of the Contractor.pdf |
| 12/16/2019 | 3119 | 3119 SMC4-WD-471 Changing L40x40x5mm Type Shaped Steel to L50x50x5mm of SCC Seck Slab.pdf |
| 12/16/2019 | 3120 | 3120 SMC4-WD-472 Calculation Sheet of Camber of Steel Girder (1st Rev).pdf |
| 12/16/2019 | 3121 | 3121 SMC4-MS-369 MS for Drainage System Under Bridge.pdf |
| 12/16/2019 | 3122 | 3122 SMC4-MS-370 MS for Construction MSE Wall.pdf |
| 12/16/2019 | 3123 | 3123 SMC4-LC-940 Notice of Equipment Demobilization - Crawler Crane Hitachi KH180-3 at P49 Area Under Scope of BOT Vinh City Bypass |
| 12/16/2019 | 3124 | 3124 SMC4-LC-941 Notice of Equipment Demobilization - Drilling Machine Crane Kobelco 7055 at P32 Area Under Scope of 423.pdf |
| 12/16/2019 | 3125 | 3125 SMC4-LC-942 Notice of Equipment Demobilization - Crane Kato (037LA-0293) at P55 Area Under Scope of 479 Co..pdf |
| 12/16/2019 | 3126 | 3126 SMC4-MC-24 Submission of Retention Money Security for Retention Money Certificate ( Period 11th May 2018 to 30th Nov 2019).pdf |
| 12/17/2019 | 3127 | 3127 SMC4-MA-643 Report on Frequency Test of VIS Steel for Super T Girder Span S43, S46 (MoC &TS dated 04th Dec 2019).pdf |
| 12/17/2019 | 3128 | 3128 SMC4-LC-944 Cost Estimate for Design Modification of Relocation of Abutment A1.pdf |
| 12/17/2019 | 3129 | 3129 SMC4-LC-943 Submission of Weekly Report No.82.pdf |
| 12/20/2019 | 3130 | 3130 SMC4-RP-121 Updated Data of Topographic Survey at Section Km0+320-Km0+840.pdf |
| 12/20/2019 | 3131 | 3131 SMC4-MA-642A Report on Frequency Test of PC Strand for Super T Girder ( 37th).pdf |
| 12/17/2019 | 3132 | 3132 SMC4-LC-945 Acceptance of Sub Structure Construction Stage & Transfer to Construction of SuperStructure Work for P42.pdf |
| 12/18/2019 | 3133 | 3133 18-CDECE-BCHIV-MDNTL Report on the Implementation on Dec 2019 HIV-AIDS Prevention Program for HCRR3 Construction Project MDSTL |
| 12/18/2019 | 3134 | 3134 SMC4-LP-60 Submission of Retention Money Security for Retention Money Payment Certificate ( Period 11th May 2018 to 30th Nov 2 |
| 12/18/2019 | 3135 | 3135 SMC4-MS-371 Report on Loading Test of Pier Head's Supporting System at Pier P50.pdf |
| 12/18/2019 | 3136 | 3136 SMC4-MS-372 MS for Fabrication of U Ditch.pdf |
| 12/18/2019 | 3137 | 3137 SMC4-WD-473 WD of Parapet of Spans P32-P36.pdf |
| 12/18/2019 | 3138 | 3138 SMC4-LC-946 Report on Phenomenon of Gaps under Elastomeric Bearings & Treatment Method.pdf |
| 12/18/2019 | 3139 | 3139 SMC4-LC-947 Arrangement of HDPE Corrugate Conduit for ITS System in the Median Barrier on the Bridge.pdf |
| 12/18/2019 | 3140 | 3140 SMC4-LC-948 Execute Fabrication of Transparent Panel (Polycarbonate ) & Install the Embeded Anchor Bolts for Noise Barrier Ite |
| 12/19/2019 | 3141 | 3141 SMC4-WD-474 WD of Detail for Catch Basin & U Ditch of Drainage System under Viaduct Section P50-P61.pdf |
| 12/19/2019 | 3142 | 3142 SMC4-WD-475 WD of Parapet of Span P11-P16.pdf |
| 12/19/2019 | 3143 | 3143 SMC4-WD-476 WD of Parapet of Span P36-P40.pdf |
| 12/19/2019 | 3144 | 3144 SMC4-LC-949 Additional Supervision Cost of Engineer's Staff (Oct 2019 ).pdf |
| 12/19/2019 | 3145 | 3145 SMC4-MS-373 Report on Loading Test of Pier Head's Supporting System at Pier P7.pdf |
| 12/19/2019 | 3146 | 3146 SMC4-MS-374 Report on Loading Test for Supporting System at P17.pdf |
| 12/19/2019 | 3147 | 3147 SMC4-LC-950 Installation of Crack Induction Joint on A1 Abutment Wall.pdf |
| 12/19/2019 | 3148 | 3148 SMC4-MA-644 Testing Result of Anchor Bolt D25(M24) of Viet Thang Co.Ltd.pdf |
| 12/19/2019 | 3149 | 3149 SMC4-MA-645 Electrical Material of Vonta Co.-Luminaires Material.pdf |
| 12/20/2019 | 3150 | 3150 SMC4-LC-951 Reply to the Engineer's Letter ENG-PK1-1084-1.37 dated 13 Dec 2019 Regarding Reminder on Submission of Outstanding |
| 1/4/2020 | 3151 | 3151 SMC4-WD-477 Scope of Geotextile Layout for the Pavement Structure of the Expressway in MSE Wall.pdf |
| 12/19/2019 | 3152 | 3152 12034 BGTVT-CQLXD Strengthening quality control,progress and Labor safety.pdf |
| 12/21/2019 | 3153 | 3153 SMC4-LC-952 Submission of Weekly Report No.83.pdf |
| 12/24/2019 | 3154 | 3154 SMC4-LC-953 Report on Environment Monitoring in Construction Stage Dec 2019 (Base on EMP).pdf |
| 12/21/2019 | 3155 | 3155 SMC4-LC-954 Report on Environment Monitoring in Construction Stage 2nd time in Dec 2019 Based on S1.43.pdf |
| 12/21/2019 | 3156 | 3156 SMC4-LC-955 Additional Equipment Mobilization Document for Superstructure Work under Scope of 407 Co..pdf |
| 12/30/2019 | 3157 | 3157 SMC4-LC-956 Additional Equipment Mobilization Document for Construction of Parapet Work at P32-P47 under Scope of 414 Co..pdf |
| 12/25/2019 | 3158 | 3158 SMC4-MA-646 Report on Trial Mix of Concrete Class D (250Mpa) for Reinforced Concrete Pipes of Ha Thanh JSC.pdf |
| 12/21/2019 | 3159 | 3159 SMC4-WD-478 WD of Median Barrier of Spans P19-P23 (2nd).pdf |
| 12/21/2019 | 3160 | 3160 SMC4-WD-479 WD of Median Barrier of Span P23-P27 (2nd).pdf |
| 12/23/2019 | 3161 | 3161 SMC4-LP-61 Supporting the Contractor on Getting Permission for the Method of Fencing, Traffic Control at Project.pdf |
| 1/8/2020 | 3162 | 3162 SMC4-MS-375 Loading Test Outline Support System TP2-4, TP6-10, TP12-14 (G1+G2) for Steel Girder Erection.pdf |
| 12/23/2019 | 3163 | 3163 SMC4-MS-376 Permission for Circulation of Vehicles to Transport Overlength Cargo on Road (Transportation of Steel Pier Head).p |
| 12/23/2019 | 3164 | 3164 SMC4-LC-957 Report on Incident of Broken Underground Information Cables During the Construction of the MSE Wall.pdf |
| 12/23/2019 | 3165 | 3165 SMC4-MS-377 Supplement of Method Drawing for Erection of Pre Tensioning Pre Stress Super T Girder Span S42 (P41-P42).pdf |
| 12/24/2019 | 3166 | 3166 SMC4-WD-480 WD of Median Barrier of Spans P32-P36.pdf |
| 12/24/2019 | 3167 | 3167 SMC4-WD-481 WD of Median Barrier of Spans P11-P16.pdf |
| 12/23/2019 | 3168 | 3168 SMC4-LC-959 Acceptance of Sub Structure Construction Stage & Transfer to Constructiron of Superstructure Work for P55.pdf |
| 12/24/2019 | 3169 | 3169 2726-LD-TM Coordination with Bridge 205 in Settlement of Breakage of Army Communication Cable at No.16 PVD Street.pdf |
| 12/25/2019 | 3170 | 3170 SMC4-WD-482 WD of Detail for Catch Basin & U-Ditch of Drainage System under Viaduct Section A1-P10.pdf |
| 12/28/2019 | 3171 | 3171 SMC4-WD-483 WD of Substructure- Design Change of Body Wall, Head Wall & Wing Wall of Abutment A1 (2nd).pdf |
| 12/25/2019 | 3172 | 3172 SMC4-WD-484 WD of Detail of Deck Drain Box.pdf |
| 12/25/2019 | 3173 | 3173 SMC4-WD-485 WD of Parapet & Median Barrier of Spans P57-P61.pdf |
| 12/25/2019 | 3174 | 3174 SMC4-WD-486 WD of Median Barrier of Span P36-P40.pdf |
| 12/25/2019 | 3175 | 3175 SMC4-MS-376A Calculation of Tendon Cable Elongation for Pier Head P7.pdf |
| 12/25/2019 | 3176 | 3176 SMC4-MA-647 Report on Frequency Test of Paint Epicon Primer HB Brow & Epicon HB 300 Grey N7 of Hai Phong Paint JSC ( Sample 22 |
| 12/25/2019 | 3177 | 3177 SMC4-MA-648 Report on Frequency Test of Paint Umeguard SX Red Brow CS-511 & Umeguard SX Light Grey CS-614 of Hai Phong Paint J |
| 3/27/2020 | 3178 | 3178 SMC4-MA-649 Test Result of Dong Anh Cold Reduce Steel Wire D4,D5 used for Drainage Pipes.pdf |
| 12/25/2019 | 3179 | 3179 SMC4-RP-122 Supplement of 5 Permits from DRVN (fr 9Dec19 to 9 Jan2020, fr 13 Dec19 to 13 Jan 2020, fr 21 Dec19 to 21 Jan 2020, |
| 12/26/2019 | 3180 | 3180 SMC4-MS-378 MS of Trial Excavation for MSE Wall.pdf |
| 12/27/2019 | 3181 | 3181 SMC4-WD-487 WD of Detail for Catch Basin & U-Ditch of Drainage System Under Viaduct Section P42-P49.pdf |
| 12/27/2019 | 3182 | 3182 SMC4-MS-379 MS for Construction of Noise Barrier.pdf |
| 12/28/2019 | 3183 | 3183 SMC4-MA-650 Report on Frequency Test of Reinforcing Steel VGS for Parapet S36,S37,S38,S39 S40 Right Side ( M0C&TS dated 25 Dec |
| 12/28/2019 | 3184 | 3184 SMC4-MA-651 Report on Frequency Test of Reinforcing Steel VGS for Pier Column & Pier Head P48, Parapet of Spans S34-S36 Left S |
| 12/27/2019 | 3185 | 3185 SMC4-LC-961 Report on the Phenomenon of Gaps under Elastomeric Bearing & Treatment Method (2nd).pdf |
| 12/27/2019 | 3186 | 3186 SMC4-MS-381 Report on Loading Test of Supporting System at Pier P8.pdf |
| 12/27/2019 | 3187 | 3187 SMC4-MS-380 Report on Loading Test of Pier Head's Supporting System at P53.pdf |
| 1/9/2020 | 3188 | 3188 SMC4-LC-963 Report on Completion of Eemedial Works for Concrete Surface of Pier Column P25.pdf |
| 12/27/2019 | 3189 | 3189 SMC4-LC-964 Acceptance of CIP Concrete Pile Foundation Construction Stage & Transfer to Construction of Substructure Work for |
| 12/27/2019 | 3190 | 3190 SMC4-WD-488 WD Top Elevation of Parapet & Median Barrier at Span S36 9P35-P36).pdf |
| 12/27/2019 | 3191 | 3191 SMC4-AD-117 AD of CIP Concrete Pile D 1.2m of Pier P32R.pdf |
| 12/27/2019 | 3192 | 3192 SMC4-LC-962 Submission of Weekly Report No.84.pdf |
| 12/27/2019 | 3193 | 3193 SMC4-LC-965 Notice of Environmental Monitoring Schedule in Jan 2020 at Construction Phase.pdf |
| 12/30/2019 | 3194 | 3194 SMC4-LC-966 Notice of EOT for the Comlpetion of the Project & Additional Cost Due to Design Modification for Off Ramp HQV-B.pd |
| 12/30/2019 | 3195 | 3195 SMC4-MS-382 Calculation of Tendon Cable Elongation for Pier Head P8.pdf |
| 12/30/2019 | 3196 | 3196 941-GM-SXD Invitation Letter-Attend a Meeting in order to Reach an Argrement on the Plan of Tree Cutting Pruning & Removing fo |
| 1/2/2020 | 3197 | 3197 SMC4-MA-653 Report on Frequency Test of Reinforcing Steel VIS for Super T Girder of Span S44,S45 ( MoC& TS dated 28 Dec 2019). |
| 12/31/2019 | 3198 | 3198 SMC4-LC-968-Suplement of the Documents for stage inspection to proceed next work.pdf |
| 12/31/2019 | 3199 | 3199 SMC4-MA-652 Submission of the minute of checking asphalt concrete plant and updated calibration certificate equipment, materia |
| 12/31/2019 | 3200 | 3200 SMC4-MA-654 Proposal for approval of Report on frequency test of PC Strand for SuperT Girder (38th time).pdf |
| 12/31/2019 | 3201 | 3201 SMC4-MS-383 Submission of Method Statement for Anti-Glare Fence.pdf |
| 12/31/2019 | 3202 | 3202 SMC4-MS-384 Method Statement of Traffic Control for Public Road-Arranging Traffic Control after Opening U-turn P56-P57.pdf |
| 12/31/2019 | 3203 | 3203 SMC4-AD-118 As-Built Drawings of Superstructure - Steel Bridge - Detail of Segment 7 - Rigid Pier Head P17.pdf |
| 12/31/2019 | 3204 | 3204 SMC4-AD-119 As-Built Drawings of Pre-Tensioning Pre-Stressed Super T Girder Span S56(P55-P56).pdf |
| 12/31/2019 | 3205 | 3205 SMC4-MC-25 Interim Payment Certificate No.18(Period 01 st Dec 2019 to 31 st December 2019).pdf |
| 12/31/2019 | 3206 | 3206 SMC4-LC-969 Engineer's Confirmation for Safety and Environment Satisfaction (Dec 01,2019 to Dec 31,2019).pdf |
| 12/31/2019 | 3207 | 3207 SMC4-LC-970 Additional Equipment and Manpower Mobilization document for construction of Parapet work at P19-P28 under Scope of |
| 12/31/2019 | 3208 | 3208 SMC4-MS-385 MS of Steel Girder Erection(3rd ).pdf |
| 12/31/2019 | 3209 | 3209 SMC4-WD-489 WD of the Elevation and Thickness of Deck slab at Span S57(P56-P57).pdf |
| 12/31/2019 | 3210 | 3210 SMC4-MA-655 Capacity Profile of Supplier and Manufacturer of Spange Rubber Packing for SCC Deck slab-steel Bridge Kien Kiet Ru |
| 12/31/2019 | 3211 | 3211 SMC4-MS-886 Supplement of Method Drawing for Erection of Super T girder at Span S56(P55-P56).pdf |
| 1/4/2020 | 3212 | 3212 SMC4-LC-971 Resubmission of Schedule for Steel Bridge (4th).pdf |
| 1/4/2020 | 3213 | 3213 SMC4-LC-972 Submission of Weekly Report No.85.pdf |
| 1/4/2020 | 3214 | 3214 SMC4-LC-973 Report on Environment Monitoring in Construction Stage (3rd in Dec 2019 based on S1.43).pdf |
| 1/4/2020 | 3215 | 3215 SMC4-LC-974 Additional Equipment Mobilization Document for Construction of Superstructure Works at P32-P53 under Scope of 479 |
| 1/4/2020 | 3216 | 3216 SMC4-WD-490 WD of Parapet & Median Barrier of Spans P8-P11.pdf |
| 1/4/2020 | 3217 | 3217 SMC4-WD-491 WD of Parapet & Median Barrier at Spans P53-P57.pdf |
| 1/6/2020 | 3218 | 3218 SMC4-MS-387 MS for Traffic Control for Public Road at Section A1-P24- Vol VIII-Adjusted Arrangement TC at U turn P15-P16 Durin |
| 1/6/2020 | 3219 | 3219 SMC4-WD-492 WD of Deck Slab Span 32.pdf |
| 1/6/2020 | 3220 | 3220 SMC4-LC-975 Construction Schedule of Jan 2020.pdf |
| 1/6/2020 | 3221 | 3221 SMC4-MS-388 Report on Loading Test of Pier Head's Supporting System at P44, P45.pdf |
| 1/6/2020 | 3222 | 3222 SMC4-AD-120 AD of Substructure of Pier P28.pdf |
| 1/6/2020 | 3223 | 3223 SMC4-AD-121 AD of Substructure of Pier P29.pdf |
| 1/6/2020 | 3224 | 3224 SMC4-AD-122 AD of Substructure of Pier P30.pdf |
| 1/7/2020 | 3225 | 3225 SMC4-MS-389 Supplement Method Drawing for Pier Head Construction at P48.pdf |
| 1/7/2020 | 3226 | 3226 SMC4-MS-390 MS for Parapet of MSE Wall.pdf |
| 1/7/2020 | 3227 | 3227 SMC4-WD-493 WD of Pipe Culvert D400, U Ditch & Catch Basin Section Retaining Wall.pdf |
| 1/7/2020 | 3228 | 3228 SMC4-AD-123 AD of SuperT Girder Span 11 (P10-P11).pdf |
| 1/7/2020 | 3229 | 3229 SMC4-LC-976 Notice of Demobilization of Crane Kobelco 7055 at P27 under Scope of 407.pdf |
| 1/7/2020 | 3230 | 3230 SMC4-LC-977 Submission of the Contractor's Programme without Off Ramp HQV-B.pdf |
| 1/7/2020 | 3231 | 3231 SMC4-LC-978 Countermeasures for the Delayed Progress of Steel Bridge Work.pdf |
| 1/9/2020 | 3232 | 3232 SMC4-MA-656 Report on Frequency Test of Reinforcing steel-VGS for SuperT Girder of Span S54-S58 (MoC&TS dated 24 Dec 2019).pdf |
| 1/9/2020 | 3233 | 3233 SMC4-MA-657 Report on Frequency Test of Reinforcing Steel-VGS for Pier Head P8, Body Wall, Head Wall, Wing Wall of Abutment A1 |
| 1/9/2020 | 3234 | 3234 SMC4-MA-658 Report on Frequency Test of Reinforcing Steel-VGS for Deck Slab & Diaphragm S54-S61; Link Slab P53-P61(MoC&TS date |
| 1/8/2020 | 3235 | 3235 SMC4-LT-32 Capacity Profile of Las -XD 298 of ITST.pdf |
| 3/2/2020 | 3236 | 3236 SMC4-MA-659 Trial Mix of Concrete Class C2 of Transmeco BP & Site Laboratary Las XD 668 & Proposal to Using Mix Proportion for |
| 1/8/2020 | 3237 | 3237 SMC4-MA-660 Report on Frequency Test of VGS for Deck Slab, Parapet S41R, Diaphragm S42R, Link Slab P39R, Centre Median S21-S28 |
| 1/8/2020 | 3238 | 3238 SMC4-MA-661 Testing Result Chemical Composition of Dong Anh Cold Reduce Steel Wire D4,D5 Used for Drainage Pipes.pdf |
| 1/8/2020 | 3239 | 3239 SMC4-MA-662 Characteristic Strength for Concrete Class C of Viet Tiep BP(new Location) - RP 4 (3-30 Nov 2019).pdf |
| 1/8/2020 | 3240 | 3240 SMC4-MA-663 Characteristic Strength for Concrete Class B of Transmeco BP - RP 4 (1-30 Nov 2019).pdf |
| 1/8/2020 | 3241 | 3241 SMC4-MA-664 Characteristic Strength for Concrete Class C of Asean BP (new Location) - RP 4 (3-29 Nov 2019).pdf |
| 1/8/2020 | 3242 | 3242 SMC4-MA-665 Characteristic Strength for Concrete Class C of Transmeco BP - RP 10 (1-30 Nov 2019).pdf |
| 1/8/2020 | 3243 | 3243 SMC4-MA-666 Characteristic Strength for Concrete Class A of Viet Tiep BP(new Location) - RP 6 (1-30 Nov 2019).pdf |
| 1/8/2020 | 3244 | 3244 SMC4-MA-667 Characteristic Strength for Concrete Class Y of Viet Tiep BP(new Location)- RP 4 (1-11 Nov 2019).pdf |
| 1/9/2020 | 3245 | 3245 SMC4-LC-979 Equipment & Manpower Mobilization Document of Subcontractor Thanh Long Group JSC for Erection of Steel Girder - 3 |
| 1/9/2020 | 3246 | 3246 SMC4-LC-980 Submission of Weekly Report No.86.pdf |
| 1/9/2020 | 3247 | 3247 SMC4-RP-123 Report on Survey of Existing Utilities at Approach Road & MSE Wall Area.pdf |
| 1/9/2020 | 3248 | 3248 SMC4-AD-124 As-Built Drawings of Substructure of Pier P58.pdf |
| 1/9/2020 | 3249 | 3249 SMC4-AD-125 As-Built Drawings of Substructure of Pier P57.pdf |
| 1/9/2020 | 3250 | 3250 SMC4-AD-126 As-Built Drawings of Substructure of Pier P27.pdf |
| 1/9/2020 | 3251 | 3251 SMC4-AD-127 As-Built Drawings of Substructure of Pier P23.pdf |
| 1/9/2020 | 3252 | 3252 SMC4-AD-128 As-Built Drawings of Substructure of Pier P24.pdf |
| 1/7/2020 | 3253 | 3253 92 BGTVT-KHDT Authorization for Approval of Detailed design modification.pdf |
| 1/8/2020 | 3254 | 3254 SMC4-LC-211 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P54.pdf |
| 1/9/2020 | 3255 | 3255 SMC4-MA-669 Report on Frequency Test of Reinforcing Steel-VIS Bar for U Ditch (MoC &TS dated 28 Dec 2019).pdf |
| 1/9/2020 | 3256 | 3256 SMC4-MA-668 Report on Frequency Test of Reinforcing Steel-VGS for Pier Column & Pier Head of Pier P45, P48, Deck Slab Span S42 |
| 1/9/2020 | 3257 | 3257 SMC4-LC-982 Starting the Construction of Drainage System Under the Viaduct of Section A1-P10 & P19-P25.pdf |
| 1/9/2020 | 3258 | 3258 SMC4-LC-981 Reply Letter & Withdrawal of the Submitted Letter Regarding Capacity Profile of Subcontractor - Nam anh Technology |
| 1/9/2020 | 3259 | 3259 SMC4-MA-670 Report on Frequency Test of Bolts Material for Steel Bridge S10T (including Nut & Washer) Taking Sample dated 12 N |
| 1/9/2020 | 3260 | 3260 81-SGTVT-QLKCHGT Suspension of Construction, Road Excavation in the Projects Located on HN City during Lunar Tet of Year of Ra |
| 1/11/2020 | 3261 | 3261 SMC4-LC-983 Additional Supervision Cost of Engineer's Staff (Nov 2019).pdf |
| 1/11/2020 | 3262 | 3262 SMC4-LC-984 Report on the Phenomenon of Crack on Concrete Surface Pier Columns.pdf |
| 1/11/2020 | 3263 | 3263 SMC4-WD-494 WD of Road Work - Expressway from Km0+494.22-Km0+568.40 ( 1st Rev.).pdf |
| 1/11/2020 | 3264 | 3264 SMC4-MS-391 MS of Trial Excavation for Drainage System under Bridge.pdf |
| 1/11/2020 | 3265 | 3265 SMC4-AD-129 AD of Substructure of Pier P35.pdf |
| 1/11/2020 | 3266 | 3266 SMC4-AD-130 AD of Substructue of Pier P25.pdf |
| 1/11/2020 | 3267 | 3267 SMC4-AD-131 AD of Substructure of pier P26.pdf |
| 1/11/2020 | 3268 | 3268 SMC4-LC-989 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work for P49.pdf |
| 1/11/2020 | 3269 | 3269 SMC4-LC-990 Acceptance of Sub-Structure Construction Stage & Transfer to Construction of Superstructure Work for P50.pdf |
| 1/11/2020 | 3270 | 3270 SMC4-LC-985 Report on the Phenomenon of Cracks on the Stem Wall of Abutment A1.pdf |
| 1/11/2020 | 3271 | 3271 SMC4-LC-986 Additional Equipment Mobilization Document of 1 Tractor & 2 Trailers for Transportation & Erection Work of Super T |
| 1/11/2020 | 3272 | 3272 SMC4-LC-987 Machine Mobilization Document (Manlifting Machine) of Thanh Long JSC for Erection of Steel Girder (1st).pdf |
| 1/11/2020 | 3273 | 3273 SMC4-AD-132 AD of Substructure of Pier P36.pdf |
| 1/11/2020 | 3274 | 3274 SMC4-AD-133 AD of substructure of Pier P37.pdf |
| 1/11/2020 | 3275 | 3275 SMC4-AD-134 AD of Substructure of Pier P22.pdf |
| 1/11/2020 | 3276 | 3276 SMC4-AD-135 AD of Substructure of Pier P60.pdf |
| 1/13/2020 | 3277 | 3277 SMC4-AD-136 AD of Substructure of Pier P21.pdf |
| 1/11/2020 | 3278 | 3278 SMC4-LC-988 Supplement of Documents for Stage Inspection to Proceed Next Works.pdf |
| 1/13/2020 | 3279 | 3279 SMC4-AD-137 AD of Substructure of Pier P20.pdf |
| 1/13/2020 | 3280 | 3280 SMC4-AD-138 AD of substructure of pier P59.pdf |
| 1/13/2020 | 3281 | 3281 SMC4-AD-139 AD of Substructure of Pier P17.pdf |
| 1/13/2020 | 3282 | 3282 SMC4-AD-140 AD of Substructure of Pier P18.pdf |
| 1/11/2020 | 3283 | 3283 SMC4-AD-141 AD of Substructure of Pier P14.pdf |
| 1/13/2020 | 3284 | 3284 SMC4-AD-142 AD of Substructure of Pier P15.pdf |
| 1/13/2020 | 3285 | 3285 SMC4-AD-143 AD of Substructure of Pier P38.pdf |
| 1/13/2020 | 3286 | 3286 SMC4-AD-144 AD of Substructure of Pier P39.pdf |
| 1/13/2020 | 3287 | 3287 SMC4-AD-145 AD of Substructure of Pier P40.pdf |
| 1/13/2020 | 3288 | 3288 SMC4-WD-495 WD of Parapet & Median Barrier of Spans P49-P53.pdf |
| 1/13/2020 | 3289 | 3289 SMC4-WD-496 WD of Median Barrier of Spans P30-P32.pdf |
| 1/13/2020 | 3290 | 3290 SMC4-MS-392 Method Drawing for Erection of Super T Girder at Span S50.pdf |
| 1/13/2020 | 3291 | 3291 SMC4-LC-970A Submission of Monthly Report No.20.pdf |
| 1/22/2020 | 3292 | 3292 SMC4-MA-671 Report on Frequency Test of Materials for Cement Concrete at Viet Tiep BP (22nd to 23rd ).pdf |
| 1/22/2020 | 3293 | 3293 SMC4-MA-672 Report on Frequency Test of Material for Cement Concrete at Transmeco BP ( 52th-54th).pdf |
| 1/13/2020 | 3294 | 3294 SMC4-MA-673 Report on Frequency Test of Paint Epicon Primer HB Reddich Brown of Hai Phong Paint JSC (Sample 17Dec19).pdf |
| 1/13/2020 | 3295 | 3295 SMC4-MA-674 Report on Frequency Test of Paint Galbon S-HB PZ L1 of Hai Phong Paint JSC (Sample 21 Dec19).pdf |
| 1/13/2020 | 3296 | 3296 SMC4-MA-675 Report on Frequency Test of Paint Fluorex Finish Grey Ral 7035, Fruorex UnderCoat EP Grey Ral 7038 & Epicon Prime |
| 1/13/2020 | 3297 | 3297 SMC4-MA-676 Update Profile of Noise Barrier Material Product Manufactured by Nippon Steel& Suminkin Metal supplied by Nam Anh |
| 1/14/2020 | 3298 | 3298 SMC4-MA-677 Frequency Test of VGS to Use for Deck Slab & Parapet S42R, Center Median S35-S37 ( MoC&TS dated 4 Jan2020).pdf |
| 1/14/2020 | 3299 | 3299 SMC4-MA-678 Frequency Test of VGS to Use for Deck Slab & Diaphragm S54-S61, Link Slab P53-P61 ( M0C& TS dated 3Jan2020).pdf |
| 1/14/2020 | 3300 | 3300 SMC4-MA-679 Frequency Test of VIS to Use for Super T Girder of Span S54 (MoC & TS 2 Jan 2020).pdf |
| 1/14/2020 | 3301 | 3301 SMC4-MA-680 Frequency Test of VGS to Use for Deck Slab & Diaphragm S55, S56 (MoC & TS 4 Jan 2020).pdf |
| 1/14/2020 | 3302 | 3302 SMC4-MA-681 Frequency Test of VIS to use for Super T Girder of Span S32,S49 ( M0C&TS dated 7 Jan 2020).pdf |
| 1/14/2020 | 3303 | 3303 SMC4-MA-682 Frequency Test of VGS to Use for Deck Slab & Diaphragm S7, S8,S13-S15, Body Wall, Head Wall & Wing Wall of Abutmen |
| 1/14/2020 | 3304 | 3304 SMC4-LC-993 Notice on Schedule for Tet Holiday 2020.pdf |
| 1/14/2020 | 3305 | 3305 SMC4-AD-146 AD of Pre Tensioning Pre Stressed Super T Girder Span 50 (P49-P50).pdf |
| 1/14/2020 | 3306 | 3306 SMC4-MS-395 Relocation & Protection of Existing Utilities Document at Approach Road & MSE Wall Area (11st).pdf |
| 1/14/2020 | 3307 | 3307 SMC4-MS-394 Supplement of Method for Erection of Super T Girder at Span S55 (P54-P55).pdf |
| 1/14/2020 | 3308 | 3308 SMC4-MS-393 Calculation of Tendon Cable Elongation of Pier Head P43.pdf |
| 1/14/2020 | 3309 | 3309 SMC4-RP-124 Report on Loading Test of Pier Head's Supporting System at P48.pdf |
| 1/14/2020 | 3310 | 3310 SMC4-MA-683 Use Concrete Class C1,C3,C4 -30Mpa at Viet Tiep BP ( New Location) to change Concrete Class E-21 Mpa for Items U D |
| 1/14/2020 | 3311 | 3311 SMC4-LC-991 Notice for Leave of Contractor Project Manager on 15Jan2020 - Mr Kytayama.pdf |
| 1/14/2020 | 3312 | 3312 SMC4-LC-992 Notice for Leave of Contractor Project Manager during Tet Holiday- Mr Kytayama.pdf |
| 1/14/2020 | 3313 | 3313 SMC4-MA-684 Testing Result of HDPE of Vonta Conduit- Vonta Co.Ltd.pdf |
| 1/14/2020 | 3314 | 3314 SMC4-MA-685 Electrical Material of Vonta Co.LTD - Cable Pulling Box Material.pdf |
| 1/22/2020 | 3315 | 3315 SMC4-MA-686 Report on Frequency Test of Materials for Cement Concrete at Asean BP (28th-29th).pdf |
| 1/21/2020 | 3316 | 3316 SMC4-MA-687 Testing Result of Permeable Backfill Material (Cao Duong Quarry, Commune, Exploited by Hien Luong Mineral Exploita |
| 1/14/2020 | 3317 | 3317 SMC4-LC-994 Reply to the Engineer for Assurance of Safety & Environment during Tet Holiday 2020.pdf |
| 1/14/2020 | 3318 | 3318 SMC4-AD-147 AD of Super T Girder Span 55 (P54-P55).pdf |
| 1/15/2020 | 3319 | 3319 SMC4-LP-62 VAT Invoices for Interim Payment Certificate No.13.pdf |
| 1/15/2020 | 3320 | 3320 SMC4-LP-63 VAT Invoices for Interim Payment Certificate No.14.pdf |
| 1/15/2020 | 3321 | 3321 SMC4-LP-64 VAT Invoices for Interim Payment Certificate No.15.pdf |
| 1/15/2020 | 3322 | 3322 SMC4-LP-65 VAT Invoices for Interim Payment Certificate No.16.pdf |
| 1/15/2020 | 3323 | 3323 SMC4-LP-66 VAT Invoices for Interim Payment Certificate No.17.pdf |
| 1/15/2020 | 3324 | 3324 SMC4-LP-67 VAT Invoices for Interim Payment Certificate No.18.pdf |
| 1/21/2020 | 3325 | 3325 SMC4-MS-396 MS for Construction Approach Slab of Abutment A1.pdf |
| 2/11/2020 | 3326 | 3326 SMC4-MS-397 Method Statement for Construction of Road Work.pdf |
| 1/15/2020 | 3327 | 3327 112-BQLDATL-DA1 Plan for Construction of HCRR3 Construction Project MD_STL Section during Lunar Tet 2020.pdf |
| 1/18/2020 | 3328 | 3328 SMC4-MS-398 Resubmission of Permission for Circulation Vehicle to Transport Overlength Cargo on Road ( Transportation of Steel |
| 1/18/2020 | 3329 | 3329 SMC4-MS-399 Report on Loading Test of Temporary Support TP12, TP13 (G1+G2), TP9 (G3+G4) for Steel Girder Erection.pdf |
| 1/18/2020 | 3330 | 3330 SMC4-LC-995 Report on Environment Monitoring in Construction Stage (1st in Jan 2020 Based on.pdf |
| 1/18/2020 | 3331 | 3331 SMC4-LC-996 Submission of Weekly Report No.87.pdf |
| 1/18/2020 | 3332 | 3332 SMC4-WD-497 WD of Parapet & Median Barrier of Spans at P44-P49.pdf |
| 1/18/2020 | 3333 | 3333 SMC4-AD-148 AD of Pre Tensioning Super T Girder of Span 10 (P9-P10).pdf |
| 1/18/2020 | 3334 | 3334 SMC4-MA-688 Cable & Grounding Wire Electrical Material of Thuong Dinh Electrical Wires & Cables JSC & Supplied by Vonta Co.Ltd |
| 1/18/2020 | 3335 | 3335 SMC4-MA-689 Electrical Material of Vestel Co.Ltd - Luminaires Material.pdf |
| 1/18/2020 | 3336 | 3336 SMC4-MA-690 Capacity Profile of Supplier New Linh JSC for PVC Pipe Manufactured by Thuan Phat JSC.pdf |
| 1/18/2020 | 3337 | 3337 SMC4-MA-691 Capacity Profile Vonta Co.Ltd for Material of Lighting Poel & Bolt(2nd).pdf |
| 1/18/2020 | 3338 | 3338 SMC4-MA-692 Report on Frequency Test of Reinforcing Steel VGS for Pier Head P48, Deck Slab S42L-S44L, Link Slab P41L,P42L, Dia |
| 1/18/2020 | 3339 | 3339 SMC4-MA-693 Test Result of Angle Steel of SCC Deck Slab- Steel Bridge Thai Nguyen Iron & Steel JSC.pdf |
| 1/18/2020 | 3340 | 3340 SMC4-LC-997 Permission for Traffic Control of Steel Girder Erection.pdf |
| 1/18/2020 | 3341 | 3341 SMC4-LC-988 Resubmission of Schedule for Steel Bridge (5th).pdf |
| 1/18/2020 | 3342 | 3342 SMC4-MS-400 Report on Loading Test of Temporary Support TP14(G1+G2) for Steel Girder Erection.pdf |
| 1/20/2020 | 3343 | 3343 SMC4-MS-401 Plan view of Method Statement for Cutting Removal & Relocation Trees from begin Point to P6.pdf |
| 1/20/2020 | 3344 | 3344 SMC4-LC-999 Acceptance of Sub Structure Construction Stage & Transfer to Construction of SuperStructure Work for P10.pdf |
| 1/20/2020 | 3345 | 3345 SMC4-LC-1000 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P11.pdf |
| 1/21/2020 | 3346 | 3346 SMC4-MA-694 Report on Frequency Test of Welding Material -Welding Wire SF71 (Taking Sample dated 7 Jan 2020).pdf |
| 1/21/2020 | 3347 | 3347 SMC4-LC-1001 Proposal for Manpower Mobilization Document for Superstructure Work.pdf |
| 1/21/2020 | 3348 | 3348 SMC4-LC-1002 Contractor's Confirmation on Scope of Work of Noise Barrier.pdf |
| 1/21/2020 | 3349 | 3349 SMC4-WD-498 WD of Parapet of Span P32-P36 (1st Rev).pdf |
| 1/21/2020 | 3350 | 3350 SMC4-LC-1003 Manpower Mobilization Document of VONTA Co.Ltd for Construction & Installation of Lighting System- 1st.pdf |
| 1/21/2020 | 3351 | 3351 SMC4-LC-1004 Result Report on Preparation Work for Assurance of Safety, Security & Environmental for Coming Tet Holiday 2020.p |
| 1/21/2020 | 3352 | 3352 SMC4-LC-1005 Report on Environment Monitoring in Construction Stage 2nd time in Jan 2020 (Based on S1.43).pdf |
| 1/21/2020 | 3353 | 3353 SMC4-LC-1006 Notice of Environmental Monitoring Schedule in Feb 2020 at Construction Phase.pdf |
| 1/21/2020 | 3354 | 3354 SMC4-WD-499 WD of Elevation & Thickness of Deck Slab S13(P12-P13), S42(P41-P42), S56(P55-P56).pdf |
| 1/21/2020 | 3355 | 3355 SMC4-WD-500 WD of Electric & Lighting- Gerneral View of Electric Lighting & ITS System for Expressway ( 2nd).pdf |
| 1/21/2020 | 3356 | 3356 SMC4-WD-501 WD of Painting for Steel Concrete Composite Deck Slab (1st).pdf |
| 1/22/2020 | 3357 | 3357 185 TB-BQLDTL Notice on Conclusions given by PMU Thang Long in the Meeting to review the Implementation of Package 1 and Packa |
| 2/4/2020 | 3358 | 3358 152 PMUTL-DA1 Design change of Drainage under Viaduct.pdf |
| 2/4/2020 | 3359 | 3359 SMC4-MS-402 Report on Loading Test of Temporary Suport TP10 (G3+G4) for Steel Girder Erection.pdf |
| 2/7/2020 | 3360 | 3360 SMC4-LC-1007 Additional Machine & Manpower Mobilization Document of Subcontractor Thanh Long Gr JSC for Transportation of Stee |
| 2/7/2020 | 3361 | 3361 SMC4-LC-1008 Additional Equipment & Manpower Mobilization Document of 3 Truck Cranes of Subcontractor Thanh Long Gr JSC for Er |
| 2/7/2020 | 3362 | 3362 SMC4-LP-68 Supporting Contractor on Getting Permission for Protection & Relocation of Underground Communication Cable & Draina |
| 2/7/2020 | 3363 | 3363 SMC4-MS-403 Approval Document of Protection of Underground Communication Cable at Approach Road & MSE Wall Area (1st).pdf |
| 2/8/2020 | 3364 | 3364 SMC4-MA-695 Used to Aggregate Sub Base Course Type II, Dmax = 37.5mm for SubGrade Material.pdf |
| 2/8/2020 | 3365 | 3365 SMC4-LP-69 Proposal for PMU Thang Long's Support in Sending a Written Request to Bac Tư Liem Power Co, for Facilitation & Coor |
| 2/7/2020 | 3366 | 3366 SMC4-LC-1009 Submission of Construction Schedule of Feb 2020.pdf |
| 2/7/2020 | 3367 | 3367 SMC4-LC-1010 Withdrawal of the Letter MA-0634 dated 9 Dec19.pdf |
| 2/7/2020 | 3368 | 3368 SMC4-LC-1011 Withdrawal of the Letter WD-0494 dated 9Jan 20.pdf |
| 2/7/2020 | 3369 | 3369 SMC4-WD-502 WD the Top Elevation of Parapet & Median Barrier at Span S58(P57-P58), S61(P60-P61).pdf |
| 2/10/2020 | 3370 | 3370 SMC4-LC-1012 Design Change of Connection of Drainage System Under Viaduct with Ring Road No.3 Widening Project & Drainage Pipe |
| 2/10/2020 | 3371 | 3371 SMC4-WD-501A WD Top Elevation of Parapet & Median Barrier at Span S37( P36-P37).pdf |
| 2/10/2020 | 3372 | 3372 SMC4-LC-1013 Explanation for the Engineer's Comments of Manpower Mobilization Document for Supporting Works.pdf |
| 2/10/2020 | 3373 | 3373 SMC4-LC-1014 Report on Environment Monitoring in Construction Stage , 3rd Time in Jan 2020 (Based on S1.43).pdf |
| 2/10/2020 | 3374 | 3374 SMC4-LC-1015 Submission of Weekly Report No.88.pdf |
| 2/26/2020 | 3375 | 3375 SMC4-MA-696 Report on Frequency Test of PC Strand for Super T Girder (39th).pdf |
| 2/10/2020 | 3376 | 3376 SMC4-MA-697 Report on Frequency Test of Paint for Steel Bridge of Hai Phong Paint JSC (Sample dated 3Jan20).pdf |
| 2/10/2020 | 3377 | 3377 SMC4-MA-698 Update Profile of Noise Barrier Material Product Manufactured by Nippon Steel Metal, Supplied by Nam Anh CO.Ltd (2 |
| 2/10/2020 | 3378 | 3378 SMC4-MA-699 Report on Frequency Test of Angle Steel L75x75x9,L90x90x10 for Steel Bridge of Thai Nguyen JSC(Sample dated 9 Jan |
| 2/10/2020 | 3379 | 3379 SMC4-MS-405 Report on Loading Test of Temporary Support TP6, TP7, TP8(G3+G4) for Steel Girder Erection.pdf |
| 2/10/2020 | 3380 | 3380 SMC4-MS-406 Method Drawing for Erection of Super T Girder at S46 (P45-P46).pdf |
| 2/11/2020 | 3381 | 3381 288-PMUTL-DA1 Reinstatement of Drainage Culvert D1250 for Office of Ministry of Public Security.pdf |
| 2/12/2020 | 3382 | 3382 SMC4-MA-700 Submission Test Plan for Noise Barrier.pdf |
| 2/12/2020 | 3383 | 3383 SMC4-MA-701 Report on Frequency Test of Materials for Cement Concrete at Viet Tiep BP (24th to 25th) & Updated R28 (23rd).pdf |
| 2/12/2020 | 3384 | 3384 SMC4-MA-702 Report on Frequency Test of Materials for Cement Concrete at Asean BP (30th) & Updated R28 (29th).pdf |
| 2/12/2020 | 3385 | 3385 SMC4-MA-703 Report on Frequency Test of Materials for Cement Concrete at Transmeco BP (55th to 56th) & Updated R28 (54th).pdf |
| 2/12/2020 | 3386 | 3386 SMC4-MA-704 Capacity Profile of Supplier, Manufacturer of Asphalt Material for Asphalt Concrete.pdf |
| 2/15/2020 | 3387 | 3387 SMC4-MS-407 Method for Erection of Super T Girder at Span S48(P47-P48).pdf |
| 2/12/2020 | 3388 | 3388 SMC4-WD-503 WD of Parapet Span P36-P40(1st Rev.).pdf |
| 2/12/2020 | 3389 | 3389 SMC4-WD-504 WD of Superstructure -Deck Slab for Span 8 & Link Slab at Pier P7 (2nd).pdf |
| 2/12/2020 | 3390 | 3390 SMC4-WD-505 WD of Superstructure-Deck Slab for Span 9 & Link Slab P9 at Pier P9 (2nd).pdf |
| 2/12/2020 | 3391 | 3391 SMC4-WD-506 WD of Superstructure- Deck Slab for Span 7 (2nd).pdf |
| 2/12/2020 | 3392 | 3392 SMC4-WD-507 WD of Parapet (Right Side) of Span P27-P32 (1st Rev.).pdf |
| 2/12/2020 | 3393 | 3393 SMC4-WD-508 WD of Parapet & Median Barier of Span P57-P61 (2nd).pdf |
| 2/12/2020 | 3394 | 3394 SMC4-LC-1016 Acceptance of SubStructure Construction Stage & Transfer tro Construction of Superstructure Work for P45.pdf |
| 2/22/2020 | 3395 | 3395 SMC4-MA-705 Characteristic Strength for Concrete Class G of Transmeco BP- RP 02( fr 12 Oct 19 to 27 Oct 19).pdf |
| 2/13/2020 | 3396 | 3396 SMC4-MA-706 Characteristic Strength for Concrete Class B of Transmeco BP - RP 05 (fr 2 Dec 19 to 30 Dec 19).pdf |
| 2/13/2020 | 3397 | 3397 SMC4-MA-707 Characteristic Strength for Concrete Class C of Viet Tiep BP (new Location) - RP 05 (fr 2 Dec 19 to 31 Dec 19).pdf |
| 2/13/2020 | 3398 | 3398 SMC4-MA-708 Characteristic Strength for Concrete Class C of Asean BP( New Location)- RP 05 (for 01 Dec 19 to 29 Dec 19).pdf |
| 2/13/2020 | 3399 | 3399 SMC4-MA-709 Characteristic Strengh for Concrete Class C of Transmeco BP- RP 11 (fr 01 Dec19 to 31 Dec 19).pdf |
| 2/13/2020 | 3400 | 3400 SMC4-LC-1017 Submission of Monthly Report No.21.pdf |
| 2/13/2020 | 3401 | 3401 SMC4-LC-1018 Checking Record of Equipment & Manpower of Manpower & Equipment Mobilization Document of Thanh Long Gr for Transp |
| 2/13/2020 | 3402 | 3402 SMC4-LC-1019 Engineer's Confirmation for Safety & Environment Satisfaction (Jan 2020).pdf |
| 2/13/2020 | 3403 | 3403 SMC4-LC-1020 Request for Instruction on Noise Barrier for P26-P27 Area.pdf |
| 2/13/2020 | 3404 | 3404 SMC4-LC-1021 Supplement of Document for Stage Inspection to Proceed Next Works.pdf |
| 2/13/2020 | 3405 | 3405 SMC4-WD-509 WD of General Arrangement of Traffic Sign for Express Way Km0+130 to Km2+812.5(update).pdf |
| 2/13/2020 | 3406 | 3406 SMC4-WD-510 WD of Road Work - Express Way from Sta.0+320.00-Sta.0+447.90.pdf |
| 2/15/2020 | 3407 | 3407 SMC4-AD-149 AD of Pre Tensioning Pre Stressed Super T Girder Span 48 (P47-P48).pdf |
| 2/15/2020 | 3408 | 3408 SMC4-AD-150 AD of Pre Tensioning Pre Stressed Super T Girder Span 46 (P45-P46).pdf |
| 2/15/2020 | 3409 | 3409 SMC4-WD-511 WD Top Elevation of Parapet & Median Barrier at Span S38 9P37-P38).pdf |
| 2/15/2020 | 3410 | 3410 SMC4-MS-408 Method for Erection of Super T Girder at Span S43 ( P42-P43).pdf |
| 2/15/2020 | 3411 | 3411 SMC4-LC-1022 Submission of Weekly Report No.91.pdf |
| 2/21/2020 | 3412 | 3412 SMC4-LC-1023 Report on Environment Monitoring in Construction Stage (1st Time in Feb 2020, based on S1.43).pdf |
| 2/17/2020 | 3413 | 3413 SMC4-MA-694A Reply on RC Pipe D400, D500, Precast Bearing D400, D500- Ha Thanh Concrete JSC.pdf |
| 2/17/2020 | 3414 | 3414 SMC4-LT-33 Updated Document of Independent Laboratories of ITST (Road Lab 1, Vilas 276-Las-XD 831,201).pdf |
| 2/17/2020 | 3415 | 3415 SMC4-LC-1024 Additional Machine Mobilization Document (1 Crane 200 ton) of Thanh Long JSC for Erection of Steel Bridge- 4th.pd |
| 2/17/2020 | 3416 | 3416 SMC4-LC-1025 Renewal of the Calibration Certificate of the Approved Truck Crane 180 Ton of Subcontractor Thanh Long JSC for Er |
| 2/17/2020 | 3417 | 3417 SMC4-MA-710 Testing Result of Augnment Bar Use for Bracing Work of Paraweb Strip.pdf |
| 2/17/2020 | 3418 | 3418 SMC4-MA-711 Testing Result of Paraweb Strip Material.pdf |
| 2/19/2020 | 3419 | 3419 SMC4-MS-409 MS of Removal & Relocation of Trees at Section from Beginning Points to P16 (2nd).pdf |
| 2/17/2020 | 3420 | 3420 SMC4-MS-410 Report on Loading Test of Temporary Support TP13, TP14 (G3+G4) for Steel Girder Erection.pdf |
| 2/21/2020 | 3421 | 3421 SMC4-MS-411 Changing Screw Jack by H Beam to Support Steel Girder at Temporary Piers Position of TP2 to TP10.pdf |
| 2/19/2020 | 3422 | 3422 SMC4-MS-412 MS for Construction of MSE Wall.pdf |
| 2/17/2020 | 3423 | 3423 SMC4-LC-1026 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P48.pdf |
| 2/15/2020 | 3424 | 3424 325-GM-BQLDATL Invitation- Meeting on Implementation of Cutting-Removing-Rooting up Green Trees for Construction of HCRR3.pdf |
| 2/15/2020 | 3425 | 3425 65 QD-BQLDATL Approval Decision for Modification of Detailed Design of On-Off Ramps HCRR3 Construction Project.pdf |
| 2/19/2020 | 3426 | 3426 SMC4-MS-413 Resubmission of Permission for Circulation of Vehicles to Transport Overlength Cargo on Road (Transportation of St |
| 2/19/2020 | 3427 | 3427 SMC4-MC-26 Appication for Interim Payment Certificate 19 (Period 01st Jan to 31st Jan 2020).pdf |
| 2/19/2020 | 3428 | 3428 SMC4-MS-414 Report on Loading Test of Temporary Support TP2 (G3+G4) for Steel Girder Erection.pdf |
| 2/19/2020 | 3429 | 3429 SMC4-AD-151 AD of Pre Tensioning Pre Stressed Super T Girder Span 43 (P42-P43).pdf |
| 2/19/2020 | 3430 | 3430 SMC4-MS-415 Method Drawing for Erection of Super T Girder at Span S53(P52-P53) & S54 (P53-P54).pdf |
| 2/19/2020 | 3431 | 3431 SMC4-WD-512 WD of Road Work -Expressway from Station Km0+494.22-Km0+568.40 (1st Rev.).pdf |
| 2/19/2020 | 3432 | 3432 SMC4-LC-1027 Calculation Verifying the Construction Sequence for Deck Slab Work & Request to Supply Additional Related Documen |
| 2/19/2020 | 3433 | 3433 SMC4-MA-712 Capacity Profile of Supplier New Link JSC for PVC Pipe- Thuan Phat JSC (2nd).pdf |
| 2/19/2020 | 3434 | 3434 SMC4-MA-713 Report on Frequency Test of Bolt Material for Steel Bridge S10T ( Including Nut & Washer) Taking Sample dated 11 D |
| 2/19/2020 | 3435 | 3435 SMC4-MA-714 Test Result of Stud Bolt of Hangzhou Jiaxiang Bolts Co.,Ltd & Welding Procedure for Steel Bridge.pdf |
| 2/19/2020 | 3436 | 3436 SMC4-MA-715 Test Result of Shear Stud(D19x155,D19x205) & Welding Procedure for Steel Bridge.pdf |
| 2/19/2020 | 3437 | 3437 SMC4-MA-716 Capacity Profile of Supplier & Manufacturer of Deck Drain Box, Trash rack-Traffic Sign System (Warning & Regulator |
| 2/19/2020 | 3438 | 3438 SMC4-MS-416 Notice on Expected Schedule of Removal & Relocation of Trees at Section from Beginning Point to Pier P16.pdf |
| 2/20/2020 | 3439 | 3439 SMC4-LC-1028 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work P43.pdf |
| 2/20/2020 | 3440 | 3440 SMC4-LC-1029 Additional Equipment Mobilization Document for Parapet Work at P56-P60 Under Scope of 414 Co..pdf |
| 2/20/2020 | 3441 | 3441 SMC4-LC-1030 Additional Supervision Cost of Engineer's Staff (Dec 19).pdf |
| 2/20/2020 | 3442 | 3442 SMC4-LC-1031 Documents for Stage Inspection Proceed Next Works P23-P26, P28, P38-P40.pdf |
| 2/20/2020 | 3443 | 3443 SMC4-WD-515 WD of Parapet & Median Barrier of Spans P49-P53 (2nd).pdf |
| 3/3/2020 | 3444 | 3444 SMC4-MS-417 Document of Protection of Manhole for Water Supply at MSE Wall Righ Side (1st).pdf |
| 2/20/2020 | 3445 | 3445 SMC4-RP-125 Updated Report on th Phenomenon of Crack on Abutment A1's Stem Wall& Treatment Method.pdf |
| 2/20/2020 | 3446 | 3446 SMC4-MA-717 Testing Result of Non-Woven Geotextile ART14-Vietnam Geotextile JSC.pdf |
| 2/20/2020 | 3447 | 3447 SMC4-MA-718 Test Result of Sponge Rubber Packing for SCC Deck Slab of Steel Bridge- Kien Kiet Rubber Mechanical JSC.pdf |
| 2/20/2020 | 3448 | 3448 SMC4-MA-719 Report on Frequency Test of Paint for Steel Bridge of Hai Phong Paint JSC ( Sampling Dated 17 Jan2020).pdf |
| 2/20/2020 | 3449 | 3449 SMC4-WD-513 WD of Parapet & Median Barrier of Spans P8-P11 (2nd).pdf |
| 2/27/2020 | 3450 | 3450 SMC4-WD-514 WD of Parapet & Median Barrier of Spans P53-P57(2nd).pdf |
| 2/20/2020 | 3451 | 3451 SMC4-MA-720 Report on Frequency Test of Paint for Steel Bridge of Hai Phong Paint JSC ( Sampling dated 9 Jan 2020).pdf |
| 2/20/2020 | 3452 | 3452 SMC4-LC-1033 Manpower Mobilization Document for Superstructure Work (2nd).pdf |
| 2/21/2020 | 3453 | 3453 SMC4-LC-1032 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P53.pdf |
| 3/9/2020 | 3454 | 3454 SMC4-LC-1034 Machine & Manpower Mobilization Documnet of Hanoi Infrastructure & Cultural Construction Cor. for Cutting & Pruni |
| 2/22/2020 | 3455 | 3455 SMC4-LC-1035 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work for P52.pdf |
| 2/22/2020 | 3456 | 3456 SMC4-MS-402A MS for Production of Precast RC Bearing for Circular Culvert.pdf |
| 2/22/2020 | 3457 | 3457 SMC4-MS-418 Report on Loading Test of Temporary Support TP6, TP7, TP9 (G1+G2) for Steel Girder Erection.pdf |
| 2/22/2020 | 3458 | 3458 SMC4-WD-516 WD Top Elevation of Parapet & Median Barrier S39 (P38-P39).pdf |
| 2/22/2020 | 3459 | 3459 SMC4-WD-517 WD of Elevation & Thickness of Deck Slab S55(P54-P55).pdf |
| 2/22/2020 | 3460 | 3460 SMC4-WD-518 WD Top Elevation of Parapet & Median Barrier at Spans S12(P11-P12)-S16(P15-P16).pdf |
| 2/22/2020 | 3461 | 3461 SMC4-LC-1036 Submission of Weekly Report No.92.pdf |
| 2/22/2020 | 3462 | 3462 SMC4-LC-1037 Additional Machine & Manpower Mobilization Document (Tractor, Trailer,Driver ) of Subcontractor Thanh Long JSC - |
| 2/22/2020 | 3463 | 3463 SMC4-AD-152 AD of Pre Tensioning Pre Stressed Super T Girder Span 53 (P52-P53).pdf |
| 2/22/2020 | 3464 | 3464 SMC4-LC-1038 Report on Environment Monitoring in Construction Stage (2nd Time in Feb 2020, Based on S1.43).pdf |
| 2/25/2020 | 3465 | 3465 SMC4-MA-721 Report on Frequency Test of Reinforcing Steel VIS for Super T Girder Span S52 (MoC&TS dated 13 Feb 2020).pdf |
| 2/25/2020 | 3466 | 3466 SMC4-MA-722 Report on Frequency Test of Reinforcing Steel VIS for Super T Girder of Span S33 ( MoC&TS dated 11 Feb 2020).pdf |
| 2/25/2020 | 3467 | 3467 SMC4-AD-153 AD of Pre Tenssioning Pre Stressed Super T Girder Span S54(P53-P54).pdf |
| 2/25/2020 | 3468 | 3468 SMC4-MS-419 Report on Loading Test of Temporary Support TP10 (G1+G2) for Steel Girder Erection.pdf |
| 2/25/2020 | 3469 | 3469 SMC4-WD-519 WD Top Elevation of Parapet & Median Barrier at Spans S54(P53-P54) to S57(P56-P57).pdf |
| 2/25/2020 | 3470 | 3470 SMC4-WD-520 WD of the Elevation & Thickness of Deck Slab at Span S47 (P46-P47).pdf |
| 2/25/2020 | 3471 | 3471 SMC4-WD-521 WD of Substructure -Upper Part of Pier Head P32 (2nd).pdf |
| 2/25/2020 | 3472 | 3472 SMC4-WD-522 WD of Parapet & Median Barrier of Spans P44-P49 (2nd).pdf |
| 2/25/2020 | 3473 | 3473 SMC4-WD-523 WD of Substructure-Elevation of Bearing Pier P43(1st).pdf |
| 2/25/2020 | 3474 | 3474 SMC4-WD-524 WD of Adjustmetn of Exterior Girder EXT1-G1 & EXT1-G10 Span S44 (P43-P44).pdf |
| 2/25/2020 | 3475 | 3475 SMC4-LC-1039 Clarification of Pavement Structure for Approach Road & Urban Road form Km0+320.00-Km0+835.70.pdf |
| 2/25/2020 | 3476 | 3476 SMC4-LC-1040 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Substructure Work for P53.pdf |
| 2/25/2020 | 3477 | 3477 SMC4-MS-420 Report on Loading Test of Temporary Support TP8 ( G1+G2) for Steel Girder Erection.pdf |
| 2/25/2020 | 3478 | 3478 SMC4-MS-421 Submission of Changing Diagonal Bracing Bar at Temporary TP2, TP3(G1+G2).pdf |
| 2/25/2020 | 3479 | 3479 SMC4-LC-1041 Request for Reply of Submitted Documents Regarding Drainage System.pdf |
| 2/25/2020 | 3480 | 3480 SMC4-MS-422 Method Drawing for Erection of Super T Girder at Span S10 (P9-P10)-S12 (P11-P12).pdf |
| 2/25/2020 | 3481 | 3481 SMC4-WD-525 WD of Painting for SCC Deck Slab (2nd).pdf |
| 2/27/2020 | 3482 | 3482 SMC4-MA-670A Notification of Using VIS Steel for Super T Girders of S54.pdf |
| 3/12/2020 | 3483 | 3483 SMC4-WD-526 WD of Removal & Relocation of Trees at Section from Beginning Point to P16 (1st).pdf |
| 2/27/2020 | 3484 | 3484 SMC4-WD-527 WD of Parapet & Median Barrier of Spans at A1-P8.pdf |
| 2/27/2020 | 3485 | 3485 SMC4-WD-528 WD Top Elevation of Parapet & Median Barrier at Span S35 (P34-P35).pdf |
| 2/27/2020 | 3486 | 3486 SMC4-MA-724 Frequency Test of Angle Steel L50x5x5 for SCC Deck Slab - Steel Bridge of Thai Nguyen Iron & Steel JSC ( Sampling |
| 3/2/2020 | 3487 | 3487 SMC4-MA-725 Report on Trial Mix Result Concrete Class C2 at Transmeco BP.pdf |
| 2/27/2020 | 3488 | 3488 SMC4-MA-726 Report on Trial Mix of Concrete Class E at Viet Tiep BP & Proposal for Using Mix Proportion for Construction of PK |
| 2/27/2020 | 3489 | 3489 SMC4-LC-1042 Manpower Mobilization of Subcontractor Hiep An JSC for Painting Work for Concrete Structures on Main Site.pdf |
| 2/27/2020 | 3490 | 3490 SMC4-LC-1043 Cost Estimate for Design Change of Drainage under Viaduct Design Change of Drainage Pipe Culvert D500.pdf |
| 2/27/2020 | 3491 | 3491 SMC4-LC-1044 Proposal to Replacement of Some Pre Tennsionging Pre Stressed Super T Girders of S49 by Girders of the Span S45 f |
| 2/27/2020 | 3492 | 3492 SMC4-LC-1045 Notice of Environmental Monitoring Schedule Mar 2020 at Construction Phase.pdf |
| 2/27/2020 | 3493 | 3493 SMC4-MA-727 Notification on Transfering VGS Steel for the Use of Deck Slab S47.pdf |
| 2/27/2020 | 3494 | 3494 SMC4-MA-728 Testing Result of Waterproofing Material Haseal 5 of Manufacturer Ha An JSC.pdf |
| 2/27/2020 | 3495 | 3495 SMC4-MA-729 Capacity Profile of Supplier New Link for PVC Pipe Material of Manufacturer Thuan Phat JSC (3rd).pdf |
| 3/2/2020 | 3496 | 3496 SMC4-LC-1046 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P51.pdf |
| 3/2/2020 | 3497 | 3497 SMC4-MS-423 Report on Loading Test of Temporary Support TP4 (G1+G2) for Steel Girder Erection.pdf |
| 3/2/2020 | 3498 | 3498 SMC4-LC-1047 Additional Machine & Manpower Mobilization Document (Man Lift Machine) of Thanh Long JSC (2nd).pdf |
| 2/29/2020 | 3499 | 3499 SMC4-MC-27 Resubmit for Interim Payment Certificate No.19 ( Period 01st -31st Jan 2020).pdf |
| 3/2/2020 | 3500 | 3500 SMC4-MS-424 Method Drawing for Erection of Super T Girder at Span S49 (P48-P49).pdf |
| 3/2/2020 | 3501 | 3501 SMC4-MA-730 Report on Frequency Test of Paint for Steel Bridge of Hai Phong Paint JSC ( Sampling dated 11 Feb 2020).pdf |
| 3/2/2020 | 3502 | 3502 SMC4-MA-731 Capacity Profile of Supplier Transport Materials Equipment Trading Transmeco for Steel Material of Manufacturer of |
| 3/2/2020 | 3503 | 3503 SMC4-RP-126 Report on Digging Roots for Survey of the Root’s Elevation & Underground Utilities (From Abutment A1 to Pier P15). |
| 3/2/2020 | 3504 | 3504 SMC4-LC-1049 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P8.pdf |
| 3/2/2020 | 3505 | 3505 SMC4-LC-1048 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P9.pdf |
| 3/2/2020 | 3506 | 3506 SMC4-LC-1050 Acceptance of Sub structure Construction Stage & Transfer to Construction of Superstructure Work for P7.pdf |
| 3/2/2020 | 3507 | 3507 SMC4-LC-1051 Submission Weekly Report No.93.pdf |
| 3/2/2020 | 3508 | 3508 491-GM-BQLDATL Monthly Meeting Thursday 5 Mar 2020.pdf |
| 3/3/2020 | 3509 | 3509 SMC4-MS-426 Report on Loading Test of Temporary Support TP2 (G1+G2) for Steel Girder Erection.pdf |
| 3/3/2020 | 3510 | 3510 SMC4-MS-425 Report on Loading Test of Temporary Support TP3 (G1+G2) for Steel Girder Erection.pdf |
| 3/4/2020 | 3511 | 3511 SMC4-AD-154 AD of Pre Tensioning Pre Stressed Super T Girder Span 49 ( P48-P49).pdf |
| 3/4/2020 | 3512 | 3512 SMC4-LC-1054 Construction Schedule of March- 2020.pdf |
| 3/4/2020 | 3513 | 3513 SMC4-LC-1053 Notice for Leave for Key Personnel (Safety Manager) - MR Thai Binh Duong 16 Mar to 1 Apr 2020.pdf |
| 3/4/2020 | 3514 | 3514 SMC4-LP-70 Proposal for Extension of Advance Payment Security.pdf |
| 3/4/2020 | 3515 | 3515 SMC4-LC-1052 Clarification of the Location of Basement for Traffic Sign Board at Pier P7.pdf |
| 3/4/2020 | 3516 | 3516 505 PMUTL-DA1 Scope of Work on Central Median.pdf |
| 3/4/2020 | 3517 | 3517 SMC4-RP-127 Supplement for Report on Digging Roots Survey of the Root's Elevation & Underground Utilities ( from Abutment A1 t |
| 3/4/2020 | 3518 | 3518 SMC4-WD-529 WD of Miscellaneous -Drainage Layout for Steel Bridge (1st).pdf |
| 3/4/2020 | 3519 | 3519 SMC4-MS-427 Supplement Method Drawing for Super t Girder Erection at Span S12.pdf |
| 3/4/2020 | 3520 | 3520 SMC4-LC-1055 Report on Environment Monitoring in Construction Stage (3rd Time in Feb 2020 Based on S1.42).pdf |
| 3/4/2020 | 3521 | 3521 SMC4-MA-733 Report on Frequency Test of Elastomeric Bearing Manufactured by Kawakin Core Tech VN Co., Ltd & Supplier by THQ Gl |
| 3/6/2020 | 3522 | 3522 SMC4-WD-528A WD of Median Barrier of Spans P53-P57 (1st).pdf |
| 3/13/2020 | 3523 | 3523 SMC4-MS-426A Method Drawing for Construction Layer of Road Work at Exressway from Station Km0+494.22 to Km0+568.04.pdf |
| 3/6/2020 | 3524 | 3524 SMC4-MA-734 Report on Frequency Test of Paint for Steel Bridge of Hai Phong Paint JSC Sampling dated 13 Feb 2020.pdf |
| 3/6/2020 | 3525 | 3525 SMC4-LC-1057 Additional Machine& Manpower Mobilization Document of Subcontractor Hanoi Infrastructure & Culture for Cutting & |
| 3/12/2020 | 3526 | 3526 SMC4-WD-530 Report on Checking Installation of MSE Wall on Left Side & Replacement of the Existing C7L Panel with the New One. |
| 3/6/2020 | 3527 | 3527 SMC4-MA-732 Using Type uPVC D160 to Replace uPVC D150 of Mechanically Stabilized Earth ( MSE) Retaining Wall.pdf |
| 3/6/2020 | 3528 | 3528 SMC4-LC-1056 Notice of Equipment Demobilization Crawler Crane Hitachi KH180-3 at P23-P27 Area Under Scope of 412 Co..pdf |
| 3/6/2020 | 3529 | 3529 SMC4-LC-1058 Notice of Equipment Demobilization- Excavator CAT 320D at P534 Area Under Scope of 423 Co..pdf |
| 3/6/2020 | 3530 | 3530 SMC4-LC-1060 Withdrawal of the letter LC-1053 dated 3 Mar 2020.pdf |
| 3/6/2020 | 3531 | 3531 TEDI Clarification of Pavement Structure Used for the Approach Road & Uban Road from Km0+320.00 to Km-+835.700.pdf |
| 3/7/2020 | 3532 | 3532 SMC4-WD-531 WD of Elevation & Thickness of Deck Slab at Span S54(P53-P54).pdf |
| 3/7/2020 | 3533 | 3533 SMC4-WD-532 WD of Top Elevation of Parapet & Median Barier at Span S40 (P39-P40).pdf |
| 3/7/2020 | 3534 | 3534 SMC4-WD-533 WD of Superstructure -Deck Slab for S43 and Link Slab P43 (1st).pdf |
| 3/7/2020 | 3535 | 3535 SMC4-WD-534 WD of Miscellaneous- Parapet & Median Barrier of Spans P16-P19 (1st).pdf |
| 3/9/2020 | 3536 | 3536 SMC4-MS-428 Supplement the Method Drawing for Super T Girder Erection at Span S11.pdf |
| 3/6/2020 | 3537 | 3537 SMC4-LC-1061 Notice for Leave for Key Personnel ( Safety Manager).pdf |
| 3/7/2020 | 3538 | 3538 SMC4-MA-735 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab S46-S48 , Diaphram Span S45-S49, Parapet S30, S53- |
| 3/7/2020 | 3539 | 3539 SMC4-MA-736 Report on Frequency Test of Reinforing Steel VIS Steel Bar for Super T Girder Span S51, S52 (MoC&TS 25 Feb 2020).p |
| 3/7/2020 | 3540 | 3540 SMC4-MA-737 Report on Frequency Test of Reinforcing Steel VGS Steel for Catch Basin CB-2B Section A1-P10,Section P18-P25,Catc |
| 3/7/2020 | 3541 | 3541 SMC4-MA-738 Report on Frequency Test of Reinforcing Steel VGS for Pier Head P32 & Catch Basin Section P18-P25 ( M0C&TS dated 2 |
| 3/9/2020 | 3542 | 3542 SMC4-LC-1059 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work P44.pdf |
| 3/9/2020 | 3543 | 3543 SMC4-LC-1062 Submission of Weekly Report No.94.pdf |
| 3/9/2020 | 3544 | 3544 SMC4-WD-535 WD of Detail of Noise Barrier (2nd).pdf |
| 3/9/2020 | 3545 | 3545 SMC4-WD-536 WD of General Layout of Noise Barrier (3rd).pdf |
| 3/10/2020 | 3546 | 3546 SMC4-MS-429 Method Drawing for Super T Girder Erection at Span S10.pdf |
| 3/13/2020 | 3547 | 3547 SMC4-MS-430 Method Drawing for Erection of Super T Girder at S52 (P51-P52).pdf |
| 3/11/2020 | 3548 | 3548 SMC4-LC-1063 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work for P51.pdf |
| 3/11/2020 | 3549 | 3549 SMC4-WD-537 WD of Median Barrier of Spans P40-P44.pdf |
| 3/11/2020 | 3550 | 3550 SMC4-WD-538 WD of Painting of Parapet for Main Bridge.pdf |
| 3/11/2020 | 3551 | 3551 SMC4-WD-539 WD of Parapet of Spans P40-P43.pdf |
| 3/13/2020 | 3552 | 3552 SMC4-MA-739 Capacity Profile of Manufacturer & Supplier of Pull Box & U Bolt for Lighting Hai Anh Co.Ltd.pdf |
| 3/27/2020 | 3553 | 3553 SMC4-MS-431 Method Statement of Lighting Base on Median Barrier.pdf |
| 3/12/2020 | 3554 | 3554 SMC4-LT-34 Updated Equipment of Site Laboratory LAS-XD 668 Quality Verification.pdf |
| 3/11/2020 | 3555 | 3555 SMC4-LC-1064 Submission of Monthly Report No.22.pdf |
| 3/12/2020 | 3556 | 3556 SMC4-LC-1065 Documents of Losses Caused by the Happent Incident on 23 Aug 2019 during Construction of CIP Concrete Pile No. C9 |
| 3/11/2020 | 3557 | 3557 SMC4-LC-1066 Notice of Deadline for Starting Production of Noise Barrier.pdf |
| 3/11/2020 | 3558 | 3558 51-PMUTL-DA1 Approval for Subcontractor for Relocation, Cutting & Pruning Trees.pdf |
| 3/12/2020 | 3559 | 3559 SMC4-LC-1067 Acceptance of Sub Structure Constructure Stage & transfer to Construction of Superstructure Work for P9.pdf |
| 3/12/2020 | 3560 | 3560 SMC4-LC-1068 Report on Environment Monitoring in Construction Stage (1st Time in Mar 2020, based on S1.43).pdf |
| 3/12/2020 | 3561 | 3561 SMC4-LC-1069 Withdrawal of the Letter SMC4-LC-1065-20 dated 10 Mar 2020.pdf |
| 3/12/2020 | 3562 | 3562 SMC4-LC-1070 Acceptance of Sub Structure Construction Stage & Transfer to Construction of Superstructure Work for P8.pdf |
| 3/12/2020 | 3563 | 3563 SMC4-LT-35 Updated Document of Independent Laboratories of IBST ( LAS-XD 01, LAS-XD 03, LAS-XD 05).pdf |
| 3/12/2020 | 3564 | 3564 SMC4-WD-540 WD of Detail of Pipe Culvert D500 & Catch Basin Type (CB-A) under Viaduct Section A1-P61.pdf |
| 3/30/2020 | 3565 | 3565 SMC4-WD-541 WD of Detail of Pipe Culvert D400, U-ditch& Catch Basin in the Section of Retaining Wall.pdf |
| 3/30/2020 | 3566 | 3566 SMC4-WD-542 WD of Detail of Catch Basin U-ditch of Drainage System under Viaduct Section A1-P10.pdf |
| 3/12/2020 | 3567 | 3567 SMC4-WD-543 WD of General Layout of Drainage System from Km0+400-Km2+812.50.pdf |
| 3/30/2020 | 3568 | 3568 SMC4-WD-544 WD of Detail for Catch Basin U-ditch of Drainage System under Viaduct Section P18-P25.pdf |
| 3/12/2020 | 3569 | 3569 SMC4-MA-740 Characteristic Strength for Concrete Class A of Viet Tiep BP (New Location) - RP No.7 (from 1 Dec to 31 Dec 2019). |
| 3/12/2020 | 3570 | 3570 SMC4-MA-741 Characteristic Strength for Concrete Class C of Transmeco BP- Rp No.2 (from 3 Jan to 19 Jan 2020).pdf |
| 3/12/2020 | 3571 | 3571 SMC4-MA-742 Characteristic Strength for Concrete Class B of Transmeco BP-RP No.6 (from 3 Jan to 18 Jan 2020).pdf |
| 3/12/2020 | 3572 | 3572 SMC4-AD-155 AD of Substructure of Pier P55.pdf |
| 3/12/2020 | 3573 | 3573 SMC4-AD-156 AD of Substructure of Pier P56.pdf |
| 3/13/2020 | 3574 | 3574 SMC4-RP-128 Report on Completion of Remedial Works for Crack on A1 Abutment's Stem Wall.pdf |
| 3/13/2020 | 3575 | 3575 SMC4-LC-1074 Regarding the Submission of AD for Tranfering Stage of Substructure P7,P8,P9,P44,P51.pdf |
| 3/13/2020 | 3576 | 3576 SMC4-LC-1071 Acceptance of Substructure Construction Stage & Transfer to Construction of Superstructure Work for P7.pdf |
| 3/13/2020 | 3577 | 3577 SMC4-LC-1072 Withdrawal of letter SMC4-LC-1061.20.pdf |
| 3/13/2020 | 3578 | 3578 SMC4-LC-1073 Summary Table of Waste Disposal Implemented by the Subcontractors at Nguyen Khe Disposal Area from Oct to Dec 201 |
| 3/14/2020 | 3579 | 3579 SMC4-MA-744 Electrical Material- Luminaires.pdf |
| 3/13/2020 | 3580 | 3580 SMC4-MS-432 Erection Method of Deck Panel for Steel Bridge.pdf |
| 3/14/2020 | 3581 | 3581 SMC4-AD-157 AD of Pre Tensioning Pre Stressed Super T Girder of Span 9 (P8-P9).pdf |
| 3/13/2020 | 3582 | 3582 SMC4-AD-158 AD of Pre Tensioning Pre Stressed Super T Girder Span S52 (P51-P52).pdf |
| 3/13/2020 | 3583 | 3583 SMC4-MA-745 Report on Frequency Test of VGS to Use for Diaphragm S53L-S56L, Parapet P41R-P45R (the MoC&TS dated 29 Feb 2020).p |
| 3/13/2020 | 3584 | 3584 SMC4-MA-746 Report on Frequency Test of VGS to Use for Deck Slab S53-S54, Link Slab P54 (the MoC&TS dated 3 Mar 2020).pdf |
| 3/13/2020 | 3585 | 3585 SMC4-MA-747 Report on Frequency Test of VGS to Use for Deck Slab & Diaphragm S54-S61, Link Slab P53-P61 ( the MoC&TS dated 3 M |
| 3/13/2020 | 3586 | 3586 SMC4-MA-748 Report on Frequency Test of VIS to Use for Super T Girder Span S32,S49 ( the MoC&TS dated 6 Mar 2020).pdf |
| 3/16/2020 | 3587 | 3587 320 PMUTL-DA1 Design Change of Drainage under Viaduct.pdf |
| 3/16/2020 | 3588 | 3588 SMC4-MA-743 Report on Test Result of Deck Drain Box, Trash Rack Material Manufactured by Tran Duc Hung Co.Ltd & Supplied by H |
| 3/13/2020 | 3589 | 3589 SMC4-LC-1076 Submission of Weekly Report No.95.pdf |
| 3/13/2020 | 3590 | 3590 SMC4-LC-1075 Confirmation for Safety & Environment Satisfaction (1 to 29 Feb 2020.pdf |
| 3/13/2020 | 3591 | 3591 SMC4-MS-433 Method Drawing for Erection of Super T Girder at Span S9 (P8-P9).pdf |
| 3/13/2020 | 3592 | 3592 SMC4-MA-434 Calculation of Tendon Cable Elongation of Pier Head P32.pdf |
| 3/13/2020 | 3593 | 3593 SMC4-WD-545 WD of Elevation & Thickness Deck Slab at Span S43 (P42-P43), S48 (P47-P48), S53 (P52-P53).pdf |
| 3/13/2020 | 3594 | 3594 SMC4-MA-749 Updated Profile of Noise Barrier of Nippon Supplied by Nam Anh (3rd).pdf |
| 3/13/2020 | 3595 | 3595 SMC4-MA-750 Report on Frequency Test of Materials for Cement Concrete at Transmeco BP(57th).pdf |
| 3/13/2020 | 3596 | 3596 SMC4-MA-751 Report on Frequency Test of Materials for Cement Concrete at Viet Tiep BP (26th,27th) & Updated Result Cement R28 |
| 3/16/2020 | 3597 | 3597 SMC4-WD-546 Calculation Sheet for Camber of Steel Girder (2nd Rev.).pdf |
| 3/16/2020 | 3598 | 3598 SMC4-AD-159 AD of Pre Tensioning Pre Stressed Super T Girder of Span 8 (P7-P8).pdf |
| 3/16/2020 | 3599 | 3599 SMC4-MA-752 Test Result of Stainless Steel Bolt (SUS 304) Material of Tongheer Fassterners Co.SND.BHD (Malaysia).pdf |
| 3/16/2020 | 3600 | 3600 SMC4-MA-753 Report on Frequency Test Paint for Steel Bridge of Hai Phong JSC (Sampling dated 25 Feb 2020).pdf |
| 3/16/2020 | 3601 | 3601 SMC4-MA-754 Notification on Transfering VGS Steel for the Use of Diaphragm S43, Link Slab at Pier P51,P52.pdf |
| 3/16/2020 | 3602 | 3602 SMC4-MA-755 Notification on Transfering VGS Steel for the Use off Deck lab, Diaphragm S12.pdf |
| 3/16/2020 | 3603 | 3603 SMC4-MA-756 Notification on Transfering VIS Steel for the Use of Super T Girder off G10- Span S44 of 414 Co.Ltd.pdf |
| 3/16/2020 | 3604 | 3604 SMC4-LC-1077 Mobilization Document of Bolt Tension Meter.pdf |
| 3/16/2020 | 3605 | 3605 SMC4-LC-1078 Reply on Engineer's Warning about Construction Quality of Drainage Pipe Culvert.pdf |
| 3/16/2020 | 3606 | 3606 611 TB-BQLDATL Notice on Conclusions given by PMU Thang Long in the Meeting.pdf |
| 3/16/2020 | 3607 | 3607 95 TB-BGTVT Notice on Conclusions given by Vice Minister Nguyen Ngoc Dong in the Site Visit(n).pdf |
| 3/17/2020 | 3608 | 3608 SMC4-MA-757 Freqquency Test of Stud Bolts of Hanzhou Jiaxiang Gaogiang Bolts Co. Ltd & Welding Procedure for Steel Bridge.pdf |
| 3/17/2020 | 3609 | 3609 SMC4-MA-758 Frequency Test of Shear Stud Connector for Steel Bridge Taking Sample dated 2 Mar 2020.pdf |
| 3/17/2020 | 3610 | 3610 SMC4-MA-759 Testing Result of Bolt Used for Lighting Pole Vonta Co.Ltd.pdf |
| 3/17/2020 | 3611 | 3611 SMC4-MS-435 Supplement of Sequence for Construction of Pier Head at P16, P19.pdf |
| 3/17/2020 | 3612 | 3612 SMC4-WD-547 WD of Parapet of Spans P53-P57 (1st).pdf |
| 3/17/2020 | 3613 | 3613 SMC4-WD-548 WD of Parapet of Spans P49-P53 (1st).pdf |
| 3/17/2020 | 3614 | 3614 SMC4-WD -549 WD of Median Barrier of Spans P49-P53 (1st).pdf |
| 3/17/2020 | 3615 | 3615 SMC4-LC-1079 Concrete Compressive Strength Testing R7 of Super T Girder of Span S52.pdf |
| 3/18/2020 | 3616 | 3616 SMC4-LC-1080 Submission of Weekly Report No.96.pdf |
| 3/18/2020 | 3617 | 3617 SMC4-LC-1081 Document for Mobilization of Subcontractor Thanh Long Group JSC for Construction of Steel Bridge.pdf |
| 3/18/2020 | 3618 | 3618 SMC4-LC-1082 Contractor's Clarification on Choise of Anchor Bolt for Noise Barriers.pdf |
| 3/18/2020 | 3619 | 3619 SMC4-AD-160 AD of Pre Tensioning Pre Stressed Super T Girder of Span 7 (A1-P7).pdf |
| 3/19/2020 | 3620 | 3620 SMC4-WD-550 WD of Electric & Lighting - Conduit Layout of Electric Lighting & ITS System for Expressway (1st).pdf |
| 3/19/2020 | 3621 | 3621 SMC4-MA-760 Notification on Transfering VIS Steel for the Use of Super T Girder G7- Span S32 of 422 Co..pdf |
| 3/19/2020 | 3622 | 3622 SMC4-LC-1083 Machine & Manpower Mobilization Document for Finishing Work of Structure at Project.pdf |
| 3/19/2020 | 3623 | 3623 SMC4-MS-436 Document of Reconnecting Culvert Pipe D1250 of Ministry of Police Sercurity ( 1st).pdf |
| 3/30/2020 | 3624 | 3624 SMC4-LC-1084 Respond to Galvanized Bolts Delivered at Factory for the Steel Bridge.pdf |
| 3/24/2020 | 3625 | 3625 SMC4-MA-761 Approval of Electrical Material- Luminaires( Slighting ... JSC).pdf |
| 3/19/2020 | 3626 | 3626 SMC4-LC-1085 Construction Plan of Drainage under Viaduct and Site Hand over plan.pdf |
| 3/20/2020 | 3627 | 3627 SMC4-LC-1086 Mobilization Document of Subcontractor Thanh Long Group JSC for Construction of Steel Bridge.pdf |
| 3/20/2020 | 3628 | 3628 SMC4-LC-1088 Withdrawal of the Letter SMC4-MS-0436 dated 18Mar2020.pdf |
| 3/28/2020 | 3629 | 3629 SMC4-WD-551 WD of Detail for Catch Basin U-Ditch of Drainage System under Viaduct Section P42-P49.pdf |
| 3/20/2020 | 3630 | 3630 SMC4-WD-552 WD of Miscellaneus- Parapet of Spans P8-P11 (1st).pdf |
| 3/20/2020 | 3631 | 3631 SMC4-WD-553 WD of Miscellaneous-Median Barrier of Span P44-P49 (1st).pdf |
| 3/20/2020 | 3632 | 3632 SMC4-WD-554 WD of Detail for Catch Basin U Ditch of Drainage System under Viaduct Section P11-P17.pdf |
| 3/20/2020 | 3633 | 3633 SMC4-MC-28 Application for Interim Payment Certificate No. 20 ( Period 1-29 Feb 2020).pdf |
| 3/20/2020 | 3634 | 3634 SMC4-LC-1087 Acceptance of Sub Structure Constructure Stage & Transfer to Construction of Superstructure Work for P44.pdf |
| 3/21/2020 | 3635 | 3635 SMC4-WD-557 WD of Electric & Lighting Equipment & Facilities of Electruc for Lighting & ITS System for Expressaway (1st).pdf |
| 3/21/2020 | 3636 | 3636 SMC4-WD-556 WD of Antiglare Fence from A1-P61.pdf |
| 3/21/2020 | 3637 | 3637 SMC4-WD-555 WD of Elevation & Thickness of Deck Slab S11(P10-P11), S12(P11-P12).pdf |
| 3/21/2020 | 3638 | 3638 SMC4-LC-1089 Additional Machine & Manpower Mobilization Document(1 Crane 220Ton) of Subcontractor Thanh Long JSC for Erection |
| 3/21/2020 | 3639 | 3639 SMC4-LC-1090 TOR & Cost Estimate for General Traffic Control for Public Road for Construction Stage 2.pdf |
| 3/23/2020 | 3640 | 3640 SMC4-MS-437 Resubmission of Erection Method of Deck Panel for Steel Bridge (2nd).pdf |
| 3/23/2020 | 3641 | 3641 SMC4-LC-1092 Supplement of As-built Documents for Substructure P29, P30.pdf |
| 3/23/2020 | 3642 | 3642 SMC4-WD-558 WD of Miscellaneous-Parapet of Spans P44-P49 (1st).pdf |
| 3/23/2020 | 3643 | 3643 SMC4-MA-762 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab Span S9,P10,P12-Diaphragm S9,S10-S12,S16- Parapet |
| 3/23/2020 | 3644 | 3644 SMC4-MA-763 Report on Frequency Test of Stud Bolt Hangzhou Jiaxiang Gaoqiang Boilts Co.Ltd (Sampling dated 7 Mar 2020).pdf |
| 3/30/2020 | 3645 | 3645 SMC4-MA-764 Report on Frequency Test of Bolt Material for Steel Bridge S10T (including Nut & Washer) Taking Sample dated 7 Mar |
| 3/23/2020 | 3646 | 3646 SMC4-MA-765 Report on Frequency Test of Paint for Steel Bridge of Hai Phong Paint JSC (Sample dated 7 Mar 2020).pdf |
| 3/23/2020 | 3647 | 3647 SMC4-MS-438 Structure Calculation Sheet for Erection Method of Deck Panel for Steel Bridge (1st).pdf |
| 3/23/2020 | 3648 | 3648 SMC4-LC-1091 Additional Supervision Cost of Engineer's Staff in Jan2020.pdf |
| 3/24/2020 | 3649 | 3649 SMC4-MS-439 Resubmission of the Supplement of Sequence for Construction of Pier Head at P16, P19 (rev.2).pdf |
| 3/23/2020 | 3650 | 3650 SMC4-1093 Construction Plan of Drainage under Viaduct & Site Hand Over Plan ( Rev.1).pdf |
| 3/24/2020 | 3651 | 3651 SMC4-MA-766 Report on Frequency Test of Material for Cement Concrete at Asean BP (31st) & Updated Result of Cement R28 (30th). |
| 3/25/2020 | 3652 | 3652 SMC4-MA-767 Testing Result of Paraweb Strip Material.pdf |
| 3/25/2020 | 3653 | 3653 SMC4-MA-768 Proposal to Use Concrete Class D - 25MPa ( Ha Thanh) to Change Concrete Class E - 21 MPa for RC in Ha Thanh.pdf |
| 3/25/2020 | 3654 | 3654 SMC4-MA-769 Mix Proporation for Trial Mix Class C2 at Asean BP.pdf |
| 3/25/2020 | 3655 | 3655 SMC4-MA-770 Report on Frequency Test of Material for Reinforced Concrete Structure Manufactured in Ha Thanh.pdf |
| 3/30/2020 | 3656 | 3656 SMC4-MA-771 Report on Frequency Test of Shear Stud Connector for Steel Bridge ( Taking Sample dated 14 Mar 2020).pdf |
| 3/25/2020 | 3657 | 3657 SMC4-MA-772 Test Result of Hot Dipped Galvanized Bolts by KPF Vina ( Boils)& Anh Duong JSC (Nut& Washer) & Supplied by Tan Co |
| 3/25/2020 | 3658 | 3658 SMC4-MA-773 Capacity Profile of Manufacturer & Supplie of Mechanical Product Material- Hai Anh Co.Ltd.pdf |
| 3/25/2020 | 3659 | 3659 SMC4-WD-559 WD the Top Elevation of Parapet & Median Barrier at Span S41 (P40-P41).pdf |
| 3/25/2020 | 3660 | 3660 SMC4-WD-560 WD of Superstructure- Deck Slab for Span 33.pdf |
| 3/25/2020 | 3661 | 3661 SMC4-WD-561 WD of Superstructure - Deck Slab for Span 44.pdf |
| 3/25/2020 | 3662 | 3662 SMC4-MS-440 MS for Erection of Super T Girder S44 (P43-P44), S45 (P44-P45).pdf |
| 3/25/2020 | 3663 | 3663 SMC4-AD-161 AD ofPre Tensioning Pre Stressed Super T Girder Span 45 (P44-P45).pdf |
| 3/25/2020 | 3664 | 3664 SMC4-LC-1094 Submission of Weekly Report No.97.pdf |
| 3/25/2020 | 3665 | 3665 SMC4-LC-1095 Supplement of AD for Substructure Pier P23-26, P28, P38.pdf |
| 3/25/2020 | 3666 | 3666 SMC4-LC-1096 Document Status for WD of Parapet& Center Median.pdf |
| 3/25/2020 | 3667 | 3667 SMC4-LC-1097 Notice of Equipment Demobilization of Crane Kobelco 7055 for Construction of Substructure Under Score of Co.423.p |
| 3/25/2020 | 3668 | 3668 SMC4-AD-162 AD of Pre Tensioning Pre Stressed Super T Girder Span 44 (P43-P44).pdf |
| 3/26/2020 | 3669 | 3669 SMC4-LC-1098 Report on Environment Monitoring in Construction Stage 2nd time in March 2020 (base on S1.43).pdf |
| 3/26/2020 | 3670 | 3670 SMC4-MA-774 Supplement of Capacity Profile of Electrical Material of Vestel Trade Co.& Osram- Luminaires.pdf |
| 3/26/2020 | 3671 | 3671 SMC4-WD-562 WD of Miscellaneous- Detail of Road Marking on Expressway.pdf |
| 3/26/2020 | 3672 | 3672 SMC4-WD-563 WD of Median Barrier of Spans A1-P8 (1st).pdf |
| 3/26/2020 | 3673 | 3673 SMC4-WD-564 WD of Median Barrier of Spans P8-P11 (1st).pdf |
| 3/26/2020 | 3674 | 3674 SMC4-WD-565 WD of Parapet of Spans A1-P8 (1st).pdf |
| 3/27/2020 | 3675 | 3675 SMC4-MA-775 Report on Frequency Test of Reinforcing Steel VGS for Parapet of Span S47-S61 ( MoC & TS dated 15 Mar 2020).pdf |
| 3/27/2020 | 3676 | 3676 SMC4-MA-776 Report on Frequency Test of Reinforcing Steel VIS Bar for Super T Girder Span S51 (M0C& TS dated 18 Mar 2020).pdf |
| 3/28/2020 | 3677 | 3677 SMC4-MA-777 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab S46-S49 ( MoC& TS dated 17 Mar 2020).pdf |
| 3/26/2020 | 3678 | 3678 SMC4-MA-778 Report on Frequency Test of Reinforcing Steel VGS for Deck Slab & Parapet S43R,S44R,S45R-Link Slab P42R,P43R-Diaph |
| 3/26/2020 | 3679 | 3679 SMC4-MA-779 Updated Capacity Profile of Electrical Cable & Ground Wire Material of Thuong Dinh Electrical Wire & Cable JSC.pdf |
| 3/27/2020 | 3680 | 3680 SMC4-MA-780 Updated Capacity Profile of Supplier, Manufacturer Bitumen, Bitumen Emulsion Used for Asphalt Concrete.pdf |
| 3/26/2020 | 3681 | 3681 SMC4-WD-566 WD of the Elevation & Thickness of Deck Slab at Spans S49 (P48-P49), S52 (P51-P52).pdf |
| 3/31/2020 | 3682 | 3682 SMC4-WD-567 WD of Detail for Catch Basin Uditch of Drainage System under Viaduct Section P35-P41.pdf |
| 3/27/2020 | 3683 | 3683 SMC4-WD-568 WD of Miscellaneous-General Layout of Signboard & Road Marking on the Expressway.pdf |
| 3/27/2020 | 3684 | 3684 SMC4-RP-129 Report on Updated Data of Topographic Survey Pham Van Dong Street at Section From Km0+440 to Km0+494.22.pdf |
| 3/27/2020 | 3685 | 3685 SMC4-LC-1099 Notice of Environment Monitoring Schedule in Apr 2020 at Construction Phase.pdf |
| 3/27/2020 | 3686 | 3686 SMC4-LC-1100 Supplement of AD for Substructures P27, P36, P37,P57.pdf |
| 3/27/2020 | 3687 | 3687 SMC4-LC-1101 Notice of Equipment Demobilization- Crawler Crane Hitachi KH 180-3 & Drilling Machine Kobelco 7055 R10 under Scop |
| 3/28/2020 | 3688 | 3688 SMC4-MC-29 Resubmit for Interim Payment Certificate No.20 ( Period 1-29 Feb 2020).pdf |
| 3/31/2020 | 3689 | 3689 SMC4-MA-783 Report on Frequency Test of Reinforcing Steel VIS for Super T Girder of Span S33, Uditch (MoC&TS dated 17 Mar 2020 |
| 3/31/2020 | 3690 | 3690 SMC4-MA-781 Report on Frequency Test of Galvanized Bolt Material & Galvanized Nut & Washer Used for Steel Bridge ( Sampling da |
| 3/30/2020 | 3691 | 3691 SMC4-MS-441 MS for Construction of Deck Drainage System.pdf |
| 3/30/2020 | 3692 | 3692 SMC4-MS-442 MS of Painting of Concrete Surface of Parapet, SPT Girder & Retaining Wall.pdf |
| 3/30/2020 | 3693 | 3693 SMC4-LC-1102 Notice on Isolation of 2 Staffs & Prevention Methods Against COVID19 of the Contractor.pdf |
| 3/30/2020 | 3694 | 3694 SMC4-WD-569 WD of Parapet of Spans P40-P43 (2nd).pdf |
| 3/30/2020 | 3695 | 3695 SMC4-WD-570 WD of Elevation & Thickness of Deck Slab at Spans S16 (P15-P16), S20 (P19-P20).pdf |
| 3/30/2020 | 3696 | 3696 SMC4-AD-163 As Built Drawings of Pre Tensioning Pre Stressed Super T Girder Span 44 ( P43-P44).pdf |
| 3/30/2020 | 3697 | 3697 SMC4-LC-1103 Supplement for Construction Plan of Drainage Under Viaduct & Site Hand over Plan ( Rev.1).pdf |
| 3/30/2020 | 3698 | 3698 SMC4-LC-1104 Supplement of AD for Substructure Pier P21, P22, P59, P60.pdf |
| 3/30/2020 | 3699 | 3699 SMC4-LC-1105 Report on Phenomenon of Gaps Under Elastomeric Bearings & Treatment Method (3rd).pdf |
| 3/30/2020 | 3700 | 3700 SMC4-MA-785 Material- Reinforced Concrete Pipes D1250, Precast Bearing D1250 Used for Drainage System- Ha Thanh Concrete JSC.p |
| 11/23/2017 | 11A | 11A 2107-PMUTL-DA1 Approval for Replacement of project Manager.pdf |
| 11/23/2017 | 11A | 11A-2107-PMUTL-DA1 Approval for Replacement of project Manager.pdf |